CM Report - 3B - 2 - CIP Report - October 2025CAPITAL
IMPROVEMENTS
PROGRAM
REPORT
OCTOBER 2025
r e
c_d
IL
No Text
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City's progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description - A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status - A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase - Indicates the current phase of the project.
• Overall Progress (Current Phase) - Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget - The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding: The amount of funding currently planned for future fiscal years. Typicially
these will be an estimate based on the design.
• Budget Adherence - Shows whether the project is currently under budget, on target, or over
budget.
• Project Update - Gives a short summary of progress since the previous month, highlighting major
milestones, current work, upcoming activities, or public impacts. Updates are intentionally brief,
focusing on information most relevant to City Council and the public.
• Department / Engineering Firm / General Contractor - Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
No Text
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane.
CIP Project Number: 2022-02
Project Status: On Hold
Project Phase: Pre -Design .• m
Overall Progress (Current Phase): 36%
CIP Funding Source(s): General Fund
Adopted Budget: $465,000 r
x
Budget Adherence: On Target
=
Project Update: Phase 1 design has been completed,
and a detailed application for TxDOT funding covering
all four phases was submitted on June 19, 2025.The project is paused pending review and award of
funding, with a decision now expected early November 2025.
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
FM • • & PEARSON•IMPROVEMENTS
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
JORPMO„
Pearson.
CIP Project Number: 2022-13c
R4IM9;
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller+
Adopted Budget: $960,000
a
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 11
Project Description: Adds deceleration lanes at Byron
Nelson Parkway and Southridge Lakes Parkway with
enhanced landscaping.
a
ouwownw 9J
CIP Project Number: 2022-06
Project Status: In Progress HNH Sf
Project Phase: Closeout.
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund
Adopted Budget: $1,200,000
mom
Budget Adherence: On Target �'°
Project Update: Coordination with TxDOT has .14
continued in order to address punch list items. Restoration work began mid -September. Staff and
TxDOT continue to work with contractor to address outstanding items. Restoration work projected to be
complete by the end of October, at which point TxDOT and City will re -inspect for approval and close-
out of project.
Department: Public Works
Engineering Firm: Kimley-Horn
General Contractor: EARTC
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental
Intersection Improvements.
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 1%
F ye 51
nay 3
>
Project Locations
_W
�1�
o
,n•µ a
2
CIP Funding Source(s): General Fund, Roadway Impact ,
Fee Fund, Tarrant County Bond a
Adopted Budget: $8,900,000 s
Budget Adherence: On Target
Project Update: A pre -construction meeting with the contractor was held at the end of June. The
temporary driveway near Primrose School is expected to be constructed the week of October 13.
Franchise utilities are still working in the area but have cleared enough to allow construction to begin.
Preparation for construction is underway, and the closure of Union Church Road is scheduled for the
week of November 3rd, weather permitting.
Department: Public Works
Engineering Firm: Kimley-Horn
General Contractor: McMahon Contracting LP
CIP REPORT
OCTOBER 2025 12
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15
Project Status: In Progress 4
Project Phase: Design -
Overall Progress (Current Phase): 26%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $1,975,000
Budget Adherence: On Target
Project Update: The City's consultant is in the process
of creating new roadway alignment proposals, following initial ROW negotiations with neighboring
properties.
Department: Public Works
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
Project Description: Improves the corridor with
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 30%
CIP Funding Source(s): General Fund
Adopted Budget: $2,070,000
Budget Adherence: On Target
SOLMLAKE BLVD
Project Update: There has been no major change bI j 1 12 !
on the project since the last update. Construction was recently completed on Phase 3 near the DPS
Headquarters. Staff also met with business owners on North Carroll Avenue near Lakewood Drive to
discuss driveway access concerns. Kimley-Horn is evaluating potential solutions, and the contractor
has temporarily paused work until the SH 114 signal poles are delivered or an alternative design for
Lakewood Drive is determined.
Department: Public Works
Engineering Firm: Kimley-Horn
General Contractor: Tejas Cutters
CIP REPORT
OCTOBER 2025 13
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements. N
F7
CIP Project Number: 2022-33c P.—A-LN r IPL
Project Status: In Progress 1.
