Loading...
Item 4J - MemoItem 4J CITY OF SOUTH LAKE MEMORANDUM May 21, 2024 To: Alison Ortowski, City Manager From: Rob Cohen, Director of Public Works Subject: Approve contract change orders with Gliden Industries, LLC for a total not to exceed $782,000 for work necessary to complete the Emergency Operations Center Relocation project. Action Requested: Approve contract change orders with Gliden Industries, LLC for a total not to exceed $782,000 for work necessary to complete the Emergency Operations Center Relocation project. Background Information: The purpose of this item is to seek City Council approval of contract change orders with Gliden Industries, LLC (Gliden) for work required to complete the Emergency Operations Relocation Project for a total contract amount not to exceed $782,000. At its December 5, 2023, meeting, City Council approved a construction contract award for Gliden in an amount not to exceed $753,000 for the Emergency Operations Center Relocation project. The City issued the Notice to Proceed with construction activities on January 2, 2024. Gliden's scope of work for the project generally consisted of the following: selective demolition, tenant finish -out, modifications to existing mechanical, electrical, plumbing, information technology, and fire protection systems, and structural modifications to support operable partitions. In addition, Gliden would coordinate with the City's contractors that include, but are not limited to the following: access control, data equipment, fiber optic, A/V equipment, modular wall systems, radio communications, and furniture systems. During construction, when issues arise where the planned construction conflicts with existing facilities, when there is a product substitution request for any reason, a gap in the design, or a revision to original project assumptions, a Contract Change Order (CCO) will be issued to reconcile those issues. To date, six (6) CCOs have been Page 1 of 3 Item 4J issued for a current total contract amount of $745,803, leaving $7,197 in the remaining contingency. The most recent change order for $28,830 is required for work related to the HAM radio, as presented in item 41. Gliden's original scope of work involved providing a new pathway for low voltage/coaxial cabling to the new HAM radio room. Under the revised recommendation from the City's radio system vendor (MCA), Gliden would perform coring and preparation of the roof, to accommodate the new antennae systems. The cabling and antennae systems would be installed by MCA. The project is currently 85% complete, with remaining items including final connections to existing systems for HVAC and fire suppression, installation of the modular walls, installation of IT equipment, and other finish -outs. Because the project is CCPD funded and the next CCPD meeting is scheduled after the anticipated project completion, staff is seeking to preserve the remaining contingency for the project for any issues that arise in the final stages. Financial Considerations: A summary of the awarded budget, costs, and remaining contract balance for this project budget is shown in the following table. Table 1. Proiect Cost Breakdown. ITEM COST CONTRACT FUND BALANCE ORIGINAL AUTHORIZATION (12/05/2023) $753,000 CONSTRUCTION Awarded Construction Contract (Gliden) $654,000 $99,000 Contract Chanqe Orders (1 — 6) $91,803 $7,197 Revised contract amount of $782,000 1 1 $36,197 The funding for this additional authorization will be provided from the existing fund balance for the project in the FY 2024 Capital Improvements Program in the CCPD Fund. Strategic Link: This item links to the City's Strategy Map strategic focus area of Safety and Security and Financial Objective F2: Investing to provide & maintain high quality public assets. It is also included in the 2035 Health and Wellness Plan HW30.3. Citizen Input/ Board Review: The Crime Control and Prevention District (CCPD) Board reviewed the change orders at its May 14, 2024 meeting. Page 2 of 3 Item 4J Legal Review: The original construction contract agreement has been reviewed by the City Attorney. No additional review is required for this increase in authorization. Alternatives: The City Council may recommend approval or denial of the request. Staff Recommendation: Approve of contract change orders with Gliden Industries, LLC for a total not to exceed amount of $782,000 for work necessary to complete the Emergency Operations Center Relocation project. Supporting Documents: Attachment A: Contract Change Orders 01-06 Staff Contact: Rob Cohen, Director of Public Works Lauren LaNeave, Deputy Director of Public Works Administration Mamerto Estepa Jr, P.E., Project Manager Page 3 of 3