Loading...
CM Report - Capital Improvements Plan Monthly ReportCAPITAL IMPROVEMENTS PROGRAM REPORT AUGI All IL No Text ABOUT THE CIP REPORT The City of Southlake is committed to keeping the community informed about the progress of major infrastructure investments. This monthly report shares updates on all active Capital Improvements Program (CIP) projects. HOW TO READ THIS REPORT This monthly Capital Improvements Program (CIP) Report provides the current status of all active projects, meaning projects that are currently in preconstruction, which includes design, property or easement acquisition, study, or those actively in construction. Each project highlight includes key details such as its current phase, percentage of completion, adopted budget, and whether it is tracking under, at, or over budget. Only active projects are included in this report. Projects that have not yet entered preconstruction, or those that have been completed, are not shown here. By reviewing this report each month, readers can track the City's progress in delivering CIP projects, from early design through construction completion, ensuring transparency and accountability in how public funds are invested. UNDERSTANDING THE PROJECT HIGHLIGHTS Each project highlight includes: • Project Status - A quick reference to whether the project is on track, delayed, or otherwise impacted. • Project Phase - Indicates the current phase of the project. • Overall Progress - Percentage of completion for the current phase. • Current Project Funding - The amount of funding currently awarded through the FY 2025 Capital Budget and prior fiscal years. This does not include planned funding for future fiscal years. • Future Planned Funding: The amount of funding currently planned for future fiscal years. Typicially these will be an estimate based on the design. • Budget Adherence - Shows whether the project is currently under budget, at budget, or over budget. • Project Update - Gives a short summary of progress since the previous month, highlighting major milestones, current work, upcoming activities, or public impacts. Updates are intentionally brief, focusing on information most relevant to City Council and the public. • Department / Engineering Firm / General Contractor - Identifies the City department managing the project and, if awarded, the firms responsible for design and construction. For full project descriptions and more details, visit www.CityofSouthlake.com/CIP. No Text Project Status: On Hold Project Phase: Pre -Design Overall Progress (Current Phase): 36% Current Project Funding: $465,000 Future Planned Funding: TBD - Pending grant request Budget Adherence: At Budget F w x 3 3 .ten W Project Update: The last milestone achieved was the completion of design for Phase 1. A detailed application for TxDOT funding was submitted on June 19 to encompass all four phases, and is currently under review. At present, the project is paused pending the review and funding award from TxDOT. The funding decision is expected to be announced in October 2025, at which point the project will resume. Department: Public Works Engineering Firm: KSA General Contractor: Not Awarded Yet Project Status: On Hold Project Phase: Design Overall Progress (Current Phase): 90% Current Project Funding: $960,000 Future Planned Funding: Pending final design Budget Adherence: At Budget � R41T . 011h f f Z Project Update: The most recent milestone was the completion of design in May 2024. Construction of the project was placed on hold to prioritize the Continental Intersections improvements in the corridor. The project will resume once those improvements are complete in order to maintain alternate means of travel for area residents. Department: Public Works Engineering Firm: DEC General Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 r FM • ' DECELERATION LANES AT BYRON• • Project Status: In Progress a U Project Phase: Closeout Overall Progress (Current Phase): 99% FM 7709' Current Project Funding: $1,200,000 Future Planned Funding: $0 Budget Adherence: At Budget ■ Project Update: The most recent milestone involved continued coordination with TxDOT to address identified construction punch list items. A Registered Accessibility Specialist (RAS) was brought in to ensure the sidewalks comply with Texas Accessibility Standards (TAS), and the final report has been received. Based on this report, TxDOT has agreed to remove a previously disputed item from the punch list. Currently, staff are working with TxDOT and the contractor to resolve remaining items, including addressing deficient sidewalk panels. In the coming weeks, restoration work will continue, including reworking the Byron Nelson Turn Lane to improve ride quality and replacing defective sidewalk panels near Southridge Lakes. Department: Public Works Engineering Firm: Kimley-Horn General Contractor: EARTC FM 1938 & CONTINENTAL•IMPROVEMENTS Project Status: In Progress s Project Phase: Construction 9�w c Project Location Overall Progress (Current Phase): 0% �R Current Project Funding: $8,900,000.