Item 6 - Corridor Committee Meeting Report - Stormwater Master Plan Southlake Corridor Planning Committee Meeting Report
Meeting 54 — January 28, 2026
MEETING
LOCATION: 1400 Main St., Southlake, Texas 76092
City Council Chambers
IN
ATTENDANCE:
• City Council Members: Randy Robbins, Frances Scharli, Kathy Talley,
Austin Reynolds
• Planning & Zoning Commission Members: Daniel Kubiak, Michael
Forman, David Cunnigham
• City Staff: Dennis Killough, Jenny Crosby, Daniel Cortez, Cyndi Cheng,
Ryan Firestone, Jeff Ginn, Lauren LaNeave
AGENDA
ITEMS:
1 . Call to Order.
2. Administrative Comments.
3. Review, discuss, and make recommendations regarding a proposed office and
warehouse development on an approximately 8.1-acre property located at 2185 E.
Southlake Boulevard.
4. Review, discuss, and make recommendations regarding site plan improvements for
Pottery Barn located at 1440 Civic Place.
5. Review, discuss, and make recommendations regarding a proposed Westin Event
Venue Addition located at 1200 E. SH 114.
6. Review, discuss, and make recommendations regarding a proposed 21-acre mixed-
use development, including commercial and residential uses, and an alternative all-
residential development plan for property located at 300-684 Davis Boulevard.
7. Review, discuss, and make recommendations regarding a proposed residential
development to include 11 single-family lots and located at 940-1050 S. Carroll Ave.
and 1000-1040 Breeze Way.
8. Review, discuss, and make recommendations regarding a proposed realignment of
two single-family lots located at 1275 and 1285 Shady Oaks Drive.
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 1
9. Overview of the Stormwater Master Plan, an Element of the Southlake
Comprehensive Plan.
10.Adjournment.
MEETING
OVERVIEW:
On January 28, 2026, the Southlake Corridor Planning Committee held
their 54th meeting. The Committee was sent a packet of materials prior to
the meeting that were to be discussed during the session. A meeting
agenda was posted, and the meeting time was advertised on the City's
website. The following meeting report focuses on discussion points made
during the meeting by members of the Committee, public and City staff.
This report is neither verbatim nor does it represent official meeting
minutes; rather it serves to inform elected and appointed officials, City
staff, and the public of the issues and questions raised by the Committee,
City staff, and any attendees of the meeting. Interested parties are
strongly encouraged to follow development cases through the process.
Please visit CityofSouthlake.com/Planning for more information
ITEM #9 DISCUSSION — Overview of the Stormwater Master Plan, an Element of the
Southlake Comprehensive Plan.
Staff presentation: Daniel Cortez
• Comprehensive Plan Elements
• How are the plans aligned
• Committee role
• Policy framework considerations
• What should the policy consider?
• Example policy considerations
• Plan adoption process
• What are utility master plans?
• Water system focus
• Wastewater system focus
• Stormwater and drainage focus
• What to expect?
• Communication
• Public engagement
Questions for Staff
Daniel Cortez
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 2
Thank you, Mr. Chairman, and members of the Council and Commission. I'm happy to
finally kick off this utility plan process with this committee.
Today, I want to revisit what this process means for us and where we are starting. We
are now touching the plan elements related to the comprehensive plan. Council is used
to seeing plan elements connected to the City's Strategic Management System, and this
should be viewed in a similar way.
It's important to be clear that we are not engineering solutions today. Instead, we'll
be asking policy-level questions—generally yes-or-no questions—that will guide staff
direction. From those answers, staff will draft policy statements. Those statements will
be shared during upcoming SPIN open houses and will incorporate feedback from
residents, Planning & Zoning, and City Council.
Think of this as creating a stormwater strategy map for the City. Tonight, we'll cover
background, context, and data—how drainage basins function, FEMA and NFIP
requirements, and state permits. We'll also discuss what our infrastructure looks like
today and what it could look like. Then we'll shift into policy discussion.
The purpose tonight is to review regulatory and financial considerations, provide a high-
level overview of stormwater management, summarize prior studies from the last five to
ten years, and address resident concerns. Throughout, we'll pause for policy discussion
and seek your feedback.
At the highest level, stormwater management has four jobs:
1 . Convey water safely so it doesn't overwhelm streets, homes, or infrastructure
2. Store water to manage peak flows
3. Mitigate risk, recognizing hazards vary across the city
4. Protect water quality from sediment, oils, nutrients, and pollutants
Each policy question tonight ties back to one or more of these jobs.
The overall intent of stormwater management is simple: soak it in, slow it down, and
spread it out. Speeding up stormwater is often not desirable. Our City Engineer, Jeff
Ginn, will expand on that shortly.
With that, I'll turn it over to our Director of Public Works, Lauren Laneve, to walk through
regulatory and financial considerations.
Lauren LaNeave
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 3
Thank you, Daniel.
