Item 4F-4G Attachement AM E M O R A N D U M
TO:
FROM:
SUBJECT:
April 21, 2023
Alison Ortowski, Assistant City Manager
Rob Cohen, Director of Public Works
Wastewater Master Plan Modeling Recommendation
REQUEST
We respectfully recommend completing a modified wastewater system modeling prior to the
adoption of the updated Wastewater Master Plan, and request to enter into an agreement with
Freese and Nichols for these services. Freese and Nichols provided an updated scope of work
in November 2022, and we recommend proceeding with the scope as presented.
BACKGROUND
As required by charter, the City of Southlake updates certain master plan documents every four
years. The most recent Wastewater Master Plan was adopted in 2012 and utilized modeling from
2009 that identified needed improvements for current and future capacity. Since that time the City
has conducted flow monitoring with the Town of Westlake for the N-1 interceptor in 2016, and
flow monitoring along with smoke and dye testing in 2017 - 2018.
In 2021, Public Works and Planning & Development Services began preparations for a master
plan update, and with that the evaluation of updated studies and modeling to inform plan
recommendations. The following questions and information shaped the basis of the request and
recommendation above:
•What will modeling tell us that we don’t already know?
At a fundamental level, modeling the wastewater system will ensure that our system can
meet the demand of both our residential and day-time population. The modeling will also
inform us to direct resources toward correcting issues with current capacity and building
out our system to handle future capacity.
Our current knowledge of the wastewater system is largely based on the 2007 -2010
Sanitary Sewer Evaluation Study (SSES), which included the above referenced 2009
model. Since that time the North Service Area has had an increase in development, and
staff recommends modeling this area to best plan future capital projects and determine
the efficiency and capacity of the existing infrastructure.
•What needs to be further investigated?
The following summarizes the major items requiring further investigation:
o The original model only included all 10-inch mains and larger, and some 8-inch
mains (approximately 40% of the 2009 infrastructure), the proposed scope
Page 2
includes all wastewater lines within the North Service Area. This will allow for a
more accurate model.
o This model will inform issues with the design and capacity of existing infrastructure,
for example the Lonesome Dove lift station and wet well.
o Improve wastewater basin accuracy, including the design of flow, volume, and
capacity throughout the basins. The City is divided into two service areas (north
and south) and within these areas are basins that map where wastewater collects
before flowing to the outfall area.
o Identify impacts of development segments that were not modeled previously.
o Inform the capital improvements program and impact of future growth on the
wastewater system.
• Do we need to model the full system to answer our questions?
No, it does not need to be modeled as a full system. The wastewater system is divided
into two basins (also referred to as service areas) and then further sub -basins. The
wastewater system requires individual models for each sub-basin. Our recommendation
is to model the nine sub-basins within the north service area due to the south service area
being largely developed and not having much capacity for growth or expected additional
flow from development.
SCOPE & TIMELINE
The proposed project scope and timeline is attached to this memo, and includes all needed
elements to finalize the master plan. The estimated time to complete the full modeling is an
estimated 6 – 9 months, with an additional three months to finalize master plan recommendations.
FINANCIAL IMPACT
The financial impact of this agreement is estimated at $169,800. Funding for this agreement is
budgeted in the AWIA project of the Capital Improvements Program (CIP).
Attachments: Scope of Work Guide, updated November 2022
CC: Daniel Cortez, Director of Economic Development & Tourism
Dennis Killough, Director of Planning and Development Services
Lauren LaNeave, Deputy Director of Public Works – Administration
Page 1 of 5
City of Southlake
Wastewater Master Plan Update - Scope of Services
November 21, 2022 DRAFT
Project Background: This project is an update to the City’s Wastewater Master Plan in order to proactively
plan for the future of the Denton Creek/Grapevine Lake collection system in the City of Southlake. The
master plan process will update the future flow projections, update the hydraulic wastewater model,
and provide an updated Capital Improvements Plan (CIP) for the Denton Creek/Grapevine Lake service
areas (for the purposes of this report, this will be referred to the North Service Area). As the City
approaches its ultimate buildout conditions, the Master Plan update will focus on developing projects
needed to promote a high level of service for existing and future customers in the North Service Area.