• Future Planned Funding: $0 �. UNION CHURCFI Budget Adherence: At Budget Project Update: The pre -construction meeting was held with the contractor at the end of June. The contractor has since obtained the required TxDOT permit, and staff have been reviewing the contractor's submissions. Staff are coordinating with Charter and Tri-County on necessary relocations that conflict with the project improvements. Additionally, staff are evaluating the feasibility of prohibiting parking along Watermere Drive for the duration of the Union Church closure. The road closure of Union Church will begin after the franchise relocations are completed. Note: This project is a companion project to S. Peytonville & W. Continental Intersection Improvements. Department: Public Works Engineering Firm: Kimley Horn General Contractor: McMahon Contracting LP CIP MONTHLY REPORT AUGUST 2025 1 PA_ 2 Project Status: In Progress Project Phase: Design Overall Progress (Current Phase): 26% Current Project Funding: $1,975,000 Future Planned Funding: Pending final design Budget Adherence: At Budget 26 Project Update: The City is currently coordinating an access easement on the Sunoco site in conjunction with the Municipal Service Center & Public Safety Training Tower project. Department: Public Works Engineering Firm: Kimley-Horn General Contractor: Not Awarded Yet Project Status: In Progress Project Phase: Construction Overall Progress (Current Phase): 10% Current Project Funding: $2,070,000 Future Planned Funding: $0 Budget Adherence: At Budget E HIGHLAND ST 3 I � 9 SOUTHLAIE BLVD � b s a., Project Update: Construction on the southern phase began in early July. In the coming weeks, pavement markings and signage will be installed along Carroll Avenue at Main Street and FM 1709, and the contractor will begin work on the median near the Carroll Pointe Shopping Center, adjacent to the DPS Headquarters. Staff is also coordinating with the Fire Station regarding a temporary signal outage during final rerouting work. Staff met with business owners at the intersection of Carroll Avenue and Lakewood Drive to discuss concerns about limited access to their driveway. A follow-up meeting is being scheduled to explore potential access solutions. If an option is agreed upon, staff will coordinate with Kimley-Horn to evaluate its feasibility and, if viable, proceed with design and a contractor change order. Department: Public Works Engineering Firm: Kimley-Horn General Contractor: Tejas Cutters CIP MONTHLY REPORT AUGUST 20251 Pf.__ 3 RANDOL MILL WATER LINE UPSIZING' • Project Status: In Progress Project Phase: Bidding/Pre-Con N MDCNInG tlIRa Ln - PHEASANT LN we Overall Progress (Current Phase): 89% OEMAL OAKIoA Current Project Funding: $3,400,000 LL RAry A i Dn tA Future Planned Funding: $0 s Budget Adherence: At Budget L r Project Update: The most recent milestone was the completion of design and the advertisement of the project for proposals in May. Proposals were reviewed and scored by the evaluation committee based on best value. A construction contract will be recommended for award to Quality Excavation at the August 9 Council meeting. Construction is expected to begin in the fall, pending completion of franchise utility relocations. Department: Public Works Engineering Firm: KSA eneral Contractor: Not Awarded Yet S. PEYTONVILLE• •N IMPROVEMEN Project Status: In Progress s _ Project Phase: Construction 0 Project Location �.. Overall Progress (Current Phase): 0% Z w Current Project Funding: $6,185,000 Future Planned Funding: $0 �.. uNioHCF[rtxw Budget Adherence: At Budget r Project Update: The project, combined with the FM 1938 and Continental Boulevard intersection im- provement, was awarded to McMahon Contracting, LP in late May 2025. Work on this phase will not begin until the substantial completion of the FM 1938 and Continental Boulevard intersection improve- ments to minimize mobility impacts. The anticipated start is approximately 18 months after the FM1938 and Continental phase begins. Note: This project is a companion project to FM 1938 & Continental Blvd. Intersection Improvements. Department: Public Works Engineering Firm: Kimley Horn eneral Contractor: McMahon Contracting LP CIP MONTHLY REPORT AUGUST 20251 PAGE 4 Project Status: In Progress Project Phase: Design Overall Progress (Current Phase): 30% Current Project Funding: $1,650,000 Future Planned Funding: TBD - Pending TxDOT Budget Adherence: At Budget „ �p�soumuKeo � . so uae ary uMis u ,T m Q " M 0 0.,......