Item 3B2 - CIP ReportITEM 3B - 2
MAY 2026
II
The information in this report is updated as of April 30, 2026.
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City’s progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description – A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status – A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase – Indicates the current phase of the project.
• Overall Progress (Current Phase) – Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget – The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding: The amount of funding currently planned for future fiscal years. Typicially
these will be an estimate based on the design.
• Budget Adherence – Shows whether the project is currently under budget, on target, or over
budget.
• Project Update – Gives a short summary of progress since the end of the previous month,
highlighting major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department / Engineering Firm / General Contractor – Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
MAY 2026 | 1CIP REPORT
DOVE SIDEWALK PHASE 1
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
to staff in early March. Prior to construction, staff will coordinate with affected residents, submit plans to
Texas Department of Licensing and Regulation (TDLR) for regulatory review, and obtain a construction
estimate from the City’s concrete contractor, Apex Concrete Construction, Inc. Construction is
anticipated to begin this summer. Apex’s contract with the City covers the scope of work for this project
and was already competitively bid. Utilizing Apex’s contract for this work will greatly expedite this
project and allow the City to provide amenities requested by the community.
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane
CIP Project Number: 2022-02
Project Status: On Hold
Project Phase: Pre-Design
Overall Progress (Current Phase): 98%
CIP Funding Source(s): General Fund
Adopted Budget: $505,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
Project Update: Final schematic design was provided
FM 1709 & PEARSON INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
Pearson.
CIP Project Number: 2022-13c
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller
Adopted Budget: $960,000
Future Planned Funding: $2,440,000 (Estimate)
MAY 2026 | 2CIP REPORT
FM 1709 DECELERATION LANES AT BYRON NELSON AND SOUTHRIDGE LAKES
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: EARTC
Project Update: The project is now complete. Staff and the contractor met with TxDOT on May 7,
2026 for a final walkthrough, and TxDOT approved the completed work. A 30-day testing period will
now occur to confirm the intersection signals are operating properly with TxDOT’s system, which also
effectively starts the two-year warranty period under the City’s contract. The punch-list items were
completed by the City’s contractor under an existing agreement for another project. This is the final
month that this project will be included in this report.
Project Description: Adds deceleration lanes at Byron
Nelson Parkway and Southridge Lakes Parkway with
enhanced landscaping.
CIP Project Number: 2022-06
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund
Adopted Budget: $1,200,000
Future Planned Funding: $0
Budget Adherence: Under Budget
FM 1938 & CONTINENTAL BLVD. INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Union Church Road re-opened ahead of schedule on March 31st, all roadway and culvert
improvements on Union Church Road have been completed. Work outside the pavement will continue
through May, including the sidewalk extension along Union Church Road. Traffic signal improvements
are ongoing, and roadway improvement focus is now on the W Continental Blvd side of the intersection.
Construction on that side has begun and traffic control for the Davis Blvd deceleration lane and
improvements to the southside of Continental are currently expected to be complete by the end of May.
Franchise utilities conflicts that the team are aware of have been cleared.
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental
Intersection Improvements.
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 54%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Tarrant County Bond
Adopted Budget: $8,900,000
MAY 2026 | 3CIP REPORT
MUSTANG COURT INDUSTRIAL AREA ACCESS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: The 60% design has been completed. The City’s consultant is currently conducting ROW
acquisition discussions with adjacent property owners. Discussions are also being conducted with the
utility companies regarding relocation of existing facilities. The consultant will proceed with designing to
90% while the ROW discussions are continuing. Once the ROW is acquired and the design is completed,
the project will be let out for bid.
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $1,975,000
Future Planned Funding: $5,050,000 (Estimate)
Budget Adherence: On Target
N. CARROLL AVE. CORRIDOR
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
Project Update: Construction on the Carroll Avenue Mobility Improvements Project remains substantially
complete. Remaining work is limited to final traffic signal- and sign-related items, including signal cabinet
replacement at the SH 114 and N. Carroll Avenue intersection to accommodate the upgraded detection
equipment. Staff is coordinating the remaining work with TxDOT and the contractor, and project
completion is anticipated by Summer 2026.
