Item 3B3 - CIP Report - FebruaryFEBRUARY 2026
The information in this report is updated as of January 31, 2026.
Item 3B3
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City’s progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description – A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status – A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase – Indicates the current phase of the project.
• Overall Progress (Current Phase) – Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget – The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding: The amount of funding currently planned for future fiscal years. Typicially
these will be an estimate based on the design.
• Budget Adherence – Shows whether the project is currently under budget, on target, or over
budget.
• Project Update – Gives a short summary of progress since the end of the previous month,
highlighting major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department / Engineering Firm / General Contractor – Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
FEBRUARY 2026 | 1CIP REPORT
DOVE SIDEWALK PHASE 1
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
application was not selected for funding, and resident contacts were notified of this and how the City
intends to move forwards with this project in January. Prior to the funding opportunity, design work
for Phases 1 and 2 was ongoing under an existing contract, which had been placed on hold during the
application review period. With the funding decision now confirmed, the City is returning to a phased
approach, and staff met with the consultant November 21 to review expectations for completing
the combined Phase 1 & 2 design package. City and consultant have determined that no additional
supplements are needed for this work. Design is anticipated to be completed by March 2026, with
construction expected to begin Summer 2026.
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane
CIP Project Number: 2022-02
Project Status: On Hold
Project Phase: Pre-Design
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund
Adopted Budget: $465,000
Future Planned Funding: TBD-Pending final design
Budget Adherence: On Target
Project Update: Staff learned mid-November that the
FM 1709 & PEARSON INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
Pearson.
CIP Project Number: 2022-13c
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller
Adopted Budget: $960,000
Future Planned Funding: $2,440,000 (Estimate)
FEBRUARY 2026 | 2CIP REPORT
FM 1709 DECELERATION LANES AT BYRON NELSON AND SOUTHRIDGE LAKES
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: EARTC
Project Update: Re-inspection with TxDOT was held January 29th and showed a few items still
outstanding. Staff are currently coordinating with TxDOT to resolve these issues with the Contractor
who has taken no exceptions to us utilizing another TxDOT-certified contractor to complete the
outstanding items. The work would be paid for out of existing Contractor’s agreement with the City.
Project Description: Adds deceleration lanes at Byron
Nelson Parkway and Southridge Lakes Parkway with
enhanced landscaping.
CIP Project Number: 2022-06
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund
Adopted Budget: $1,200,000
Future Planned Funding: $0
Budget Adherence: On Target
FM 1938 & CONTINENTAL BLVD. INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Construction began October 27th, Union Church Road was closed November 3rd, and
construction is currently ahead of schedule. Drainage improvements at critical drainage structure #18 are
expected to be complete in January. Installation of underground traffic signal infrastructure began late
November, and roadway improvements began early January. Franchise utilities are still working to clear
conflicts in the area but are not impeding construction.Union Church Road is anticipated to reopen ahead
of schedule in late March, weather permitting.
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental
Intersection Improvements.
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 26%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Tarrant County Bond
Adopted Budget: $8,900,000
FEBRUARY 2026 | 3CIP REPORT
MUSTANG COURT INDUSTRIAL AREA ACCESS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: Appraisals for the right-of-way acquisitions are being performed by the City’s
consultant. Utility location is being performed and the consultant continues to work on the 60% design.
It is anticipated that right-of-way negotiations will begin in March.
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 55%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $1,975,000
Future Planned Funding: $5,050,000 (Estimate)
Budget Adherence: On Target
N. CARROLL AVE. CORRIDOR
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
Project Update: Construction continues to progress. The median extension at the Lake Wood Dr
intersection has been completed, with pavers currently being installed. Demolition work for the left-
turn lane addition has been completed, and reinforcing steel placement is underway in preparation for
concrete placement. The new traffic signal at SH114 has been installed, and three new trees were planted
near Main Street earlier this year as part of Southlake’s initiative to plant 2,026 trees citywide. Overall
project completion remains expected by mid-March, weather permitting.