Project Phase: Construction W%"`°'"`°"
Overall Progress (Current Phase): 1%s
%.AMATIDM d!
il6CAM �CCIR
CIP Funding Source(s): General Fund, Utility Fund, s
Water Impact Fee Fund .�.a...o
Adopted Budget: $3,400,000 FT/
Budget Adherence: On Target
Project Update: Construction was awarded to Quality Excavation at the August 19, 2025 City Council
meeting. A pre -construction conference was held September 16, and material submittals and review are
still ongoing. Franchise utility work is underway in the area, but this work is in a limited portion of the
project limits. Construction began October 6th with erosion control and tree removal. The contractor will
begin installing temporary above ground waterline in coming days in advance of the permanent water
line replacement.
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard
and South Peytonville Avenue intersection. This project
is a companion project to FM 1938 & Continental Blvd.
Intersection Improvements.
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 1%
F ye 51
Project Locations
_W
g
z
CIP Funding Source(s): General Fund, Utility Fund, '
Roadway Impact Fee Fund, Storm Water Utility System, �
Tarrant County Bond -
Adopted Budget: $6,185,000
Budget Adherence: On Target
Project Update: No major changes since last update. This project is a companion to the FM1938 and
Continental Boulevard intersection improvements. The contract was awarded to McMahon Contracting
late May 2025, and work on this phase will not begin until the substantial completion of the companion
project to minimize mobility impacts. The anticipated start is approximately 18 months after the FM1938
and Continental phase begins.
Department: Public Works
Engineering Firm: Kimley-Horn
General Contractor: McMahon Contracting LP
CIP REPORT
OCTOBER 202b 14
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 100%
CIP Funding Source(s): TxDOT Green Ribbon Funding
Adopted Budget: $400,000
Budget Adherence: On Target
Project Update: Phase 1 has been completed at Dove
Road and 114 on the South side of the Intersection. The
project is now in the warranty period and temporary irrigation will be on -site until the plants are stable
enough to remove. The project was funded by a fully reimbursable $400,000 grant from TxDOT. This is
the final month that this project will be included in this report.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: C. Green Scalping
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Bidding/Pre-Con
Overall Progress (Current Phase): 80%
CIP Funding Source(s): TxDOT Green Ribbon Funding
Adopted Budget: $400,000
Budget Adherence: On Target
Project Update: Phase 2 design is complete and theGREEN RIBBON PROJECT PHA:
SOUTH SIDEOF DOVE RD & SH 114 INTERSEC_
project has been bid. Bid opening was completed
in late July and the City and design consultants are working with TxDOT to receive concurrence on
the lowest qualified bidder with hopes of bringing a bid award to Council in the coming months.
Construction is set to begin late this year. The project will be funded by a $400,000 fully reimbursable
grant by TxDOT.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 15
Project Description: Enhances intersections on SH 114
with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Pre -Design
Overall Progress (Current Phase): 10%
CIP Funding Source(s): TxDOT Green Ribbon Funding
Adopted Budget: $420,000
Budget Adherence: On Target
Project Update: Phase 3 was awarded the full
$420,000 to begin work at the intersection of White
Chapel and SH 114. City staff are working with the design consultant and TxDOT on phase 3 of this
project and have conducted a project kick-off and preliminary design work. City staff will be bringing
forward an Advanced Funding Agreement for phase 3 of this project in the coming months.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
Project Description: Constructs landscape, irrigation,
and hardscape improvements on FM 1938 from FM 1709
to the Southlake City limits, consistent with landscaped
median improvements north of FM 1709. The City's
scope includes landscape, irrigation, and hardscape
only.