Project Description: Improves the corridor with
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund
Adopted Budget: $2,070,000
Future Planned Funding: $0
Budget Adherence: On Target
MAY 2026 | 4CIP REPORT
RANDOL MILL WATER AND SIDEWALK IMPROVEMENTS
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
Budget Adherence: On Target
Project Update: Waterline improvements and franchise utility relocations are complete, with utility
relocations completed in February and waterline work completed in March. Residents have been
connected to the new 12-inch water line, temporary lines have been removed and concrete work began
in March. Construction of side street approaches, curb, driveways, and sidewalk are underway. The
contractor is currently working towards a substantial project completion by the end of May.
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements.
CIP Project Number: 2022-33c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 51%
CIP Funding Source(s): General Fund, Utility Fund,
Water Impact Fee Fund
Adopted Budget: $3,400,000
Future Planned Funding: $0
S. PEYTONVILLE & W. CONTINENTAL INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Adopted Budget: $6,185,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: No major changes since last update. This project is a companion to the FM1938 and
Continental Boulevard intersection improvements. The contract was awarded to McMahon Contracting
late May 2025, and work on this phase will not begin until the substantial completion of the companion
project to minimize mobility impacts. The anticipated start is approximately 18 months after the FM1938
and Continental phase begins, estimated to be no later than April 2027.
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard
and South Peytonville Avenue intersection. This project
is a companion project to FM 1938 & Continental Blvd.
Intersection Improvements.
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): General Fund, Utility Fund,
Roadway Impact Fee Fund, Storm Water Utility System,
Tarrant County Bond
MAY 2026 | 5CIP REPORT
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 2
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Central North Construction LLC
Project Update: Phase 2 construction continues to progress well on the North side of the Dove and 114
intersection. The project should be completed later this month and will then move into the warranty
phase later this spring.
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $400,000
Future Planned Funding: $0
Budget Adherence: On Target
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 3
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: Phase 3 was awarded the full $420,000 to begin work at the intersection of White
Chapel and SH 114. City staff are working with the design consultant and TxDOT on phase 3 of this
project and have conducted a project kick-off and preliminary design work. City Council authorized the
City Manager to enter into an advance funding agreement for this project at the December 2nd Council
meeting and staff are working with the consultant on design with a planned letting date for Summer of
2026.
Project Description: Enhances intersections on SH 114
with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 75%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $420,000
Future Planned Funding: $0
Budget Adherence: On Target
MAY 2026 | 6CIP REPORT
1938 MEDIAN LANDSCAPING
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: This project involves the construction of a raised concrete median from FM 1709 in
Southlake, through Keller and into North Richland Hills. The City aims to partner with TxDOT to include
landscape improvements on the new medians. The City consultant completed the 95% design, and
it is now under review by TxDOT and the City. TxDOT is currently coordinating its work around the
intersection improvements of FM 1938 at Continental Blvd. It is anticipated that work for the TxDOT
portion of the project completed by Summer 2026 and that the landscape improvements will be
constructed in a later phase of the project.
Project Description: Constructs landscape,
irrigation, and hardscape improvements on
FM 1938 from FM 1709 to the Southlake City
limits, consistent with landscaped median
improvements north of FM 1709. The City’s
scope includes landscape, irrigation, and
hardscape only.
CIP Project Number: 2024-06
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund
Adopted Budget: $1,650,000
Future Planned Funding: $0
Budget Adherence: On Target
MUNICIPAL SERVICE CENTER AND PUBLIC SAFETY TRAINING TOWER
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
Project Update: Construction now focuses on the vertical structures. The Service Bay Building framing and
roofing are complete. Work is proceeding to the installation of siding and interior electrical, mechanical,
and plumbing rough-in. At the Administration Building, tilt wall construction is underway and the vertical
positioning of the panels is expected over the next month. At the Public Safety Training Tower, foundation
work is being prepared. The project remains on schedule and aligned with the established construction
timeline.
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 56%
CIP Funding Source(s): General Fund and Utility Fund
Adopted Budget: $46,600,000
Future Planned Funding: $0
Budget Adherence: On Target
MAY 2026 | 7CIP REPORT
TOWN HALL PLAZA PARK
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Adopted Budget: $7,938,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The consultant is completing the 30% design. A two-step procurement process has
begin to find a CMAR for the project. Qualifications of prospective candidates are being reviewed to
prequalify firms to participate in the second phase of procurement. Over the next month and a half, the
most qualified CMAR candidates will participate in the RFP process to provide preconstruction services
for this project.
