Loading...
Item 7A - SPIN Meeting Report SPIN MEETING REPORT SPIN Item Number: SPIN2023-15 City Case Number: ZA23-0045 Project Name: Carillon Parc SPIN Neighborhood: 3 Meeting Date: August 8, 2023 Meeting Location: 1400 Main Street, Southlake, TX City Council Chambers Total Attendance: 30 Hosts: Danny Batsalkin Applicant Presenting: John Terrell City Staff Present: Madeline Prater, Business Manager Town Hall Forums can be viewed in their entirety by visiting http://www.cityofsouthlake.com and clicking on “I Want to” and “View” “Video on Demand” – forums are listed under SPIN by meeting date. FORUM SUMMARY: Property Situation: Northeast corner of N. White Chapel Blvd. and E. Kirkwood Blvd. Development Details: • Proposing updates at Carillon Parc on approximately 42 acres located at northeast corner of North White Chapel Boulevard and East Kirkwood Boulevard within Spin Neighborhood number three. • Interim concept plan that did not get approved because it was presented for the library and performing arts for the city. City backed out of commitment due to financials and the economy. • Site Plan has been modified to accommodate a possible future library. • Revision number one would allow developer to commence construction of five single family homes on lots along Riviera. Approvals require all infrastructure to be in place and be approved by the city before construction begins. Reason is to make sure all utilities are in place. • Opportunity with five builders to do a project with St. Jude to build five model homes. • Revision number two would allow the developer flexibility to develop retail restaurant, office, or private club if public library is not built within the development, leaving option for library use. • Revision number three would allow the developer the option to combine the two buildings into one building allowing for potential underground parking. • Revision number four would allow an optional detention/retention pond with fountain if needed for storm drainage. Done only if right of way and access easement for the drainage to go across the other track is not obtained. Builder will assume cost of maintenance of the fountain. • Revision number five would allow dedication of future valet and drop-off to be provided in Phase 1A. Cost of roadway will be escrows within Phase 1. • Entrance from the frontage road along Highway 114 is the only spot that entrance can occur because of weaving requirements by TXDOT from the exit ramp of 114 down from Whites Chapel. Working with TXDOT on a program where they are going to reverse the ramps which would allow for two main entrances and exits on the frontage road. Asking the city to approve if the state changes the ramps and reverses them. Presentation: Online Comment, Questions, and Concerns Forms: Comment: It looks beautiful, and we are excited. Question: What will happen with traffic on White Chapel? Is there going to be any expansion of the road? Answer: Expanding Whites Chapel to a four-lane divided with a median with all the turn lanes that have been approved by the state will mirror what is South of SH114 coming all the way through to Kirkwood. Comment: I love the proposed changes. Question: When do you think the dirt moving is going to be done and roads complete? Answer: Late Fall. SPIN Meeting Reports are general observations of SPIN Meetings by City staff and SPIN Representatives. The report is neither verbatim nor official meeting minutes; rather it serves to inform elected and appointed officials, City staff, and the public of the issues and questions raised by residents and the general responses made. Responses as summarized in this report should not be taken as guarantees by the applicant. Interested parties are strongly encouraged to follow the case through the Planning and Zoning Commission and final action by City Council. Southlake Connect Results for the August 8, 2023, SPIN Town Hall Forum