ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress
of major infrastructure investments. This monthly report shares updates on all active Capital
Improvements Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City's progress in delivering CIP
projects, from early design through construction completion, ensuring transparency and
accountability in how public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description - A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status - A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase - Indicates the current phase of the project.
• Overall Progress - Percentage of completion for the current phase.
• Current Project Funding - The amount of funding currently awarded through the FY 2025
Capital Budget and prior fiscal years. This does not include planned funding for future fiscal
years.
• Future Planned Funding: The amount of funding currently planned for future fiscal years.
Typicially these will be an estimate based on the design.
• Budget Adherence - Shows whether the project is currently under budget, on target, or over
budget.
• Project Update - Gives a short summary of progress since the previous month, highlighting
major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department / Engineering Firm / General Contractor - Identifies the City department
managing the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
No Text
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane.
CIP Project Number: 2022-02
Project Status: On Hold
Project Phase: Pre -Design 'a
Overall Progress: 36%
Adopted Capital Budget: $465,000
Future Planned Funding: TBD - Pending grant request
Budget Adherence: On Target
Project Update: Phase 1 design has been completed, and a detailed application for TxDOT funding
covering all four phases was submitted on June 19, 2025. The project is paused pending review and
award of funding, with a decision expected in October 2025.
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
Pearson.
CIP Project Number: 2022-13
Project Status: On Hold
Project Phase: Design
Overall Progress: 90%
Adopted Capital Budget: $960,000
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: Design was completed in May 2024, but construction was placed on hold to prioritize
the Continental Intersections improvements in the corridor. Work will resume once those improvements
are complete to preserve alternate travel routes for residents.
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 11
Project Description: Adds deceleration lanes at Byron
Nelson Parkway and Southridge Lakes Parkway with
enhanced landscaping.
CIP Project Number: 2022-06
Project Status: In Progress
Project Phase: Closeout
Overall Progress: 99%
Adopted Capital Budget: $1,200,000
Future Planned Funding: $0
Budget Adherence: On Target
Q
4
- ; ■
Project Update: Coordination with TxDOT has continued to address construction punch list items. The
Byron Nelson turn lane was reworked in late August, and a Registered Accessibility Specialist confirmed
sidewalk compliance with Texas Accessibility Standards. Staff and TxDOT are now working with the
contractor to replace defective sidewalk panels near Southridge Lakes, with restoration work scheduled
to begin in mid -September. TxDOT will reinspect once the work is complete.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: EARTC
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce,,.,w:
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental o
Intersection Improvements. Project Location����
CIP Project Number: 2022-07� Z
Project Status: In Progress
Project Phase: Construction
Overall Progress: 0%
UNION CHURCH
Adopted Capital Budget: $8,900,000
Future Planned Funding: $0 sF5
Budget Adherence: On Target
Project Update: A pre -construction meeting with the contractor was held at the end of June. A
temporary driveway for the Primrose School has been coordinated, and construction of the driveway will
occur before Union Church Road is closed. Franchise utilities are relocating, and construction is expected
to begin once utilities are cleared.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
CIP REPORT
SEPTEMBER 2025 12
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15
Project Status: In Progress
Project Phase: Design
Overall Progress: 26%
Adopted Capital Budget: $1,975,000
Future Planned Funding: Pending final design
Budget Adherence: On Target
F261
Project Update: The City is coordinating an access easement on the Sunoco site in connection with the
Municipal Service Center and Public Safety Training Tower project.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Description: Improves the corridor with
E HIGHLAND IT
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09"
Project Status: In Progress j
Project Phase: Construction r
e !
Overall Progress: 16% M
Adopted Capital Budget: $2,070,000
Future Planned Funding: $0
Budget Adherence: On Target L. BLVD
S
Project Update: Construction was recently completed on Phase 3 near the DPS Headquarters. Staff
met with business owners on North Carroll Avenue near Lakewood Drive to discuss driveway access
concerns. Kimley-Horn is evaluating potential solutions, and the contractor has temporarily paused work
until the SH 114 signal pole is delivered or an alternative design for Lakewood Drive is determined.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
CIP REPORT
SEPTEMBER 2025 13
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randol Mill Avenue, along with drainage
N
improvements.
