Item 3B3 - CIP Report - APRIL CAPI
EPO T
APRIL 2
r e
r,
5 -
No Text
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City's progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description - A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status - A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase - Indicates the current phase of the project.
• Overall Progress (Current Phase) - Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget- The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding:The amount of funding currently planned for future fiscal years.Typicially
these will be an estimate based on the design.
• Budget Adherence - Shows whether the project is currently under budget, on target, or over
budget.
• Project Update - Gives a short summary of progress since the end of the previous month,
highlighting major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department/ Engineering Firm / General Contractor - Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
No Text
DOVE SIDEWALK PHASE 1
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane
CIP Project Number: 2022-02
Project Status: On Hold m�,.�� � �' v o
Project Phase: Pre-Design
Overall Progress (Current Phase): 98%
CIP Funding Source(s): General Fund
Adopted Budget: $505,000
x
Future Planned Funding: $0 (estimate)
Budget Adherence: On Target
Project Update: Final schematic design was provided
to staff in early March. Prior to construction, staff will coordinate with affected residents, submit plans
for Texas Department of Licensing and Regulation regulatory review, and obtain a construction estimate
from the City's concrete contractor, Apex Concrete Construction, Inc. Construction is anticipated to
begin this Summer. Apex's contract with the City covers scope of work for this project and was already
competitively bid. Utilizing Apex's contract for this work will greatly expedite this project and allow the
City to provide amenities requested by the community.
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
FM • • & PEARSON • IMPROVEMENTS
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with JOROM
new turn lanes, better traffic flow, and a sidewalk along
Pearson. >
CIP Project Number: 2022-13c FM
Project Status: On Hold P
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller
Adopted Budget: $960,000
Future Planned Funding: $2,440,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 1
FM 1709 DECELERATION LANES AT BYRON NELSON AND SOUTHRIDGE LAKES
Project Description: Adds deceleration lanes at Byron •
Nelson Parkway and Southridge Lakes Parkway with
enhanced landscaping.
ouwownw..
CIP Project Number: 2022-06
Project Status: In Progress HNH IT
Project Phase: Closeout
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund R
Adopted Budget: $1,200,000
Future Planned Funding: $0 "°°°'°
Budget Adherence: Under Budget
Project Update: Staff continue to coordinate with TxDOT-certified contractor to resolve outstanding
items left by awarded contractor. A walkthrough with TXDOT occurred April 13 with additional items
noted remaining. This work is being be paid for using retention witheld from the awarded contractor's
agreement with the City. Work is expected to be completed by the end of April 2026 and will be
followed by an additional walkthrough with TXDOT before turning the intersection over to them.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: EARTC
CONTINENTAL • IMPROVEMENTS
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce ,,,, «
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental.
Intersection Improvements. ProjectLocatlon
.
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 40%
UNION CHURCH
CIP Funding Source(s): General Fund, Roadway Impact «
Fee Fund, Tarrant County Bond
Adopted Budget: $8,900,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Union Church Road re-opened ahead of schedule on March 31, all roadway and culvert
improvements on Union Church road have been completed. Drainage improvements within the creek
at critical drainage structure #18 are expected to begin in April, along with completion of the railing on
the south side of the crossing. Traffic signal improvements are on-going, though roadway improvement
focus will now switch to the W. Continental Blvd side of the intersection. Preparation for construction
on that side has begun and traffic control for the Davis Blvd deceleration lane and improvements to the
southside of Continental Blvd. is expected to be implemented mid-April. Franchise utilities have cleared
visible conflicts and the construction crew is currently working to ensure no other conflicts exist.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
CIP REPORT APRIL 2026 12
COURTMUSTANG
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15 6
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $9,270,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: The 60% design has been completed. The City's consultant is currently conducting ROW
acquisition discussions with adjacent property owners. Discussions are also being conducted with the
utility companies regarding relocation of existing facilities. The consultant will proceed with designing to
90% while the ROW discussions are continuing. Once the ROW is acquired and the design is completed,