FNI will compare proposed projects to projects in the current Master Plan to determine if they are still
needed or can be removed from the City’s long-term plan. This project scope assumes FNI is updating
the City’s Water Master Plan and will utilize demographic projections from the water project.
BASIC SERVICES
Task A. North Service Area Project Management, Data Collection, and Wastewater Flow Projections
A.1 Administration: Perform general administration duties with the project, including progress
meeting scheduling, general correspondence, office administration, and monthly invoicing.
A.2 Project Kick-off Meeting: FNI will conduct a kick-off meeting with the City to discuss and solicit
input for objectives and goals of the project. The team will also review project scope, schedule,
communication, and present a data request memorandum.
A.3 Document Control: FNI has established Document Control procedures to enable proper
recordkeeping and retrieval. The Document Control procedures use a standardized electronic
index, set up at the outset of the project. Protocols are observed for electronic and paper records,
confidentiality and security, and proper distribution and retention. Documents will be assigned
unique names and the filename and path included in the footer of each document.
A.4 Monthly Progress Reports: A Monthly Status Report will be submitted, summarizing progress
against specific tasks and scheduled tasks to be accomplished in the upcoming month; outlining
upcoming key decisions which will require input from, or discussion with, City staff; and listing any
problems or unresolved issues.
A.5 Data Collection: FNI will compile information from the City including GIS files, as-built, work order
data and preliminary design drawings for projects currently under design in the North Service
Area. FNI will review the data request memorandum with the City to determine what data and
data format is available from the City. FNI will obtain input on historical problem areas in the
collection system.
A.6 Review Historical Wastewater Flows: FNI will review historical wastewater flows and analyze
historical per-capita rates and peaking factors to establish baseline conditions for existing and
future wastewater flows in the North Service Area.
Page 2 of 5
A.7 Develop Wastewater Flow Projections in the North Service Area: FNI will use the land use
assumptions from the Water Master Plan, historical usage data and input from the City’s staff to
develop wastewater flows for existing, 5-year, 10-year, and ultimate buildout conditions for
residential and commercial land uses in the North Service Area. FNI will develop the wastewater
flows utilizing per-capitas, peaking factors values that are specific to the City of Southlake, taking
into account historical characteristics, and in accordance with TCEQ guidelines. FNI will also
compare the historical flow data by land use type and provide recommendations for per-capita
flow ranges within a specific land use type (i.e. commercial, industrial, etc.).
A.8 Meet with the City to Review the Wastewater Flow Projections in the North Service Area: FNI will
prepare for and conduct a meeting with City staff on the updated wastewater flow projections
for the North Service Area.
Task B. North Service Area Historical Flow Monitoring Review and Data Evaluation
B.1 Review of Historical Wastewater System Planning Documents: FNI will review historical planning
documents, including the previous Wastewater Master Plan and Wastewater Collection System
Flow Monitoring Report, plus other relevant documents. Results and recommendations from the
historical studies will be considered when evaluating capacity modeling and development of the
updated CIP for the North Service Area.
B.2 Historical Flow Monitoring Data Evaluation: FNI will review the flow monitoring and rainfall data
from the 2017-2018 temporary flow monitoring assessment and prepare the data to be used in
calibration of the revised model. It should be noted that this data is nearly 5 years old and could
impact the accuracy of the calibrated model with existing system flow conditions.
Task C. North Service Area Wastewater Model Development and Calibration
C.1 Evaluate and Review Wastewater System GIS for Developing All-Pipes Wastewater Model for the
North Service Area: FNI will analyze wastewater system GIS information and historical mapping
data to determine additional pipeline attribute data or connectivity corrections needed for
wastewater model development including recently constructed lines that may not be included in
the GIS. This evaluation will be conducted for the North Service Area.
C.2 Sewer Basin, Sub-Basin, and Subcatchment Generation for the North Service Area: FNI will
review and update sewer basin delineation for the North Service Area using ground contour and
system mapping. FNI will develop sewer sub-basin delineation representing meter areas and
geographical areas within each sewer basin that is more refined than the flow meter basin
delineation. FNI will generate subcatchments for each sewer sub-basin showing which areas
feed into each sewer manhole within their respective flow meter basins. FNI will develop a flow
meter schematic showing which sewer basin and metered sub- basins feed into each sewer
interceptor for model analysis and data output review.
