Item 9AItem 9A
Award contract to Triple D, Inc. in the amount of $371,460.00 for the replacement of three high pressure plane pumps at Southlake Pearson Pump Station
High Pressure Plane Pump Replacement
Purpose:
The three pumps serving the high pressure plane are not properly matched to the operating characteristics of the system
Specifications for new equipment matching the water system were advertised in December 2008
Five bids were received on December 16th
High Pressure Plane Pump Replacement
Process:
Triple D, Inc. offered the lowest bid for the pump replacement project at $371,460
The project contract provides for a completion date not later than June 1, 2009Five bids were received on December 16th
High Pressure Plane Pump Replacement
Funding:
Funds are available from the following sources:
FY 09 Operating budget for the Water Division - $314,000 for Pump Replacement
FY 09 Operating budget for the Water Division - $57,460 for Fence Replacement at Dove Elevated Storage Tank
High Pressure Plane Pump Replacement
RECOMMENDATION:
Award contract to Triple D, Inc. in the amount of $371,460.00 for the replacement of three high pressure plane pumps at Southlake Pearson Pump Station