Loading...
ITEM 4CITEM 4C Award construction contract for segments A and F of the T.W. King 30 inch water supply line to Circle C Construction, Ltd., in the amount of $2,635,235 and authorize construction phase contingencies Segment A Location Map Segment F Location Map T.W. King 30 Inch Water Supply Line Segments A and F Contractor – Circle C Construction Engineer recommends low bidder Total Bid $2,635,235 Construction Phase Contingency - 263,565 Project Budget $2,898,800 T.W. King 30 Inch Water Supply Line Segments A and F Total bid amount $2,635,235 Construction contingency 263,565 A & F construction budget $2,898,800 Current CIP budget $8,754,230 A & F construction budget 2,898,800 Remainder CIP budget $5,855,430 Recommendation Award construction contract for segments A and F of the T.W. King 30 inch water supply line to Circle C Construction, Ltd., in the amount of $2,635,235 and authorize construction phase contingencies Questions?