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Southlake Parks Development
Corporation
TURF REPLACEMENT PHASE II (NORTH PARK)
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: Not Awarded Yet
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The project is currently out for bidding. Bids are scheduled to be opened at the end of
May and award of the construction contract is anticipated to be brought to City Council in June.
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Bidding
Overall Progress (Current Phase): 25%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $5,673,000
MAY 2026 | 8CIP REPORT
TURF REPLACEMENT PROJECT
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: GeoSurfaces
Adopted Budget: $12,015,000
Future Planned Funding: $0
Budget Adherence: Under Budget
Project Update: Contractor is completing final punch list items relative to the completing work on the
turf fields (Fields 5 & 6) at Bicentennial Park. Fields are available for use by Dragon Youth Baseball. This
is the final month that this project will be included in this report.
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at Bob Jones
Park and Bicentennial Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund, Utility Fund, and
Crime Control Prevention District
BIG BEAR CREEK IMPROVEMENTS NEAR TIMBER COURT
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 59%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $135,000
Future Planned Funding: $620,000 (Estimate)
Budget Adherence: Under Budget
MAY 2026 | 9CIP REPORT
E HIGHLAND/KIMBALL 8” SEWER LINE
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Future Planned Funding: $2,395,000 (Estimate)
Budget Adherence: Under Budget
Project Update: Coordination with property owners for required easements is expected to restart late
spring. Initial offers were sent to four of the five property owners, with discussions held with three;
the fourth property was in transition when the offer was sent, and the fifth remains under legal review
regarding prescriptive right-of-way. Meetings were held in January and February to discuss continuation
of the project and to kick off coordination between City staff and TNP’s acquisition team. TNP has
provided updated acquisition letters, which are currently under staff review and will be used to resume
negotiations. Field data was collected in early March to support finalization of design, and depending
on negotiation outcomes, alternative alignments may be considered as the project advances toward
anticipated construction in summer 2027.
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue.
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 63%
CIP Funding Source(s): Sanitary Sewer Impact Fee,
Utility Fund
Adopted Budget: $245,000
EAGLE BEND & STRATHMORE SANITARY SEWER RECONSTRUCTION
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Design reached 90 percent completion in July 2024, and property owner coordination for easements is
ongoing. One of the three permanent easements has been acquired, while agreements with the Timarron
HOA and Golf Course remain under legal review. A required temporary easement has not yet been
secured. The project is on hold due to reprioritization and will resume as other projects conclude.
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76%
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000
Future Planned Funding: $820,000 (Estimate)
Budget Adherence: Under Budget
Project Update: No major changes since last update.
MAY 2026 | 10CIP REPORT
HIGGINS BRANCH NEAR WOODBROOK LN
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Coordination with property owners regarding
access easements is ongoing. Two temporary easements have been acquired, while one permanent
access easement remains under legal review. The project is on hold due to reprioritization and will
resume as other projects are completed.
Project Description: Provides erosion control and
sewer protection improvements along Higgins Branch
near Woodbrook Lane.
CIP Project Number: 2022-45c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 73%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $185,000
Future Planned Funding: $525,000 (Estimate)
Budget Adherence: Under Budget
JONES BRANCH NEAR RAINTREE DR.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Project Update: Staff completed review of the consultant’s proposed scope and fee for the Jones
Branch Infrastructure Related Stabilization Project and is currently coordinating comments and revisions
with the project consultant. Staff is targeting completion of the Engineering Services Agreement for
award at the June 16 council meeting to allow design activities to proceed.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 80%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $158,000
Future Planned Funding: $975,000 (Estimate)
Budget Adherence: On Target
MAY 2026 | 11CIP REPORT
JONES BRANCH NEAR SIMMONS CT
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Project Update: Staff completed review of the consultant’s proposed scope and fee for the Jones
Branch Infrastructure Related Stabilization Project and is currently coordinating comments and revisions
with the project consultant. Staff is targeting completion of the Engineering Services Agreement for
award at the June 16 Council meeting to allow design activities to proceed.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $885,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
LONESOME DOVE/SHADY LANE LIFT STATION IMPROVEMENTS
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
Project Update: Since the previous update, the contactor has submitted revised cost change proposals
and updated pay application documentation for review. Staff is coordinating the contractor, design
consultant, and Public Works Operations regarding outstanding piping configuration and material
procurement items, including bypass planning and project sequencing. A coordination meeting has
been scheduled to finalize design clarifications and establish an updated procurement and mobilization
schedule for the project.