CIP Project Number: 2022-33
PHCASA NT LN Yr�nL
Project Status: In Progress
WLKs�, r
Project Phase: Bidding/Pre-Cons
Overall Progress: 97/
-ATIOX OR
Adopted Capital Budget: $3,400,000
�
Future Planned Funding: $0
Budget Adherence: On Target
3
Project Update: Construction was awarded to Quality Excavation at the August 19, 2025 City Council
meeting. Contract documents have been executed, a pre -construction conference is scheduled for
September 16, and material submittals are under review.
Construction is expected to begin in the fall
pending completion of franchise utility relocations.
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
S. PEYTONVILLE•
•N IMPROVEMEN
Project Description: Installs a landscaped roundabout
drainage the Continental Boulevard
I I
1 ILL` a
with upgrades at
,
and South Peytonville Avenue intersection. This project
o
is a companion project to FM 1938 & Continental Blvd.-
q
c
Intersection Improvements.
n
n
CIP Project Number: 2022-17
R
Project Status: In Progress
7UNIONC.H
Project Phase: Construction
a
Overall Progress: 0%
_
Adopted Capital Budget: $6,185,000
Future Planned Funding: $0
Budget Adherence: On Target 4
Project Update: This project is a companion to the FM 1938 and Continental Boulevard Intersection
Improvements. The contract was awarded to McMahon Contracting in late May 2025, and work on this
phase will not begin until substantial completion of the companion project to minimize mobility impacts.
The anticipated start is approximately 18 months after the FM 1938 and Continental phase begins.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
CIP REPORT
SEPTEMBER 202b 14
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Closeout
Overall Progress: 0%
Adopted Capital Budget: $400,000
Budget Adherence: At Budget
Project Update: Phase 1 at Dove Road and State Highway 114 has been completed and is now in the
warranty period, with temporary irrigation in place until the plants are established. The project was
funded by a fully reimbursable $400,000 TxDOT grant.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: C. Green Scalping
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Bidding/Pre-Con
Overall Progress: 0%
Adopted Capital Budget: $400,000
Future Planned Funding: $0
Budget Adherence: At Budget
a
r
Project Update: Phase 2 design is complete, and the project has been bid. The City and partner
consultant from Kimley Horn has submitted the lowest qualified bid to TxDOT for certification prior
to bringing an award to Council in the coming months. Construction is set to begin late this year.
Construction for this project will be funded by a $400,000 fully reimbursable grant by TxDOT.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 15
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07
Project Status: In Progress
Project Phase: Pre -Design,;, - E
Overall Progress: 0%
- =
Adopted Capital Budget: $420,000
Future Planned Funding: $0
Budget Adherence: At Budget
I - SWEHWY 1,,
Project Update: Phase 3 has received the full $420,000 funding allocation for work at the White Chapel
and State Highway 114 intersection. City staff in conjunction with the consultant team from Kimley Horn,
held a kickoff meeting with TxDOT in August and will be bringing for the phase 3 consultant agreement
and advanced funding agreement with TxDOT to council in the near future.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Description: Constructs landscape, irrigation,
and hardscape improvements on FM 1938 from FM 1709
to the Southlake City limits, consistent with landscaped
median improvements north of FM 1709. The City's
scope includes landscape, irrigation, and hardscape
only.