the project will be let out for bid.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
N. CARROLL AVE. CORRIDOR
Project Description: Improves the corridor with it
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
�a
CIP Project Number: 2022-09
Project Status: In Progress a $ y
Project Phase: Construction a
Overall Progress (Current Phase): 52%
CIP Funding Source(s): General Fund - ExaS 7
Adopted Budget: $2,070,000
Future Planned Funding: $0 "
Budget Adherence: On TargetJ/
Project Update: Construction is substantially complete on the Carroll Avenue Mobility Improvements
Project. Recent work included completion of the Lake Wood Drive intersection improvements and
installation of additional pavement markings at the State Highway 114 and N. Carroll Avenue intersections
to provide clearer motorist guidance through the new lane configuration. Remaining work is limited to
final traffic-related items, including illuminated signs, decorate street lamps, and cameras. Given the lead
time for the remaining signal components, the project is anticipated to be completed by Summer 2026.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
CIP REPORT APRIL 2026 13
RANDOL MILL WATER AND SIDEWALK IMPROVEMENTS
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements. N
CIP Project Number: 2022-33c PHEASANT LN w, n`
Project Status: In Progress
Project Phase: Construction rz
Overall Progress (Current Phase): 33% clu
i
CIP Funding Source(s): General Fund, Utility Fund, s
Water Impact Fee Fund » ,. j .�....o
Adopted Budget: $3,400,000 t 3
p
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Waterline improvements and franchise utility relocations are complete, with utility
relocations completed in February and waterline work completed in March. Residents have been
connected to the new 12-inch water line, and temporary lines have been removed. Curb installation along
Randol Mill Avenue from Pheasant Lane to the City limits has been completed. Construction of final
right-of-way improvements, including sidewalk and side street approaches began in mid-March and is
expected to be complete this spring.
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
S. PEYTONVILLE • • N IMPROVEMEN
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard p�
g � aiN4 i!
and South Peytonville Avenue intersection. This project R3
is a companion project to FM 1938 & Continental Blvd. "
Intersection Improvements. ProjectLocataon # ,
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
UNION CHURCH
CIP Funding Source(s): General Fund, Utility Fund, n
Roadway Impact Fee Fund, Storm Water Utility System,
Tarrant County Bond _
Adopted Budget: $6,185,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: No major changes since last update. This project is a companion to the FM1938 and
Continental Boulevard intersection improvements. The contract was awarded to McMahon Contracting
late May 2025, and work on this phase will not begin until the substantial completion of the companion
project to minimize mobility impacts. The anticipated start is approximately 18 months after the FM 1938
and Continental phase begins, estimated to be no later than April 2027.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
CIP REPORT APRIL 2026 14
INTERSECTIONON •
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
.A
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $400,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Phase 2 design is complete and this phase of the project has broken ground on the
North side of the Dove and 114 intersection. The project will take approximately 42 working days to
complete and strong progress has been made thus far. This phase should be complete and move into the
warranty phase later this spring.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Central North Construction LLC
INTERSECTIONON _ •
Project Description: Enhances intersections on SH 114 _
with landscaping and corridor beautification.
CIP Project Number: 2024-07 ,$
Project Status: In Progress
Project Phase: Pre-Design '
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding � A
Adopted Budget: $420,000 .,
Future Planned Funding: $0
Budget Adherence: On Target -�
Project Update: Phase 3 was awarded the full $420,000 to begin work at the intersection of White
Chapel and SH 114. City staff are working with the design consultant and TxDOT on phase 3 of this
project and have conducted a project kick-off and preliminary design work. City Council authorized
the City Manager to enter into an advance funding agreement for this project at the December 2, 2025
Council meeting and staff are working with the consultant on design with a planned letting date for
Summer of 2026.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 15
1938 MEDIAN LANDSCAPING
Project Description: Constructs landscape, irrigation, Ne,,SOUTHLAKE D
and hardscape improvements on FM 1938 from FM 1709 H E. FM
,T09
Be packeek � Rantd 6kolf Club®
to the Southlake City limits, consistent with landscaped =
_Tes LIMITS Oj WORK WAN `
AR—
median improvements north of FM 1709. The City's SOUTHLAKe CITY LIMITS
LIMITS OF TxDOT �'
scope includes landscape, irrigation, and hardscape °� PROJECT
only. ook Q Hic NLTrvo oaks Tmmpollne Park
ne DePO v , • " pP�
ILmwes Home
pmvemenl
CIP Project Number: 2024-06 x M.