C.3 All-Pipes Hydraulic Wastewater Model Development for the North Service Area: FNI will develop
the wastewater model and utilize GIS data to include all wastewater lines within the North
Service Area in the selected modeling software. FNI will create an electronic shapefile of the
City’s water customers showing location and usage by assigning a spatial location to each meter
through a process called geocoding. This information will be used as part of the model validation
and verification process.
Page 3 of 5
C.4 Dry Weather Calibration for the North Service Area: FNI will select a dry weather calibration
event to isolate projected flows as primarily domestic contributed flows. FNI will perform dry
weather calibration of the selected dry weather flow event using calibrated flow volume by
adjusting antecedent conditions, per capita flows, diurnal curves, and dry weather infiltration in
the North Service Area. FNI shall prepare charts and profiles at selected calibration points
showing metered vs. modeled dry weather calibration for flow, depth, and velocity.
C.5 Wet Weather Calibration for the North Service Area: FNI will review the flow meter data and
select a wet weather calibration storm event. FNI will perform wet weather calibration using the
EPA approved RTK methodology on selected wet weather flow events using calibrated peak I/I.
FNI will adjust model parameters to calibrate flow, velocity and flow depth in the North Service
Area. FNI will prepare charts and profiles at selected calibration points showing metered vs.
modeled wet weather calibration results.
C.6 Design Storm Evaluation: FNI will evaluate design storms and develop recommendations on
design storms using return period and storm intensity for individual sewer basins and
interceptors, based on level of service recommendations using existing available data.
C.7 Meet with City to Review Model Development and Calibration: FNI will meet with the City to
discuss the model development, model calibration, and design storm evaluation.
Task D. North Service Wastewater System Modeling and Performance Analysis
D.1 Design Criteria and Level of Service Evaluation: FNI will evaluate and recommend wastewater
system planning criteria, including design flows, minimum and maximum pipeline velocities, TCEQ
requirements and surcharging guidelines. The criteria will determine the level of service and what
surcharging, if any, is allowed, minimum and maximum velocity constraints, etc. Criteria will be
developed for overall master planning purposes, development reviews, and environmentally
sensitive areas.
D.2 Wastewater System Capacity Evaluation for the North Service Area: FNI will run the calibrated
wastewater model with design storm(s) and identify existing surcharging and overflow locations
and other capacity/restriction issues in the North Service Area. This will provide the baseline
evaluation of where the collection system currently has issues. This task will establish critical
projects that will be included in the short-term recommendations. FNI will perform the capacity
evaluation on the existing and future collection system (5-year, 10-year, and ultimate buildout)
using the flows developed in Task A. FNI will prepare mapping and model results for the North
Service Area showing all surcharging and overflow locations by magnitude and locations. FNI will
categorize manholes by overflow amounts during design storm and sewer line surcharging by
amounts during design event(s).
D.3 Wastewater System Lift Station Assessment for the North Service Area: In parallel with the
gravity main assessment, FNI will evaluate the lift station in the North Service Area for potential
capacity issues, pump cycling and lifespan, and wet-well sizing. FNI will also evaluate the
feasibility of eliminating any existing lift stations with gravity sewer improvements. No on-site
field inspection assessment will take place as part of this task.
Page 4 of 5
D.4 Develop Wastewater System Improvement Alternatives for the North Service Area to Address
Capacity Issues: Using the results of future system modeling, FNI will develop improvements to
eliminate excessive surcharging and overflows in the collection system resulting from increased
wastewater flow from projected future growth, development, and redevelopment in the North
Service Area. FNI will develop improvements alternatives for gravity lines, lift stations, force
mains, and special structures within the North Service Area. Improvements needed to correct
existing deficiencies will also be included. FNI will utilize model results to develop improvements
to serve areas that are currently not developed or served by the City. FNI will prioritize
rehabilitation areas based on flow monitoring results and operational data to help reduce
infiltration/inflow. FNI will develop mapping showing improvements required for the 5- year, 10-
year, and ultimate buildout planning periods as well as improvements needed to correct existing
deficiencies in the North Service Area.