Project Description: Improves the corridor with
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund
Adopted Budget: $2,070,000
Future Planned Funding: $0
Budget Adherence: On Target
FEBRUARY 2026 | 4CIP REPORT
RANDOL MILL WATER AND SIDEWALK IMPROVEMENTS
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
Budget Adherence: On Target
Project Update: Construction began October 6, 2025, with the contractor completing the temporary
above-ground waterline north of Enclave Ct in October and near Mockingbird Ln in November. Franchise
utility work is nearing completion in the area and is coordinating with us to ensure both projects
are completed in a timely manner. The permanent waterline is now installed and connected to the
City system from north of Enclave Ct to south of Pheasant Ln. Temporary lines were removed in this
completed section of waterline. A temporary waterline at Morgan Rd will be placed in February and
installation of planned drainage infrastructure to support the sidewalk is on-going.
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements.
CIP Project Number: 2022-33c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 24%
CIP Funding Source(s): General Fund, Utility Fund,
Water Impact Fee Fund
Adopted Budget: $3,400,000
Future Planned Funding: $0
S. PEYTONVILLE & W. CONTINENTAL INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: No major changes since last update. This project is a companion to the FM1938 and
Continental Boulevard intersection improvements. The contract was awarded to McMahon Contracting
late May 2025, and work on this phase will not begin until the substantial completion of the companion
project to minimize mobility impacts. The anticipated start is approximately 18 months after the FM 1938
and Continental phase begins.
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard
and South Peytonville Avenue intersection. This project
is a companion project to FM 1938 & Continental Blvd.
Intersection Improvements.
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): General Fund, Utility Fund,
Roadway Impact Fee Fund, Storm Water Utility System,
Tarrant County Bond
Adopted Budget: $6,185,000
FEBRUARY 2026 | 5CIP REPORT
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 2
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: Phase 2 design is complete, and the project has been bid. Bid opening was completed
in late July and the City and design consultants recently received concurrence from TxDOT to award the
bid to the lowest qualified bidder on the project. City Council Awarded the bid for this Phase to Central
North Construction at the January 6th Council meeting and the pre-construction meeting is pending. The
project will be funded by a $400,000 fully reimbursable grant from TxDOT.
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Bidding/Pre-Con
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $400,000
Future Planned Funding: $0
Budget Adherence: On Target
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 3
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: Phase 3 was awarded the full $420,000 to begin work at the intersection of White
Chapel and SH 114. City staff are working with the design consultant and TxDOT on phase 3 of this
project and have conducted a project kick-off and preliminary design work. City Council authorized the
City Manager to enter into an advance funding agreement for this project at the December 2nd Council
meeting and staff are working with the consultant on design with a planned letting date for Summer of
2026.
Project Description: Enhances intersections on SH 114
with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $420,000
Future Planned Funding: $0
Budget Adherence: On Target
FEBRUARY 2026 | 6CIP REPORT
1938 MEDIAN LANDSCAPING
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: 60% Design submittal has been submitted to the City and reviewed by staff. Plans have
been sent to TxDOT for preliminary review. Consultant has begun work on the 90% design and will
complete the revision upon receiving comments from TxDOT.
Project Description: Constructs landscape, irrigation,
and hardscape improvements on FM 1938 from FM 1709
to the Southlake City limits, consistent with landscaped
median improvements north of FM 1709. The City’s
scope includes landscape, irrigation, and hardscape
only.
CIP Project Number: 2024-06
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund
Adopted Budget: $1,650,000
Future Planned Funding: $0
Budget Adherence: On Target
TOWN HALL PLAZA PARK
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Adopted Budget: $7,938,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: Staff received direction from City Council on the critical programmatic elements to
include in the project design. The City engaged a firm to serve as design manager on the project. The
consultant is working on the 30% design and once complete, the City will issue an RFQ/RFP to identify a
CMAR for the design portion of this project.
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 25%
CIP Funding Source(s): Southlake Parks Development
Corporation and Hotel Occupancy Tax Fund
FEBRUARY 2026 | 7CIP REPORT
TURF REPLACEMENT PHASE II (NORTH PARK)
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: Not Awarded Yet
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The consultant is completing the 100% plans for the project. Once completed, the
project will be submitted for plan check, followed by formal bidding.