Project Status: In Progress —e—e •°a°tld
Playgmana w
Project Phase: Design
Overall Progress (Current Phase): 60% 'E" Em55ioo5eSHe"o M1THe1
CIP Funding Source(s): General Fund OLeale= 'osolwo°=L«e1y o
A
Adopted Budget: $1,693,000 ngles m
w„Walauga � nt'BONPd—I Salad Intl Go® Chisholm Park
n8 TILE B GMrvrtE 0
Future Planned Funding: $0 „IEMERALDHILLg.
Budget Adherence: On Target ams CIA
Project Update: This project involves the construction of a raised concrete median from FM 1709 in
Southlake, through Keller and into North Richland Hills. The City aims to partner with TxDOT to include
landscape improvements on the new medians. The City consultant is proceeding with development of
the 90% design after receiving comments from the City and TxDOT on the 60% design. TxDOT recently
commenced with construction in Southlake. It is anticipated that work for the TxDOT portion of the
project to completed by Summer 2026 and that the landscape improvements will be constructed in a
later phase of the project.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
MUNICIPAL SERVICE CENTER AND PUBLIC SAFETY TRAINING TOWER
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower. SNIPE
CIP Project Number: 2022-79c
Progress Project Status: In Pro --Y '
1 g
Project Phase: ConstructionI
Overall Progress (Current Phase): 51% n_ ■■.
CIP Funding Source(s): General Fund and Utility Fund
Adopted Budget: $46,600,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Byrne Construction Services continues to make steady progress with construction
on the Municipal Service Center and Public Safety Training Tower Project. Construction activities
onsite are now going vertical. Visible progress can now be seen with the Service Bay Building, where
framing for the structure is now complete. Work now proceeds to the installation of the roof and siding.
Progress can also be seen at the Administration Building, as Byrne completes the concrete pours for
the structure's retaining walls. Once complete, Byrne will begin construction of the tilt wall panels. The
concrete walls for the structure will be cast flat as a single piece and tilted up to form the two-story
Administration Building. At the Public Safety Training Tower, Byrne is preparing to pour the foundations
for the structure. Site improvements over the next few weeks include paving as well as irrigation work
for landscaping. The project continues to remain aligned with the established construction timeline.
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
CIP REPORT APRIL 2026 16
TOWN HALL PLAZA PARK
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $8,138,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The consultant is completing the 30% design. An RFQ is currently advertised to
prequalify CMAR candidates for this project. The most qualified CMAR candidates will be invited to
participate in the RFP process to provide preconstruction services for this project.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
TURF REPLACEMENT PHASE 11 (NORTH PARK)
Project Description: Implements high impact park
improvements including conversion of athletic fields c
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $5,673,000
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: Plans have been resubmitted for permitting. Once the plans have satisfactorily met
permitting requirements, the bid package will be finalized and the project will be let out for bid.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 7
TURF REPLACEMENT PROJECT
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at Bob Jones
Park and Bicentennial Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 97%
CIP Funding Source(s): General Fund, Utility Fund, and
Crime Control Prevention District
Adopted Budget: $12,015,000
Future Planned Funding: $0
Budget Adherence: Under Budget
Project Update: Contractor is completing final punch list items relative to the completing work on the
turf fields (Fields 5 & 6) at Bicentennial Park. Fields are available for use by Dragon Youth Baseball.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: GeoSurfaces
BIG BEAR CREEK IMPROVEMENTS NEAR TIMBER COURT
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
_..,.,o.