We'll start with the fundamentals—regulatory and financial considerations. These are
the boundaries within which any policy goals must operate.
Stormwater management in Southlake is governed by multiple layers: federal, state,
and local requirements, along with practical constraints of the built environment. Some
requirements are mandatory; others allow flexibility. The policy questions we ask tonight
help define where that flexibility exists.
Southlake's stormwater planning evolved with the city's growth. Key milestones include:
1969: First subdivision ordinance requiring drainage studies
1990 (Ordinance 482): Formal storm drainage policy
1994 (Ordinance 605): Foundation of current drainage standards
2023 (Ordinance 1268): Post-construction stormwater ordinance with ongoing
maintenance requirements
Today's system operates under MS4 permits, FEMA floodplain regulations, U.S. Army
Corps jurisdictional waters, Texas Water Code, and local ordinances.
A frequent concern is responsibility. The City maintains public drainage
infrastructure—inlets, culverts, and systems in public rights-of-way or improved
easements. Property owners and HOAs are responsible for private drainage systems,
including natural channels and unimproved easements. That includes debris removal,
erosion repair, and vegetation management.
A policy question for the committee is whether this division of responsibility should be
revised.
Our MS4 permit requires public education, illicit discharge enforcement, construction
runoff control, post-construction management, and annual reporting to the state.
Policy Question #1:
Should the City consider changes to its stormwater enforcement approach?
Daniel Kubiak
Does anyone want to jump in? Is there a city recommendation, or examples of how
enforcement might change?
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 4
Lauren LaNeave
Enforcement varies widely by city. Southlake takes a customer service—first
approach. For minor issues, we educate first and escalate only if issues persist. More
egregious violations—like illegal dumping—trigger enforcement immediately.
The question is whether that approach is sufficient or whether the City wants to become
more proactive, which would require additional resources.
Austin Reynolds
I think education is key. I'd bet 90% of residents don't know their HOA is responsible for
detention ponds. People only find out when it's expensive. If maintenance had been
ongoing, costs wouldn't be so high.
Tracking HOA maintenance—even lightly—could help prevent downstream impacts.
Kathy Talley
I strongly agree. HOAs often don't understand permitting or stormwater responsibilities,
and residents certainly don't. I didn't even know draining a pool into the street was an
issue. Education supports our customer-first culture.
David Cunningham
There's also an awareness problem. New property owners may not know they have
drainage easements or responsibilities. This is common in older areas, especially in the
west. Education and disclosure are critical.
Randy Robbins
Education is good, but does enforcement have enough teeth? Do we actually have the
authority and effectiveness to make changes when issues persist?
Lauren LaNeave
Southlake Corridor Planning Committee Item#9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 5
Currently, enforcement is mostly reactive. Proactive inspections would require
evaluating staffing and resources.
Frances Scharli
I hope we're also looking at what the City can do better. Development has increased
runoff, and while formulas say it should balance, residents don't always see that. We
need to examine both HOA and City responsibilities.
Daniel Cortez
That's a great point. Several upcoming policy questions focus on City operations and
responsibilities. We structured the presentation to avoid overwhelming you all at once.
Daniel Kubiak
And of course, additional results usually require additional resources.
Lauren LaNeave
Exactly. Any policy recommendations will include an evaluation of required resources.
Frances Scharli
When was the last stormwater fee increase?
Lauren LaNeave
2008.
Daniel Kubiak
Okay, let's move on.
Southlake Corridor Planning Committee Item#9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 6
Lauren LaNeave
Public education is part of our MS4 permit. What I'm hearing is that the committee
supports increasing education efforts beyond minimum requirements.
Randy Robbins
My concern is that if we study everything, the cost will be astronomical. You mentioned
that we tend to be more reactionary in our approach. Does staff already have—probably
through a team approach—an anecdotal understanding of where the issues currently
are and where they're likely going to be?
We probably have staff who are bright enough to identify problem areas without paying
hundreds of thousands of dollars for a study. Can we start addressing those issues
anecdotally? Say, "This area is going to be an issue over the next 18 months due to
development—how do we mitigate that risk now?" Instead of studying it just to confirm
what we already know and ending up six months behind because we studied first rather
than acted.
Jeff Ginn
To Lauren's point about the models we have: there is a model for each watershed that
shows flood-prone areas under current infrastructure. The concern comes when we get
into public-private improvement areas.
Every time we upgrade a critical drainage structure, we are required by FEMA
regulations to do a deeper model to evaluate upstream and downstream impacts. That
process does take time. Determining the scope and extent of improvements helps
narrow down long-term capital costs.
Daniel Kubiak
Any other comments or questions on this?
Frances Scharli
I know I've been advocating for a study, but if we already know there are high-risk flood
areas, not addressing them doesn't make sense either.
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 7
Is there a way to take the information we already have, look at the whole system, and
make future decisions? If we know an area is flooding and we're not addressing it, that
doesn't make sense.