D.5 Meeting to Review System Performance Modeling and Alternatives Analysis: FNI will prepare for
and conduct a meeting with the City to discuss the system modeling and associated evaluations.
Task E. North Service Area Wastewater System CIP and Master Plan Report
E.1 Develop Draft Capital Improvement Plan Costs, Phasing Plan, and Project Drivers for the North
Service Area: FNI will develop costs for each proposed project, draft CIP scheduling of projects
based upon wastewater system modeling requirements, project drivers (such as growth,
regulatory, renewal, etc.) and mapping showing project locations. Costs will be in existing year
dollars and will include engineering and contingencies. Projects will be phased by fiscal year for
the first five year and by planning period for subsequent projects.
E.2 Compare Proposed Improvement Alternatives to 2012 CIP List: FNI will compare the developed
list of projects in this Wastewater Master Plan update to the existing 2012 CIP project list. FNI
will note differences and provide justification for potential changes to CIP projects.
E.3 Meeting to Review Draft Capital Improvements Plan: FNI will prepare for and conduct a workshop
with the City to discuss draft CIP, project phasing and results of prioritization.
E.4 Revise CIP and Prepare Draft Wastewater System Master Plan Update Report for the North
Service Area: FNI will revise the hydraulic modeling and CIP based upon the City’s comments and
feedback and prepare a master plan report discussing field test results, assumptions,
wastewater flow projections and recommended capital improvement plans including phasing
and costs of improvements for the North Service Area. The report will include colored maps
showing proposed system improvements as well as GIS digital copies. FNI will provide the City
with three (3) copies of the draft report for review plus an electronic PDF copy.
E.5 Finalize Wastewater System Master Plan Update Report for the North Service Area: FNI will
conduct a comments review meeting with City staff and will finalize the Master Plan Report
based on feedback received. FNI will provide the City with five (5) copies of the final report, and
electronic PDF copy, and any requested modeling/GIS files.
E.6 Public Involvement and Presentations: FNI will prepare for and attend up to four (4) public
meetings with various stakeholder groups to review and discuss the results and recommendations
of the Wastewater Master Plan Update.
Page 5 of 5
E.7 Coordination Meetings with TRA: FNI will prepare for and attend up to two (2) meetings with City
Staff on the following items, if necessary:
· Outstanding data needs
· Wastewater flow projections
· TRA point-of-entry hydraulics
· Planned CIP projects (TRA and Southlake)
Task Task Name Labor Cost Expense Cost Total Cost
A North Service Area Project Management, Data Collection, and Wastewater Flow Projections $21,698 $1,476 $23,175
B North Service Area Historical Flow Monitoring Review and Data Evaluation $12,699 $719 $13,418
C North Service Area Wastewater Model Development and Calibration $26,463 $1,809 $28,272
D North Service Area Wastewater System Modeling and Performance Analysis $39,394 $2,983 $42,377
E North Service Area Wastewater System CIP and Master Plan Report $57,597 $4,960 $62,556
$157,851 $11,947 $169,800
$157,851 $11,947 $169,800GRAND TOTAL
Basic Services Total
City of Southlake
Wastewater Master Plan Update - North Service Area
UPDATED 4/5/2023
Summary by Task DRAFT
Basic Services
A North Service Area Project Management, Data
Collection, and Wastewater Flow Projections
B North Service Area Historical Flow Monitoring
Review and Data Evaluation
C North Service Area Wastewater Model
Development and Calibration
D North Service Area Wastewater System Modeling
and Performance Analysis
E North Service Area Wastewater System CIP and
Master Plan Report
Southlake Wastewater Master Plan Update
Project Schedule
DEC JAN
2023 2024
Draft Wastewater CIP - October 2023
Draft Wastewater Master Plan Report - December 2023
Final Wastewater Plan Report - January 2024
NOVAUG SEP OCTFEB MAR APR MAY JUN JUL
Project Task
Key Project Milestones (Dates Approximate)