CIP Project Number: 2024-06
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): General Fund
Adopted Budget: $1,650,000
Budget Adherence: On Target
s«WORK K4N,�°o
�� 1--
UMW —
PR
[ol� rQ'mN�,LL
m� o a.ao�a�
*i�eecaa ,EQ �siaaa tpn slrom
.�48
Qa
v a
Project Update: No major changes since last update. The most recent milestone is that the City received
correspondence form the Area Engineer that TxDOT would not be including the City's landscaping work
into it's median construction project on FM1938. Staff continues to keep communication open with
TxDOT, so that this project can be incorporated into TxDOT's contractor's scope of work.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 16
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 20%
CIP Funding Source(s): General Fund, Utility Fund,
Crime Control Prevention District
Adopted Budget: $46,600,000
Budget Adherence: On Target
Project Update: Construction is underway with ongoing utility installation, site grading, and preparations
for concrete work, including boring beneath Brumlow Avenue for the site's water connection.
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 25%
CIP Funding Source(s): Southlake Parks Development
Corporation, Hotel Occupancy Tax Fund
Adopted Budget: $7,938,319
Budget Adherence: On Target
Project Update: The most recent milestone was the award of the design agreement to Kimley-Horn
Associates on June 3, 2025. The schedule is currently being revised as staff has determined that this
project will be best delivered via the construction manager at -risk (CMAR) delivery method.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 17
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $5,673,000
Budget Adherence: On Target
Project Update: The City reviewed the design consultant's 60% design submittal. The consultant is
advancing to the 90% Plans, Specs, and Opinion of Probable Cost, expected in November 2025.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown (BHB)
General Contractor: Not Awarded Yet
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at Bob Jones
Park and Bicentennial Park.
CIP Project Number: 2024-05 1
Project Status: In Progress
Project Phase: Closeout
Overall Progress (Current Phase): 95%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $12,015,000
Budget Adherence: On Target
Project Update: Contractor continues to address outstanding punch list items relative to the
performance of the turf fields at Bicentennial Park.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown (BHB)
General Contractor: GeoSurfaces
CIP REPORT
OCTOBER 2025 18
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 59%
CIP Funding Source(s): Storm Water Utility System,
Utility Fund
Adopted Budget: $148,000
Budget Adherence: On Target
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue. s
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c v
Project Status: On Hold j
Project Phase: ROW/ Easement Acquisition EHMHLAHD
Overall Progress (Current Phase): 63%
CIP Funding Source(s): Sanitary Sewer Impact Fee,
Utility Fund
Adopted Budget: $220,000
Budget Adherence: On Target
Project Update: No major changes since last update. This project is a companion to the East Highland
Water Line Upsize. Coordination with property owners is ongoing, with initial offers were sent to four of
five property owners. Discussions were held with three, while ownership of the fourth property was in
transition. The fifth is under legal review for prescriptive right-of-way. The project is scheduled to resume
Fall 2025, continued negotiations, finalization of design, and consideration of alternate alignments for
construction in Summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 19
Project Description: Replaces the existing 8-inch sewer zwn F
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76%
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000
Budget Adherence: On Target
E CONTINENTAL- BLVD
Lva w
Iva a ► war
Project Update: No major changes since last update.
Design reached 90 percent completion in July 2024,
and property owner coordination for easements is ongoing. One of the three permanent easements has
been acquired, while agreements with the Timarron HOA and Golf Course remain under legal review. A
required temporary easement has not yet been secured. The project is on hold due to reprioritization
and will resume as other projects conclude.
Department: Public Works
Engineering Firm: Peloton (Formerly Westwood)
General Contractor: Not Awarded Yet
Project Description: Provides erosion control and .aau.wrnau+
sewer protection improvements along Higgins Branch
near Woodbrook Lane.
CIP Project Number: 2022-45c��
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 73%
CIP Funding Source(s): Utility Fund, Storm Water
o
Utility System
Adopted Budget: $235,000 :
Budget Adherence: On Target
Project Update: Coordination with property owners regarding access easements is ongoing. Two
temporary easements have been acquired, while one permanent access easement remains under legal
review. The project is on hold due to reprioritization and will resume as other projects are completed.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 1 10 1
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c "
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 80% GRYiIi'
CIP Funding Source(s): Utility Fund, Storm Water"°`"
Utility System =
Adopted Budget: $158,000
Budget Adherence: On Target iya
Project Update: No major changes since last update. This is a companion project to Jones Branch
near Simmons Court. Replacement alternatives are under review, with staff preparing a life -cycle cost
analysis. Once a preferred option is selected in executive session, a new design contract will be needed
to resume design and easement acquisition.