Jeff Ginn
That's a great question. The North White Chapel Bridge Improvements study evaluated
the entire Kirkwood watershed basin. That study identified several additional CIP
projects that are now under design or planning.
When we design major drainage infrastructure, we often take that opportunity to model
the entire watershed and identify other areas for the five- and ten-year CIP programs.
The question becomes whether we only look at public infrastructure or also include
private drainage easements.
Daniel Kubiak
Hopefully the moving target settles down as the city approaches 90% build-out. Some
areas are more built out than others, but hopefully things won't change drastically over
time.
As new development applications come in, a comprehensive viewpoint should help us
address issues consistently.
Lauren LaNeave
This question gets at development standards and ordinances. If a property is
developing in or near a floodplain, there are already additional requirements.
The policy question is whether the city wants more stringent or adjusted standards for
higher-risk areas. We do know where floodplains are—federal and state governments
recognize them as well.
Daniel Kubiak
Anyone want to weigh in?
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 8
Frances Scharli
When you're doing a study like the White Chapel Bridge, how do you weigh that against
problems elsewhere in town? How does staff determine which problems get attention?
Lauren LaNeave
Prioritization is driven primarily by public safety. On the map Jeff showed, low-water
crossings highlighted in yellow are priority areas, such as Continental Boulevard.
The North White Chapel Bridge was replaced because it was a low-water crossing.
When prioritizing CIP projects, we look at public safety, readiness to move forward, land
ownership, funding availability, and feasibility.
Some projects stall due to property acquisition challenges or unwilling easement
dedication. Many factors go into prioritization.
Daniel Kubiak
Anything else on this item?
Lauren LaNeave
The next question addresses proactive planning versus reactive response. Should the
city establish a regular cadence for watershed studies rather than conducting them ad
hoc?
This would help validate assumptions, refresh priority lists, and support long-term
stormwater planning.
Daniel Kubiak
Based on tonight's discussion, I think yes.
Lauren LaNeave
That's what I'm hearing.
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 9
Austin Reynolds
I think this could dovetail with earlier comments. Perhaps every two or three years, the
city should remind HOA boards of maintenance responsibilities and require reporting,
including detention pond dredging.
Frances Scharli
The city should also take ownership of its own projects, not just private ones.
Lauren LaNeave
Moving on to Question 7: Should the city explore opportunities to address impervious
coverage through limits, mitigation requirements, or incentives?
Austin Reynolds
I'm not as concerned about impervious coverage itself as long as runoff is properly
detained and modeled for full build-out—both upstream and downstream, including
neighboring cities.
David Cunningham
Isn't the developer required to release runoff at the same rate as undeveloped land?
Lauren LaNeave
Yes, they must meet existing conditions prior to development.
David Cunningham
Then impervious coverage is indirectly regulated. If runoff exceeds undeveloped
conditions, the developer must detain it. Especially given existing drainage issues,
restrictions are appropriate.
Southlake Corridor Planning Committee Item#9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 10
Frances Scharli
We have drainage problems, which tells me our ordinances need to be reviewed. If
there weren't problems, this wouldn't be an issue.
Randy Robbins
Are we talking proactive or retroactive? Going back and fixing existing development is
unrealistic. I'm fine with moving forward, but retroactive changes would be very difficult.
Lauren LaNeave
The intent is forward-looking. Retroactive fixes would be challenging.
Daniel Kubiak
We used to recommend alternative driveway materials. Perhaps we could incorporate
recommendations—not requirements—for more permeable options.
Dennis Killough
That's a viable policy direction. The city already allows permeable paving and provides
stormwater fee discounts, though uptake has been limited.
Daniel Kubiak
Maybe those incentives could be enhanced.
Lauren LaNeave
Next question: Should the city modernize ordinances to align more closely with regional
practices?
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 11
Daniel Kubiak
We should see what neighboring cities are doing that works or doesn't. We're not alone
in these issues.
Lauren LaNeave
Last policy question: Should documented resident drainage concerns carry more weight
in capital project prioritization?
David Cunningham
That would be difficult. Life safety should be first, property damage second. Individual
complaints are hard to weigh objectively.
Randy Robbins
Resident concerns matter, but many issues are on private property, which limits what
the city can do.
Frances Scharli
We pride ourselves on service. Ignoring resident concerns would be contrary to that.
We should have criteria to evaluate them.
Daniel Kubiak
Resident concerns should be a variable, but data-driven analysis must lead. If it's a
major problem, the data will show it.
Daniel Cortez
Staff will now develop the plan based on this feedback. Policy statements will be refined
and brought to SPIN, Planning & Zoning, and City Council.
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 12
The next meeting is February 10 and will cover water and wastewater. SPIN meetings
are televised, and materials will be available on south lakecompplan.com.
STAFF PRESENTATION SHOWN TO COMMITTEE:
Southlake Corridor Planning Committee Item #9—Stormwater Master Plan
Meeting#54—January 28, 2026 Page 13