Loading...
Item 4FITEM 4F Authorize a professional services agreement for engineering design services for segments B, C, D and E of the North Water Supply Pipeline Project with Freese and Nichols, Inc. in the amount of $522,070 Background February , 2007 – Awarded Route Study Yielded 2 possible alignments Preferred Route – Proposed FM 1938 route Background Segments A and F – Construction contract awarded to Circle C Construction on February 3, 2009 by City Council Survey and Engineering work on Segments B, C, D, and E can begin Need for water line by 2012 to serve Southlake Background 7,500 L.F. – Segments A and F (construction awarded) 19,500 L.F. – Segments B, C, D, and E 2,000 L.F. - Segment D-Prime (D’) 29,000 L.F. – Total Project Length Segment B Location Map Segment C Location Map Segment D Location Map Segment E Location Map Proposed Contract EXPENSES: Basic Services - $ 340,370 Special Services – $ 181,700 Total contract amount - $ 522,070 FUNDING: Unallocated available funds $ 1,954,160 Questions?