«« - Project Update: The City of Southlake recently received correspondence form the Area Engineer at TxDOT notifying us that they would not be including the City's landscaping work into their median construction project on FM 1938. Staff continues to keep communication open with TxDOT, to seek solutions to including this project into TxDOT's contractor's scope of work. Department: Community Services Engineering Firm: Kimley-Horn General Contractor: Not Awarded Yet Project Status: In Progress Project Phase: Closeout Overall Progress (Current Phase): 100% Current Project Funding: $470,000 Future Planned Funding: $0 Budget Adherence: At Budget Project Update: Phase 1 has been complete at Dove Road and SH 114 on the south side of the intersection. The project is now in the warranty period and temporary irrigation will be on -site until the plants are stable enough to remove. The construction portion of this project was funded by a fully reimbursable $400,000 grant from TxDOT. Department: Community Services Engineering Firm: Kimley Horn General Contractor: C. Green Scalping CIP MONTHLY REPORT AUGUST 20251 PA__ 5 Project Status: In Progress Project Phase: Bidding/Pre-Con Overall Progress (Current Phase): 80% Current Project Funding: $470,000 Future Planned Funding: $0 Budget Adherence: At Budget Project Update: Phase 2 design is complete and the project has been bid. Bid opening was completed in late July and the City and design consultants are working through the bids with hopes of bringing a bid award to Council in the coming months. Construction is set to begin late this year. The construction for this project will be funded by a $400,000 fully reimbursable grant by TxDOT. Department: Community Services Engineering Firm: Kimley Horn General Contractor: Not Awarded Yet Project Status: In Progress Project Phase: Pre -Design Overall Progress (Current Phase): 10% Current Project Funding: $490,000 Future Planned Funding: $0 Budget Adherence: At Budget �1 s,�tiFP,yEl_,_� EAEEk�IAM1'I yy `l �T�•1�w1' '. .- 1161T'vliM W SIATE HWY 11 Project Update: Phase 3 was awarded the full $420,000 to begin construction at the intersection of White Chapel and SH 114. City staff, the design consultant, and TxDOT held a project kick-off meeting in early August. Department: Community Services Engineering Firm: Kimley Horn General Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 PAGE 6 Project Status: In Progress Project Phase: Construction i Overall Progress (Current Phase): 5% Current Project Funding: $46,600,000 Future Planned Funding: $0 Budget Adherence: At Budget Project Update: Staff issued the CMAR the issuance of the Notice to Proceed with Construction on August 7, 2025. Construction activities are anticipated to commence shortly and per the agreement, the anticipated final completion date is Q3 FY 2027, weather permitting. Department: Public Works Engineering Firm: RPGA (Architect) General Contractor: Byrne (CMAR) Project Status: In Progress Project Phase: Design Overall Progress (Current Phase): 20% Current Project Funding: $7,938,319 Future Planned Funding: Pending final design Budget Adherence: At Budget Project Update: City Council awarded the design agreement to Kimley-Horn Associates in June 2025. The schedule is currently being revised as staff has determined that this project will be best delivered via the construction manager at -risk (CMAR) delivery method. Department: Community Services Engineering Firm: Kimley-Horn General Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 2025 1 PAG 7 Project Status: In Progress Project Phase: Closeout Overall Progress (Current Phase): 95% Current Project Funding: $12,015,000 Future Planned Funding: $0 Budget Adherence: At Budget Project Update: The contractor is completing punch list items on the project. Department: Community Services Engineering Firm: Baird, Hampton & Brown (BHB) General Contractor: GeoSurfaces Project Status: In Progress Project Phase: Design Overall Progress (Current Phase): 30% Current Project Funding: $5,673,000 Future Planned Funding: TBD - Pending final design Budget Adherence: At Budget Project Update: The most recent milestone was the award of the design agreement to BHB on June 3, 2025. The design is anticipated to be completed in early 2026. Department: Community Services Engineering Firm: Baird, Hampton & Brown (BHB) General Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 P 8 ct Status: On Hold ct Phase: ROW/ Easement Acquisition rail Progress (Current Phase): 59% urrent Project Funding: $148,000 uture Planned Funding: $555,000 (Estimate) udget Adherence: At Budget ;' w cownMffAL BLVD ir &0 roject Update: The 90% design was completed in July 2024, after which the project was placed on old due to reprioritization. Staff has been coordinating