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 99%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $5,673,000
TURF REPLACEMENT PROJECT
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: GeoSurfaces
Adopted Budget: $12,015,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Contractor continues to address outstanding punch list items relative to the
performance of the turf fields (Fields 5 & 6) at Bicentennial Park. It is anticipated that the fields will be
ready for the start of the games being played by DYB in March 2026.
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at Bob Jones
Park and Bicentennial Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 99%
CIP Funding Source(s): Southlake Parks Development
Corporation
FEBRUARY 2026 | 8CIP REPORT
MUNICIPAL SERVICE CENTER AND PUBLIC SAFETY TRAINING TOWER
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
Budget Adherence: On Target
Project Update: Byrne Construction Services had interruptions in Janurary due to the winter storm, but
continues to make steady progress on the construction of the Municipal Service Center and Public Safety
Training Tower. Sitework remains active with ongoing utility installations and preparation for vertical
construction on the project site. Public utility installation (water, sewer, storm drain) is anticipated to
be completed by mid-February. Electricians are completing the installation of electrical conduits in the
Service Bay Building and will be wrapping up conduit installation for the site. Grading operations are
now proceeding in preparation for paving of the fire lane. Once the fire lane is paved, the next phase will
be for construction to begin going vertical. Despite the weather delays, the project remains aligned with
the established construction timeline.
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 31%
CIP Funding Source(s): General Fund, Utility Fund, and
Crime Control Prevention District
Adopted Budget: $46,600,000
Future Planned Funding: $0
BIG BEAR CREEK IMPROVEMENTS NEAR TIMBER COURT
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 59%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $148,000
Future Planned Funding: $555,000 (Estimate)
Budget Adherence: On Target
FEBRUARY 2026 | 9CIP REPORT
E HIGHLAND/KIMBALL 8” SEWER LINE
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Future Planned Funding: $2,675,000 (Estimate)
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements will be re-starting in the
coming months. Initial offers were sent to four of the five property owners, with discussions held with
three; the fourth property was in transition when the offer was sent, and the fifth is under legal review
regarding prescriptive right-of-way. A meeting was held January 21st to discuss continuation of the
project, and another will be held in February to kick of coordination between City Staff and TNP’s
acquisition team to continue easement negotiations. Dependent on negotiation outcomes, alternative
alignments may need to be considered in order to move towards construction in Summer 2027. TNP will
be gathering some field information to support finalization of design in February.
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue.
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 63%
CIP Funding Source(s): Sanitary Sewer Impact Fee,
Utility Fund
Adopted Budget: $220,000
EAGLE BEND & STRATHMORE SANITARY SEWER RECONSTRUCTION
Department: Public Works
Engineering Firm: Peloton (now Westwood)
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Design reached 90 percent completion in
July 2024, and property owner coordination for easements is ongoing. One of the three permanent
easements has been acquired, while agreements with the Timarron HOA and Golf Course remain under
legal review. A required temporary easement has not yet been secured. The project is on hold due to
reprioritization and will resume as other projects conclude.
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76%
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000
Future Planned Funding: $775,000 (Estimate)
Budget Adherence: On Target
FEBRUARY 2026 | 10CIP REPORT
HIGGINS BRANCH NEAR WOODBROOK LN
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Coordination with property owners regarding
access easements is ongoing. Two temporary easements have been acquired, while one permanent
access easement remains under legal review. The project is on hold due to reprioritization and will
resume as other projects are completed.
Project Description: Provides erosion control and
sewer protection improvements along Higgins Branch
near Woodbrook Lane.
CIP Project Number: 2022-45c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 73%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $235,000
Future Planned Funding: $475,000 (Estimate)
Budget Adherence: On Target
JONES BRANCH NEAR RAINTREE DR.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: This is a companion project to Jones Branch near Simmons Court. Discussed with
Council at November 4th meeting for recommended design. City met with residents December 9th to
discuss the selected option, provide tentative schedule, and answer questions. A meeting was held with
Simmons Court residents on February 2, 2026 to review the proposed option. Following that meeting,
staff shared all options and requested resident feedback, with a submittal deadline of February 25.