CIP Project Number: 2024-06
Project Status: In Progress
Project Phase: Design
Overall Progress: 0%
Adopted Capital Budget: $1,650,000
Future Planned Funding: $0
Budget Adherence: On Target
SOUTHLAKEO F
•eI FM 17IK
Ne k � "I,o
LIMITS 4 WORK W/IN e�
SOUTHLAKE CITY LIMITS
LIMITS OF T.DOT _ti
PROJECT
L me.4 A Wg a d �n.mleiexe wc+e
%3
C
aelaaeae�
TIL[a�xnrvliEO �EgERAIp XILIS
m �rvp
Project Update: The City received correspondence from the Area Engineer confirming that TxDOT will
not include the City's landscaping work in the FM 1938 median construction project. Staff is maintaining
communication with TxDOT to allow this work to be incorporated into the contractor's scope.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 16
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79
Project Status: In Progress
Project Phase: Construction
Overall Progress: 45%
Adopted Capital Budget: $46,600,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: A Notice to Proceed with Construction was issued on August 7, 2025. Grading has
begun, and under the agreement, the final completion date is scheduled for the third quarter of Fiscal
Year 2027.
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66
Project Status: In Progress
Project Phase: Design
Overall Progress: 0%
Adopted Capital Budget: $7,938,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The design agreement with Kimley-Horn Associates was awarded on June 3, 2025. The
project schedule is being revised to reflect delivery through the construction manager at -risk method.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 17
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Design
Overall Progress: 0%
Adopted Capital Budget: $5,673,000
Future Planned Funding: TBD - Pending final design
Budget Adherence: On Target
Project Update: The design agreement with BHB was awarded on June 3, 2025, and design completion
is anticipated in the second quarter of Fiscal Year 2026.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: Not Awarded Yet
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at Bob Jones
Park and Bicentennial Park.
CIP Project Number: 2024-05
Project Status: In Progress
Project Phase: Closeout
Overall Progress: 95%
Adopted Capital Budget: $12,015,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: The contractor is in the process of completing punch list items.
Department: Community Services
Engineering Firm: BHB
General Contractor: GeoSurfaces
CIP REPORT
SEPTEMBER 2025 18
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress: 59%
Adopted Capital Budget: $148,000
Future Planned Funding: $555,000 (Estimate)
Budget Adherence: On Target
W COHnNOf/LL BLVD q
F
Project Update: Design reached 90 percent completion in July 2024, after which the project was placed
on hold due to reprioritization. Staff has been coordinating with a Colleyville resident regarding a
required sanitary sewer easement. Work will resume as other projects are completed or reprioritization
occurs.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Description: Installs a new 8-inch sewer line
along East Highland Street to North Kimball Avenue. #
This project is a companion project to the upsize
existing 6-inch to 12-inch Water line along East z
Highland from Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85 :
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition e�sT
Overall Progress: 63%
j
Adopted Capital Budget: $220,000
Future Planned Funding: $2,675,000 (Estimate)
Budget Adherence: On Target
Project Update: This project is a companion to the East Highland Water Line Upsize. Coordination
with property owners for easements is ongoing, with initial offers sent to four of five property owners.
Discussions are active with three, while ownership of the fourth property is in transition. The fifth is under
legal review for a prescriptive right-of-way. The project is scheduled to resume in fall 2025, with design
finalization and alternative alignments identified for construction in summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 19
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress: 76%
Adopted Capital Budget: $200,000
Future Planned Funding: $975,000 (Estimate)
Budget Adherence: On Target
4
$ pC
--,A N --H WAY
Project Update: Design reached 90 percent completion in July 2024, and property owner coordination
for easements is ongoing. One of three permanent easements has been acquired, while agreements with
the Timarron HOA and Golf Course remain under legal review. A temporary easement has not yet been
secured. The project is on hold due to reprioritization and will resume as other projects conclude.
Department: Public Works
Engineering Firm: Westwood (formerly Peloton)
General Contractor: Not Awarded Yet
Project Description: Provides erosion control and
sewer protection improvements along Higgins Branch PHRABAW`"
� n
near Woodbrook Lane.
