Item 6B - Flood Studya F27-MMMM • FloodStudy HTeaOSouthlake, TX October 28, 2021 Introduction This project is approximately 1.3788-acres located at 190 Davis Blvd in Southlake, Texas, as shown in Appendix A — Figure 1. The Project site is currently undeveloped with a Sonic site to the north, single-family residential properties to the east across Davis Blvd., and undeveloped land to the south. Tributary BB-9 flows from north to south along the western side of the property. Per FIRM 48439C0090L, revised March 21, 2019, there is FEMA floodplain (Zone AE) within the Project site. The Project is planned to be developed as an HTeaO commercial property with the construction plans by Bowman Consulting. The topographic survey was performed by Spooner & Associates and dated July 21, 2021. The purpose of the flood study is to use the topographic survey data provided by Spooner & Associates to determine the corrected effective 100-year floodplain within the limits of the Project site. It is also to determine if the proposed Project will cause any adverse hydrologic impacts to the adjacent properties. It is the intent of the Project for all work to remain outside of the limits of the corrected effective 100-year floodplain of Tributary BB-9. Overall Hydrologic Analysis KCE requested the effective models for Tributary BB-9 from FEMA and received a PDF of the HEC- K output for Tributary BB-9 from lettered cross -sections A-G. In addition, KCE also received the effective models and shapefiles from the upstream LOMR 19-06-1227P by Boyd Hydrology, PLLC which became effective 4/27/2020. Since FEMA did not provide KCE with any effective hydrologic models for the watershed of Tributary BB-9, KCE instead created a HEC-HMS model to determine if the proposed Project would have an adverse hydrologic impact to other properties. KCE used the onsite topographic survey data provided by Spooner & Associates as well as the 2019 USGS lidar contour data to delineate the watershed to the downstream side of the Project site. Based on the delineations by KCE, the watershed to the downstream side of the Project is approximately 808-acres, so KCE selected the SCS Unit Hydrograph method as the most appropriate method to determine the peak discharges at the junctions. Refer to Appendix A — Figure 2 for the drainage area map. The SCS curve number (CN) represents the runoff potential of a given area with the higher the CN, the greater the runoff potential. The curve numbers are determined based on hydrologic soil type and land use. For this project, KCE determined the CN based on the hydrologic soils type from the USDA Web Soil Survey and the existing land use from the NCTCOG land use data, edited to reflect more recent developments. Refer to Appendix A — Figure 2 for the existing land uses, and the soils map is shown in Appendix A — Figure 3. r h Flood Study E HTeaO — Southlake, TX October 28, 2021 The time of concentration is defined as the time required for water to flow from the most hydraulically remote point of the basin to the design point of interest. The path of travel is divided into sheet flow, shallow concentrated flow, and open channel flow (or closed storm system flow). The times of concentration for the subbasins were calculated based on the SCS publication Technical Release 55 (TR-55) standard engineering practices. The flowpaths used are shown in Appendix A — Figure 2. The detailed time of concentration calculations are shown in Appendix C. Based on TR-55, the watershed lag time was calculated at 60% of the total time of concentration for each drainage basin. The watershed lag time is the time from the center of mass of excess rainfall to the peak rate of storm water runoff. Tables 1 and 2 shows the existing and proposed hydrologic parameters, respectively. Table 1— Existing Hydrologic Parameters Existing Sub Basin DA (acres) DA (Sq.Mi.) Lag Time (min) CN A 0.915 0.001430 7.6 68 OS-1 807.073 1.261052 39.9 82 Table 2 — Proposed Hydrologic Parameters Proposed Sub Basin DA (acres) DA (Sq.Mi.) Lag Time (min) CN A 0.915 0.001430 1.8 93 OS-1 807.073 1.261052 39.9 82 KCE used these parameters and the Atlas 14 rainfall data to create a hydrologic model for the Tributary BB-9 watershed to the downstream side of the Project