Following this deadline, staff will prepare an update for the City Council.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 80%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $158,000
Future Planned Funding: $975,000 (Estimate)
Budget Adherence: On Target
FEBRUARY 2026 | 11CIP REPORT
JONES BRANCH NEAR SIMMONS CT
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: This project is a companion project to Jones Branch near Raintree Drive. Discussed with
Council at November 4th meeting for recommended design. City met with residents December 9th to
discuss the selected option, provide tentative schedule, and answer questions. Discussed with Council at
November 4th meeting for recommended design. City met with residents December 9th to discuss the
selected option, provide tentative schedule, and answer questions. A meeting was held with Simmons
Court residents on February 2, 2026 to review the proposed option. Following that meeting, staff shared
all options and requested resident feedback, with a submittal deadline of February 25. Following this
deadline, staff will prepare an update for the City Council.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 83%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $885,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
LONESOME DOVE/SHADY LANE LIFT STATION IMPROVEMENTS
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
Project Update: Since the previous update, limited construction activity has occurred. Two pumps
have been delivered and are currently stored on-site. The contractor has submitted a cost change
proposal related to piping materials, and revised submittals for the plug valves are anticipated shortly.
Staff continues to coordinate with the contractor and consultant to review the proposed changes and
associated lead times and will provide a schedule update once these items are resolved.
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target
FEBRUARY 2026 | 12CIP REPORT
MORGAN ROAD DRAINAGE IMPROVEMENTS
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Project Update: No major changes since last update; coordination with residents on final design
recommendations has been completed, with approval secured to place underground drainage
improvements in the existing drainage easement. A secondary kick-off meeting with the consultant
was held in September to confirm the design approach and review the current project needs. The 95%
milestone design was submitted early November, and comments have been returned to the consultant.
Final design is expected to be completed in February, along with further community and Franchise
Utility coordination.
Project Description: Constructs a new drainage ditch,
culvert, and channel to reduce flooding risk on Morgan
Road.
CIP Project Number: 2022-47
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 80%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $228,000
Future Planned Funding: $600,000 (Estimate)
Budget Adherence: On Target
FLORENCE ELEVATED STORAGE TANK REPAINTING
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
Project Update: All franchise utility equipment has been successfully been relocated to temporary
facilities. The Notice to Proceed was issued on January 16, 2026, and the contractor has mobilized and is
currently performing rigging and installation of the containment system. The Florence Elevated Storage
Tank is scheduled to be taken ouf of service on February 3, 2026, at which point draining of the tank will
allow both exterior and interior rehabilitation work to proceed.
Project Description: Repaints and repairs the Florence
Elevated Storage Tank to extend its service life and
protect water quality.
CIP Project Number: 2022-37
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 5%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,745,000
Future Planned Funding: $0
Budget Adherence: On Target
FEBRUARY 2026 | 13CIP REPORT
TW KING PUMP STATION #2 BUILDOUT PHASE I
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Design work continues, with the 60% milestone design submitted in November. Staff
feedback has been provided and more detailed coordination has been completed as they work towards
a 90% design submittal expected February 2026. TDEM and FEMA reviews of the generator grant
application are complete, and our project has been selected as an alternate. Alternate projects are
funded until after primary projects and may not receive funding. As FEMA has not provided an award
timeline and generator lead times are significant, staff may withdraw the application if confirmation is
not received in the coming months for funding.
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 86%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements will be re-starting in the
coming months. Initial offers were sent to four of the five property owners, with discussions held with
three; the fourth property was in transition when the offer was sent, and the fifth is under legal review
regarding prescriptive right-of-way. A meeting was held January 21st to discuss continuation of the
project, and another will be held in February to kick of coordination between City Staff and TNP’s
acquisition team to continue easement negotiations. Dependent on negotiation outcomes, alternative
alignments may need to be considered in order to move towards construction in Summer 2027. TNP will
be gathering some field information to support finalization of design in February.
Project Description: Replaces the existing 6-inch water
line with a 12-inch line to improve service and capacity.
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.
CIP Project Number: 2022-28c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 64%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $825,000
Future Planned Funding: $2,425,000 (Estimate)
UPSIZE EXISTING 6-INCH TO 12-INCH WATER LINE ALONG EAST HIGHLAND FROM
BLYTHE LANE TO NORTH KIMBALL AVENUE