CIP Project Number: 2022-45c n� W CONTINENTAL BLVD
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition /
Overall Progress (Current Phase): 59% °
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $135,000
Future Planned Funding: $620,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 18
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue. m
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from :
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c
Project Status: On Hold
C
Project Phase: ROW/ Easement Acquisition \ NW4*ANDs7
Overall Progress (Current Phase): 63%
CIP Funding Source(s): Sanitary Sewer Impact Fee,
Utility Fund
Adopted Budget: $245,000 �° N
Future Planned Funding: $2,395,000 (Estimate)
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements is expected to restart late
spring. Initial offers were sent to four of the five property owners, with discussions held with three;
the fourth property was in transition when the offer was sent, and the fifth remains under legal review
regarding prescriptive right-of-way. Meetings were held in January and February to discuss continuation
of the project and to kick off coordination between City staff and TNP's acquisition team. TNP has
provided updated acquisition letters, which are currently under staff review and will be used to resume
negotiations. Field data was collected in early March to support finalization of design, and depending
on negotiation outcomes, alternative alignments may be considered as the project advances toward
anticipated construction in summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
EAGLE BEND & STRATHMORE SANITARY SEWER RECONSTRUCTION
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek. ECONTINEWALBLVD
Lararcu, P.um."w.r
CIP Project Number: 2023-14 ► W&V SYjtOh NEI
Project Status: On Hold I
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76% r
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000
Future Planned Funding: $820,000 (Estimate)Budget Adherence: On Target
Project Update: No major changes since last update.
Design reached 90 percent completion in July 2024, and property owner coordination for easements is
ongoing. One of the three permanent easements has been acquired, while agreements with the Timarron
HOA and Golf Course remain under legal review. A required temporary easement has not yet been
secured. The project is on hold due to reprioritization and will resume as other projects conclude.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 19
HIGGINS BRANCH NEAR • • - - • •
Project Description: Provides erosion control and , VF
sewer protection improvements along Higgins Branch i
near Woodbrook Lane.
J
CIP Project Number: 2022-45c
Project Status: On Hold i
Project Phase: ROW/ Easement Acquisition Z
Overall Progress (Current Phase): 73% w�oRw°°"N
CIP Funding Source(s): Utility Fund, Storm Water
Utility System 3 °
Adopted Budget: $185,000 —
Future Planned Funding: $525,000 (Estimate) �R � :
Budget Adherence: On Target
Project Update: No major changes since last update. Coordination with property owners regarding
access easements is ongoing. Two temporary easements have been acquired, while one permanent
access easement remains under legal review. The project is on hold due to reprioritization and will
resume as other projects are completed.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
JONES BRANCH NEAR RAINTREE DR.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 80%
CIP Funding Source(s): Utility Fund, Storm Water
yd? GRBEH@OUGH Ll�
Utility System
Adopted Budget: $158,000
Future Planned Funding: $975,000 (Estimate)
Budget Adherence: On Target
Project Update: Following a February 2, 2026 public meeting with Simmons Ct residents, staff collected
and reviewed resident feedback on the project options through a feedback from that closed on February
25. After discussion with City Council and consideration of resident input, direction was provided to
proceed with the Infrastructure Related Stabilization Project option. Staff met with the consultant on
April 6 to review the revised scope and path forward for advancing the stabilization design. Staff will
work with the consultant to finalize scope this spring
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 110
JONES BRANCH NEAR SIMMONS
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: In Progress
Project Phase: Design �+
Overall Progress (Current Phase): 83%
RAVWr�W
CIP Funding Source(s): Utility Fund, Storm Water C
Utility System `° sReee�ws�lei
Adopted Budget: $885,000
Future Planned Funding: $0 (Estimate) VMLLMS sN
Budget Adherence: On Target
Project Update: This project is a companion project to Jones Branch near Raintree Drive. Following
a February 2, 2026 public meeting with Simmons Ct residents, staff collected and reviewed resident
feedback on the project options through a feedback from that closed on February 25. After discussion
with City Council and consideration of resident input, direction was provided to proceed with the
Infrastructure Related Stabilization Project option. Staff met with the consultant on April 6 to discuss the
scope and path forward for advancing the stabilization design.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
LONESOME DOVE/SHADY • IMPROVEMENTS
Project Description: Installs emergency backup pumps '*
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0% Q
J
CIP Funding Source(s): Utility Fund
Z Adopted Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target r
Project Update: Since the previous update, the contractor has submitted a cost change proposal. Staff
is coordinating a meeting with the design consultant and Public Works Operations team to review the
proposal and discuss the project schedule.
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
CIP REPORT APRIL 2026 111
MORGAN ROAD DRAINAGE - •
Project Description: Constructs a new drainage ditch,
culvert, and channel to reduce flooding risk on Morgan
Road.