with a Colleyville resident regarding a required anitary sewer easement for the safe relocation of the sewer main. The project will resume as other rojects are completed or if reprioritization becomes necessary. epartment: Public Works ngineering Firm: VRX eneral Contractor: Not Awarded Yet ct Status: On Hold ct Phase: ROW/ Easement Acquisition rail Progress (Current Phase): 63% urrent Project Funding: $220,000 uture Planned Funding: $2,675,000 (Estimate) dget Adherence: At Budget ■ 0 a r � � S ►pG}IA AW SY Not Project Update: Staff is been working to coordinate with property owners for the purchase of easements required for the project. Initial offers were sent to four of the five property owners, with subsequent discussions held with three. Ownership of the fourth property was in transition when the offer was sent. The fifth property was submitted for legal review regarding an attorney opinion on a prescriptive right- of-way. The project was placed on hold due to reprioritization but is scheduled to resume this fall, when negotiations with property owners will continue and design will be finalized. Additionally, city staff have identified alternate alignments that will allow for an alternative construction within the current CIP plan, scheduled for summer 2027. ,te: This project is a companion project to the upsize existing 6-inch to 12-inch Water line along East Highland from Blythe ne to North Kimball Avenue. epartment: Public Works ngineering Firm: TNP eneral Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 PAGE 9 ct Status: On Hold ct Phase: ROW/ Easement Acquisition rail Progress (Current Phase): 76% urrent Project Funding: $200,000 uture Planned Funding: $975,000 (Estimate) udget Adherence: At Budget F+E., CONTINENTAL BL'VD LOG,M, L1/pp[EM WAY wAN ayROKxels�, burn c a roject Update: The most recent milestone was 90% design was completed in July 2024, when oordination with property owners for the purchase of easements required for the project began. One f the three permanent easements has been acquired, while the easement for the Timarron HOA and imarron Golf Course remains under legal review for requested amendments to the agreement. An dditional property owner, from whom a temporary construction easement is needed, has not been Dceptive or cooperative. This project was subsequently placed on hold due to reprioritization. The roject will resume as other projects are completed or if reprioritization becomes necessary. epartment: Public Works ngineering Firm: Westwood (formerly Peloton) eneral Contractor: Not Awarded Yet ct Status: On Hold ct Phase: ROW/ Easement Acquisition II Progress (Current Phase): 73% urrent Project Funding: $235,000 uture Planned Funding: $475,000 (Estimate) udget Adherence: At Budget PHEASAIR LN w,�ner .atr�n.n RMALDAFSPR IUPCAN mPaean S Lnufit��N � PLANTATION DR TY➢CMI RIPG aR � .� e NEW CASTLER p � Y61K11WlWlY�i � qSf eulila a x� roject Update: The most recent milestone was coordination with three property owners for the urchase of easements required for the project. The two temporary easements have been acquired for ie project. The remaining easement, a permanent access easement, is under legal review. This project ,as placed on hold due to reprioritization. This project will be resumed as other projects are completed, r reprioritization becomes necessary. epartment: Public Works ngineering Firm: VRX eneral Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 PAo� 10 JONES BRANCH NEAR RAINTREE DRIVE Project Status: On Hold Project Phase: Design w�ycrx• � MH.,C�STI��T Overall Progress (Current Phase): 80%� G RMNRIEE LHE4.._ Current Project Funding: $1S8,000r„�} Future Planned Funding: Pending final design GREEHBQ 1GM Lh Budget Adherence: At Budget ROL67116LN lasements. roject Update: The most recent milestone was revisiting the replacement alternatives due to ongoing iscussions with area residents. Staff has been working with the consultant to review these alternatives nd obtain life cycle cost comparisons, along with the pros and cons of each option. We are now in the rocess of summarizing the analysis results to present for City Council direction. Once a path forward determined, a new design contract will be required to resume final design and acquire the necessary Department: Public Works Feneral ngineering Firm: Westwood (formerly Peloton) Contractor: Not Awarded Yet JONES BRANCH NEAR SIMMONSCOURT Project Status: On Hold Project Phase: Design w�+.a wrnaxrxr• MN.,CW"" Overall Progress (Current Phase): 80% ««waRRw RI NTNlE LN Current Project Funding: $88S,000 Future Planned Funding: $0 (Estimate) 4, GREEN&WGH LM Budget Adherence: At Budget _. gOLlJN4 LN Project Update: This project is a companion project to Jones Branch near Raintree Drive. The most recent milestone was