site in the United States Army Corps of Engineers HEC-HMS (version 4.8) program to determine the peak discharges for the 100- and 2-year storm events. Table 3 below shows the results summary. r h Flood Study E HTeaO — Southlake, TX October 28, 2021 Table 3 — Results Summary Hydrologic 100-yr Peak Discharge (cfs) 2-yr Peak Discharge (cfs) Junction Existing Proposed Prop - Exist Existing Proposed Prop - Exist OS-1 2,547 2,547 0 873 873 0 A 5 11 5 1 5 4 Junction-1 2,548 2,548 0 873 1 873 0 Based on the results of the HEC-HMS model, although there is a slight increase in peak runoff for subbasin A due to the proposed development, the net impact at the downstream junction, Junction-1, is no change to the peak discharge for either flow event. Therefore, the proposed Project should be able to develop as planned with no detention. Per the effective FIS data, the effective 100-year peak discharge at the corporate limits of the City of Southlake approximately 3,000-ft downstream of the Project site is 2,650 cfs, so the watershed peak discharge of 2,548 cfs at Junction-1 is reasonable. Overall Hydraulic Analysis KCE requested the effective models for Tributary BB-9 from FEMA and received a PDF of the HEC- K output for Tributary BB-9 from lettered cross -sections A-G. In addition, KCE also received the effective models and shapefiles from the upstream LOMR 19-06-1227P by Boyd Hydrology, PLLC which became effective 4/27/2020. After opening the provided models and shapefiles from FEMA, KCE determined that the current effective FEMA floodplain through the Project site appears to have been moved or shifted from the actual location of the creek. Since the provided models are not in the correct location, KCE created a hydraulic model of Tributary BB-9 through the Project site. KCE used a combination of the onsite topographic survey data provided by Spooner & Associates within the Project boundaries and the USGS 2019 contour data for the offsite portions to create an existing terrain. KCE determined the Manning's n-values based on aerial images of the site and from the effective model. The downstream limits were set as a known water surface elevations from the FIS effective lettered cross-section E. The United States Army Corps of Engineers HEC-RAS (version 6.0) program was used to calculate the WSEL and velocity within the limits of the study. Table 4 below displays the HEC-RAS results from the FIS effective 100-year peak discharges through the Project site. The corrected existing floodplain is shown in Appendix A — Figure 4. Refer to Appendix D for the HEC-RAS profile and cross -sections for the FEMA storm events for Tributary BB-9. r h Flood Study E HTeaO — Southlake, TX October 28, 2021 Table 4 —100-Year HEC-RAS Results Tributary 1313-9 100-yr Results River Station Q Total (cfs) Existing WSEL (ft) Velocity (fps) Valley Storage (acre-ft) 7499 2650 639.91 3.82 16.25 7305 2650 639.24 5.49 12.7 7222 2650 638.94 6.17 11.28 7091 2650 638.28 6.82 9.16 6928 2650 637.53 6.35 6.61 6774 2650 636.78 6.26 4.24 6674 2650 636.35 5.37 2.49 6490 2650 635.75 5.31 0 Once KCE provided Bowman Consulting with the corrected existing 100-year floodplain through the Project site, the proposed site and grading plans were adjusted to remain outside of the 100- year floodplain. The FFE of the building was set at 651.00 which is more than 11-ft above the adjacent 100-year WSEL of 639.24. ��r FloodStudy HTeaOSouthlake, TX October 28, 2021 Conclusions This flood study was performed to determine if the proposed Project can be constructed as planned without causing an adverse hydrologic or hydraulic impact to other properties per the City of Southlake definition. Based on the results of the hydrologic analysis, there are minor increases in the onsite peak discharge as a result of the Project but the net impact to the watershed is no change to the peak discharge of Tributary BB-9 due to the timing of the contributing hydrographs. KCE delineated the corrected effective 100-year floodplain through the Project site using the effective FIS peak discharges. All proposed onsite improvements were designed by Bowman Consulting to remain outside of the corrected existing 100-year floodplain. The proposed FFE of the onsite building is more than 11-ft above the adjacent 100-year WSEL. Therefore, the Project should be able to be constructed as planned with no onsite detention and no floodplain reclamation. If you have any questions or comments, please feel free to call. Sincerely, Dr. Cuneyt Erbatur, PE, CFM, LEED AP Principal KCE Engineering, LLC a Texas limited liability corporation TBPE Reg. No. F-16940 I m Appendices Appendix A,-- Exhibits HTeaO — Southlake, TX October 28, 2021 PREPARED BY: OCE CHECKED BY: am, HTeaO - Southiak DRAINAGE AREA MAP Reg. #: F-16940 !