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target
MAY 2026 | 12CIP REPORT
MORGAN ROAD DRAINAGE IMPROVEMENTS
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Project Update: The 100% design submittal was provided to the City in late February, and staff feedback
was issued in late March. The design consultant is now finalizing the construction plans. With the
alignment of underground facilities established, City staff began coordinating with franchise utilities in
March to identify and address potential conflicts. Coordination with franchise utilities and the community
is expected to continue through summer. Atmos Energy Corporation has confirmed conflicts within the
proposed scope of work. Atmos is preparing contract documents to perform a relocation project and
anticipate starting in June. Atmos projects this work to take one month to complete, weather permitting.
Project Description: Constructs a new drainage ditch,
culvert, and channel to reduce flooding risk on Morgan
Road.
CIP Project Number: 2022-47
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 88%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $1,425,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
DOVE EST REPAINT
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
Adopted Budget: $490,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: City staff and consultant reviewed the findings from the Remotely Operated Vehicle
(ROV) inspection report and are advancing preparation of the rehabilitation design and project manual
for the Dove Elevated Storage Tank Repainting Project. In parallel, staff is coordinating conceptual
branding layouts and renderings for the tower graphics. Staff has also initiated coordination with
franchise utility carriers regarding the anticipated construction schedule and potential impacts to
existing telecommunications equipment mounted on the tower.
Project Description: This project is to repaint the Dove
Elevated Storage Tank. The paint on the water tower
was applied in 2006. In addition to repainting the tank’s
interior and exterior including logo artwork, this project
will also replace any structural steel components of the
tank, and yard valve/piping as necessary. This project
includes $475,000 in funding for public art.
CIP Project Number: 2022-39
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Utility Fund
MAY 2026 | 13CIP REPORT
FLORENCE ELEVATED STORAGE TANK REPAINTING
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: O&J Coatings, Inc
Project Update: The Florence Elevated Storage Tank Repainting project is substantially complete, and
the tank has been returned to service following completion of disinfection and receipt of acceptable
bacteriological test results. Interior and exterior coating work has been completed, and franchise
wireless carriers have reinstalled their equipment back onto the tower. Remaining work is limited to
minor punch list items and procurement/installation of the tank mixing system, which is a drop-in system
and does not require the tank to be taken out of service.
Project Description: Repaints and repairs the Florence
Elevated Storage Tank to extend its service life and
protect water quality.
CIP Project Number: 2022-37
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 99%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,745,000
Future Planned Funding: $0
Budget Adherence: Under Budget
TW KING PUMP STATION #2 BUILDOUT PHASE I
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Design work continues, with the 90% milestone design submitted in February. An on-
site meeting was conducted in April to finalize long-term setup and expectations. The design team is
incorporating these decisions and anticipates a final design workshop in May, with project letting and
submittal to TCEQ for regulatory review expected in June. TDEM and FEMA reviews of the generator
grant application are complete, and the project has been identified as an alternate, which may receive
funding if primary projects are not fully awarded. As FEMA has not provided an award timeline and
generator lead times are significant, staff have withdrawn the application to allow the project to be bid
upon completion of final design.
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 91%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
MAY 2026 | 14CIP REPORT
UPSIZE EXISTING 6-INCH TO 12-INCH WATER LINE ALONG EAST HIGHLAND FROM
BLYTHE LANE TO NORTH KIMBALL AVENUE
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements is expected to restart in
the coming months. Initial offers were sent to four of the five property owners, with discussions held
with three; the fourth property was in transition when the offer was sent, and the fifth remains under
legal review regarding prescriptive right-of-way. Meetings were held in January and February to discuss
continuation of the project and to kick off coordination between City staff and TNP’s acquisition team.
TNP has provided updated acquisition letters, which are currently under staff review and will be used to
resume negotiations. Depending on negotiation outcomes, alternative alignments may be considered as
the project advances toward anticipated construction in summer 2027.
Project Description: Replaces the existing 6-inch water
line with a 12-inch line to improve service and capacity.
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.
CIP Project Number: 2022-28c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 64%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $825,000
Future Planned Funding: $2,475,000 (Estimate)