revisiting the replacement alternatives due to ongoing discussions with area residents. Staff has been working with the consultant to review these alternatives and obtain life cycle cost comparisons, along with the pros and cons of each option. We are now in the process f summarizing the analysis results to present for City Council direction. Once a path forward is determined, a new design contract will be required to resume final design and acquire the necessary easements. Department: Public Works Engineering Firm: Westwood (formerly Peloton) General Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 202S I PAGI 11 ct Status: In Progress IJ ct Phase: Construction rail Progress (Current Phase): 0% urrent Project Funding: $2,810,000 uture Planned Funding: $0 udget Adherence: At Budget roject Update: The last milestone was the pre -construction meeting held with the contractor in arly April 2025. Since then, the contractor has ordered electrical components with long lead times. onstruction is expected to begin once these components arrive, which is currently projected for the -id of the year —though work may start sooner if the materials arrive ahead of schedule. epartment: Public Works ngineering Firm: Garver, LLC. eneral Contractor: Felix Construction ct Status: In Progress ct Phase: Design II Progress (Current Phase): 59% urrent Project Funding: $228,000 uture Planned Funding: $825,000 (Estimate) udget Adherence: At Budget i I 3 3 J PpRii LA LN Cpnss rinnFn na Y Project Update: The most recent milestone was the completion of coordination with residents on final design recommendations. Staff has received approval from property owners to place the drainage improvements within the existing drainage easement. A meeting with the design consultant is scheduled later in August to review the recommended design and finalize construction plans. Design will be completed in the coming months, with a CIP budget request planned for future construction. epartment: Public Works ngineering Firm: TNP eneral Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 2025 1 PAGE 12 ct Status: In Progress ct Phase: Design rail Progress (Current Phase): 80% urrent Project Funding: $2,745,000 uture Planned Funding: $0 udget Adherence: At Budget FWRMCE W s JOHNSCM MISLSIQE 4T � W � a ° RD s roject Update: The most recent milestone was the completion of design in early August. The project as advertised for proposals early August. A pre -bid meeting is scheduled for late August and proposals ill be due early September. Proposals will be reviewed, and the award is scheduled for the 2nd October ity Council meeting, with construction planned for this winter. epartment: Public Works ngineering Firm: Bartlett & West eneral Contractor: Not Awarded Yet ct Status: In Progress ct Phase: Design II Progress (Current Phase): 30% urrent Project Funding: $15,475,000 uture Planned Funding: $0 (Estimate) udget Adherence: At Budget roject Update: The most recent milestone was continued progress in project design, including the ompletion of the backup generator design. Staff will continue working with the consultant to finalize -ie remaining site design and associated requirements. Meanwhile, the FEMA grant application for the enerator is still under review. As FEMA has not provided a set award date and grants are distributed ased on a priority list, staff may choose to withdraw the application by the end of the year or early next ear if confirmation is not received in a timely manner, in order to proceed with ordering the generators ue to their long lead times. epartment: Public Works ngineering Firm: Freese and Nichols eneral Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 PAGE 13 ct Status: On Hold ct Phase: ROW/ Easement Acquisition rail Progress (Current Phase): 64% urrent Project Funding: $825,000 uture Planned Funding: $3,250,000 (Estimate) udget Adherence: At Budget Project Update: Staff has initiated coordination with property owners for the purchase of easements required for the project. Initial offers were sent to four of the five property owners, with subsequent discussions held with three. Ownership of the fourth property was in transition when the offer was sent. The fifth property was submitted for legal review regarding an attorney opinion on a prescriptive right- of-way. The project was placed on hold due to reprioritization but is scheduled to resume this fall, when negotiations with property owners will continue and design will be finalized. Additionally, city staff have identified alternate alignments that will allow construction. This project is a companion project to the East Highland/Kimball 8-inch Sewer Line. epartment: Public Works ngineering Firm: TNP eneral Contractor: Not Awarded Yet CIP MONTHLY REPORT AUGUST 20251 PAGE 14