CIP Project Number: 2022-47
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 88%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $1,425,000 VIOMBRO"LN
w
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
Project Update: The 100% design submittal was provided to the City in late February, and staff feedback
was issued in late March. The design consultant is now finalizing the construction plans. With the
alignment of underground facilities established, City staff began coordinating with franchise utilities in
March to identify and address potential conflicts. Coordination with franchise utilities and the community
is expected to continue in the coming months.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
DOVE EST REPAINT
Project Description: This project is to repaint the Dove
Elevated Storage Tank. The paint on the water tower •" "
was applied in 2006. In addition to repainting the tank's " N
interior and exterior including logo artwork, this project
will also replace any structural steel components of the a.°„.•�
tank, and yard valve/piping as necessary. This project w
includes $475,000 in funding for public art.
CIP Project Number: 2022-39 DOVERD
Project Status: Not Started
Project Phase: Design d
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Utility Fund
TEXAS ,•p,W°°••wnno rez
Adopted Budget: $490,000
Future Planned Funding: N/A
Budget Adherence: On Target
Project Update: The Engineering Services Agreement with the consultant was approved by City
Council on December 2, 2025. Since that time, a kickoff meeting was held on February 23, 2026, the
remotely operated vehicle inspection of the interior of the tank was completed on February 26, 2026,
and the inspection report was received on March 27, 2026. Staff is now reviewing the findings with the
consultant and moving forward with preparation of the design and project manual for the rehabilitation
work.
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 112
FLORENCE ELEVATED STORAGE
Project Description: Repaints and repairs the Florence
Elevated Storage Tank to extend its service life and FLDRENCER❑
protect water quality. p m
c
CIP Project Number: 2022-37 11-IIE IT
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 95% 3 �-° "°°��' I i
CIP Funding Source(s): Utility Fund JOHNSONRb $ A°
Adopted Budget: $2,745,000 z
Future Planned Funding: $0 8
Budget Adherence: On Target
Project Update: The Florence Elevated Storage Tank was taken offline in early February to allow
rehabilitation work to proceed. Interior and exterior coating of the tank was completed in mid-March,
and franchise wireless carriers have reinstalled their equipment back on the tower. Disinfection of the
tank has been completed, and bacteriological samples have been collected. The tank will be returned
to service upon receipt of acceptable test results, anticipated for April 14. While staff has continued
to monitor and maintain system pressures throughout construction, returning the tank to service will
restore pressure to those exceptions & impacts during construction.
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: O&J Coatings, Inc
STATIONTW KING PUMP D•
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 91%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
Project Update: Design work continues, with the 90% milestone design submitted in February. Staff
feedback has been provided, and the consultant is working toward final design completion in April, with
submittal to TCEQ for regulatory review also anticipated at that time. TDEM and FEMA reviews of the
generator grant application are complete, and our project has been selected as an alternate. Alternate
projects are funded after primary projects and may not receive funding. As FEMA has not provided
an award timeline and generator lead times are significant, staff is recommending withdrawal of the
application to allow the project to be bid upon completion of final design.
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 113
' • 12-INCH WATER LINE ALONG EAST HIGHLAND FROM
BLYTHE LANE • NORTH
Project Description: Replaces the existing 6-inch water F
line with a 12-inch line to improve service and capacity. 3
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line. u
CIP Project Number: 2022-28c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition e
Overall Progress (Current Phase): 64%
CIP Funding Source(s): Utility Fund, Water Impact Fee j
Fund
Adopted Budget: $825,000
Future Planned Funding: $2,475,000 (Estimate)
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements is expected to restart in
the coming months. Initial offers were sent to four of the five property owners, with discussions held
with three; the fourth property was in transition when the offer was sent, and the fifth remains under
legal review regarding prescriptive right-of-way. Meetings were held in January and February to discuss
continuation of the project and to kick off coordination between City staff and TNP's acquisition team.
TNP has provided updated acquisition letters, which are currently under staff review and will be used to
resume negotiations. Depending on negotiation outcomes, alternative alignments may be considered as
the project advances toward anticipated construction in summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT APRIL 2026 1141