¢ s �
CIP Project Number: 2022-45
PLAMMIM
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition^
Overall Progress: 73%
Adopted Capital Budget: $235,000�
Future Planned Funding: $475,000 (Estimate)
Budget Adherence: On Target
z
Project Update: Coordination with three property owners for easements is ongoing. Two temporary
easements have been acquired, while one permanent access easement remains under legal review. The
project is on hold due to reprioritization and will resume as other projects are completed.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 110
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45
Project Status: On Hold
Project Phase: Design �+
Overall Progress: 80%
RAWMAM W
Adopted Capital Budget: $158,000 `'C
Future Planned Funding: Pending final design "°' GR®CNOWGH LA
Budget Adherence: On Target
Vt8lt1N6 sN
Project Update: Alternatives for replacement are under review following discussions with residents
regarding property rights. Staff and the consultant are preparing life cycle cost comparisons and
evaluating options. The analysis will be presented in executive session, after which a new design contract
will be required to resume design and acquire easements.
Department: Public Works
Engineering Firm: Westwood (formerly Peloton)
General Contractor: Not Awarded Yet
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: On Hold
Project Phase: Design
Overall Progress: 83%
nw+m� w
Adopted Capital Budget: $885,000 t I
,ya4 6RBENBWfiN
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
ROLi1N6 hN
Project Update: This project is a companion to Jones Branch near Simmons Court. Replacement
alternatives are under review, with staff preparing a life cycle cost analysis. Once a preferred option is
selected in executive session, a new design contract will be needed to resume design and easement
acquisition.
Department: Public Works
Engineering Firm: Westwood (formerly Peloton)
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 111
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress: 0%
Adopted Capital Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target
W
a
Project Update: A pre -construction meeting with the contractor was held in April 2025. Electrical
components with long lead times have been ordered, and construction is expected to begin by year-end,
or sooner if materials arrive ahead of schedule.
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
Project Description: Constructs a new drainage ditch,
culvert, and channel to reduce flooding risk on Morgan f'
Road.
CIP Project Number: 2022-47 3 J
Project Status: In Progress
Project Phase: Design
Overall Progress: 59%
Adopted Capital Budget: $228,000 `
Future Planned Funding: $825,000 (Estimate)
Budget Adherence: On Target
TIONM DR
Project Update: Coordination with residents on final design recommendations has been completed,
with approval secured to place underground drainage improvements in the existing easement. Staff has
reviewed these recommendations with the consultant, and a secondary kick-off meeting is scheduled
for September to confirm the design approach. Final design is expected to be completed in the coming
months, with a CIP budget request to follow.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 112
Project Description: Repaints and repairs the Florence
Elevated Storage Tank to extend its service life and
FLORENCER❑
protect water quality.
c p m
CIP Project Number: 2022-37
uaE 1
Project Status: In Progress
Project Phase: Design
9
Overall Progress: 50%
3 �
"°° ��'
a z
$
Adopted Capital Budget: $2,745,000
JOF8t80NRD
a
Future Planned Funding: $0
Z
Budget Adherence: On Target
-
t
Project Update: A pre -bid meeting was held on August 26, and the bid opening is scheduled
for
September 11.
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96
Project Status: In Progress
Project Phase: Design
Overall Progress: 64%
Adopted Capital Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
r-�
11
Project Update: Design work continues, with the backup generator design completed as part of the
most recent milestone. Staff are working with the consultant to finalize the remaining site design and
requirements. The FEMA grant application for the generator is still under review, but since FEMA has not
provided an award date, staff may withdraw the application later this year or early next year to proceed
with ordering the generators due to long lead times.
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2�.__ 113
Project Description: Replaces the existing 6-inch water
line with a 12-inch line to improve service and capacity.
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.
CIP Project Number: 2022-28
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress: 64%
Adopted Capital Budget: $825,000
Future Planned Funding: $3,250,000 (Estimate)
Budget Adherence: On Target
WmR
Project Update: Coordination with property owners for required easements has advanced. Initial offers
were sent to four of five property owners, with discussions held with three. The fourth property was
in transition when the offer was sent, and the fifth is under legal review regarding a prescriptive right-
of-way. Although the project was placed on hold due to reprioritization, it is scheduled to resume this
fall with continued negotiations, finalization of design, and consideration of alternate alignments for
construction.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT
SEPTEMBER 2025 114