Department: Public Works
Engineering Firm: Peloton (Formerly Westwood)
General Contractor: Not Awarded Yet
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51 w
Project Status: On Hold �w
Project Phase: Design
Overall Progress (Current Phase): 83%
CIP Funding Source(s): Utility Fund, Storm Water --GIN
Utility System :
Adopted Budget: $885,000
Budget Adherence: On Target IL
Project Update: No major changes since last update. This project is a companion project to Jones
Branch near Raintree Drive. Replacement alternatives are under review, with staff preparing a life -cycle
cost analysis. Once a preferred option is selected in executive session, a new design contract will be
needed to resume design and easement acquisition.
Department: Public Works
Engineering Firm: Peloton (Formerly Westwood)
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 111
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,810,000
Budget Adherence: On Target
Project Update: There has been no major change since ' ' - ' M, '""' ' %, '
the last update. A pre -construction meeting in April 2025. The contractor is still waiting on long -lead
electrical components before mobilizing. Construction is expected to begin once those materials are
delivered, which is projected for mid -November.
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
Project Description: Constructs a new drainage ditch, PL WASION DR
culvert, and channel to reduce flooding risk on Morgan
Road. 5 l' a
CIP Project Number: 2022-47
Project Status: In Progress
Project Phase: Design ,
Overall Progress (Current Phase): 66% z
CIP Funding Source(s): Storm Water Utility System L�
Adopted Budget: $228,000 LN
Budget Adherence: On Target"��
Project Update: Coordination with residents on final
design recommendations has been completed, with approval secured to place underground drainage
improvements in the existing drainage easement. A secondary kick-off meeting with the consultant
was held in September to confirm the design approach and review the current project needs. The next
milestone design set is expected to be submitted in October for review. Final design will be completed in
the coming months, with a CIP budget request to follow.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 112
Project Description: Repaints and repairs the Florence
Elevated Storage Tank to extend its service life and FLORENCErt�
protect water quality. �e
CIP Project Number: 2022-37
Project Status: In Progress
Project Phase: Bidding/Pre-ConLU
Overall Progress (Current Phase): 93%�
�
CIP Funding Source(s): Utility Fund jam -QON q[) �
Adopted Budget: $2,745,000
Budget Adherence: On Target
Project Update: Sealed proposals were received
and opened on September 11, 2025. City staff and the design consultant evaluated the submissions to
determine the best value to the City. Staff will recommend award of the construction contract to the
best value proposer at the November 4, 2025 City Council meeting.
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 69%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund, General Fund
Adopted Budget: $15,475,000
Budget Adherence: On Target
Project Update: Design work continues, with the backup generator design completed as part of the
most recent milestone. Staff are working with the consultant to finalize the remaining site design
and associated requirements with the next milestone review expected in December. TDEM has been
coordinating further with the City on the grant application for the generator, though the application is
still under review. As FEMA has not provided a set award date and grants are distributed based on a
priority list, staff may choose to withdraw the application by the end of the year or early next year if
confirmation is not received in a timely manner, in order to proceed with ordering the generators due to
their long lead times.
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 113
Project Description: Replaces the existing 6-inch watery a
line with a 12-inch line to improve service and capacity.
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.,R
CIP Project Number: 2022-28c
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition,
Overall Progress (Current Phase): 64%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $825,000
Budget Adherence: On Target
Project Update: There has been no major change since the last update. Coordination with property
owners for required easements is ongoing. Initial offers were sent to four of five property owners, with
discussions held with three. The fourth property was in transition when the offer was sent, and the fifth is
under legal review regarding prescriptive right-of-way. Although the project was placed on hold due to
reprioritization, it is scheduled to resume this fall with continued negotiations, finalization of design, and
consideration of alternate alignments for construction.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
OCTOBER 2025 114