(FM 1938 F M 1 7 0 9 PEARSON JOHNSONFAWKES LNFLORENCE RDS PEYTONVILLE AVE LAKEVIEW BEAM DRMORGAN VISTA TRL HARRELL DR PEYTONVILLE N WATER LILY DRWOO D B R O O K JELLICO CIR JUDGE BLAND RD TOP RAIL LNCIMARRON TRL OVERLAND TRL SPANISH TRLKINGSWOODHILLSIDE CTS PEARSON LN WATERMERE DR SUTTON PL GRAY LNMEADOWVIEW RDGIFFORD CTLOVEGRASS LNVISTA LNBILTMORE DR ROYAL LN BREWER RD BROCK DR WINDSOR FOREST TRL VISTA RDFANNING ST MICHAEL DRREDWING DRE G R E T L N SUMAC DR MARVIN DR VERMILION CT MEADOWL A R K L N LODESTAR DR ELKIN LNRANDOL MILL AVCHESAPEAKE LNEMBER WOODS DRJORDAN DRKATELYN LN TEXAS TRLFOREST LNTRAILHEAD DR INDIAN PAINTBRUSH WAYWILD ROSE WAYM E S Q U I T E R D HOLLAND HILL WOODLAWN CT DONLEY CT TALL WOODS TRLHICKORY CT TRAIL DUST DR BRIDGEWOOD DRWILDWOOD WAYLIMERICK CT WESSEX R D BOB O LINK DR SANDHILL CT WESTMINSTER TRLHIGHLAND CT RIVER OAKS D R VISTA VIEW STGRAPE ARBOR CT WESTWOOD DR WARRINGTON LN HICKORY HOLLOW LNBROWN LN BIG BEND CVDEER HOLLOW BLVD RANCH HOUSE DRTHISTLE CT WILDERNESS CT REDWING CTTEN BAR TRLPLAYERS CIRMEADOW GLENTHORNWOOD DR VERANDA LNKILLDEER CT LUCIAN LNSWALLOW D ROSPREY CT STONEHOLLOW LN KILLDEER TRL BRENDA LNPARK PLSTONEBRIDGE LN PEARSON XINGCAMDEN CIRSTONEBURY DRE L K ' S L N TIMBERLINE L NMESQUITE CTIRONCLAD CTSTANSBURY DR STARLING CT LAKEVIEW DR HONEYSUCKLE HL W STONECASTLE DRWIMPOLE CT WLOS ALTOS TRL PALOS VERDES TRL GREENWOOD DRSPRUCE CTREMUDA CTPORTOFINO PLTWIN CREEK FERNWOOD DRKNIGHT CTBOARDWALK AVESUMMER RIDGE CT CUMBERLAND TRLSURREY CTBRISTOL GLENCARRICK CTCORRAL CTGLEN CVHAY MEADOW CTFM 1709JOHNSONF M 1 7 0 9 Junction-1 BB-9 UVOS-1 UVA Reg. #: F-16940 0 500 1,000250 Feet Path: D:\GIS\Projects\432-190_Davis\Figure 3 - Soils Map.mxd¯HTeaO - SouthlakeSOILS MAP FIGURE PREPARED BY: 10/27/20213 CHECKED BY:KME DATE: OCE PROJECT #:432 Legend !(HMS_Junctions Existing_Drainage_Area Parcels Soil Type A B C D Water Note: Drainage area delineations are based on contours with a vertical datum of NAVD88, obtained from the following source: United States Geological Survey (USGS). Pecos Dallas Lidar, 2019-07-12 PREPARED BY: OCE CI CHECKED BY: KME 061R] =uNA Reg. #: F-16940 I m Appendix B — FIS Data .• — • TX October 28, 2021 TABLE 4 - SUMMARY OF DISCHARGES (continued) PEAK DISCHARGES Lefs 0 0 0 0 FLOODING SOURCE AREA Annual Annual Annual Annual 1 LOCATION Redelineation Detailed Studv Streams TRIBUTARY BB-7 At Eagle Bend TRIBUTARY BB-8 Upstream of confluence with Big Bear Creek Upstream of left bank tributary 500 feet upstream of Continental Boulevard 0.32 ** ** 987 ** 2.25 2,550 3,500 3,950 5,000 1.22 1,450 2,000 2,250 2,900 1 RIBUTARY BB-9 Upstream of confluence with Big Bear 1.97 1,950 2,750 3,100 3,950 Creek At Southlake corporate limits 1.33 1,700 2,350 2,650 3,400 At confluence with Big Bear Creek ** Downstream of confluence of left bank tributary (approximately 1,900 feet ** downstream of the Johnson Road crossing Upstream of confluence of left bank tributary approximately 1,900 feet ** downstream of the Johnson Road crossing TRIBUTARY BB -I I 3,050 4,250 2,500 3,450 4,800 6,100 3,900 4,950 1,450 2,000 2,250 2,850 At confluence with Big Bear Creek 1.18 2,700 3,375 TRIBUTARY BB-1.2 At confluence with Big Bear Creek ** At FM 1709 TRIBUTARY BB-13 Approximately 1,500 feet upstream of 0.45 its confluence with Big Bear Creek UNNAMED TRIBUTARY TO BIG BEAR CREEK Approximately 800 feet upstream of 0.35 Keller -Hicks Road STREAM BFC-1 755 1,105 ** ** At confluence with Big Fossil Creek 2.34 4,070 At North Beach Street 2.26 4,070 At Western Center Boulevard 2.00 3,830 4,302 5,225 3,700 4,600 3,000 3,750 1,276 1,651 521 ** 5,420 6,010 7,320 5,410 6,000 7,310 5,080 5,630 6,860 z t ll t t MR KIM I I 0 1000 2000 3000 4000 5000 6000 7000 STREAM DISTANCE IN FEET ABOVE CONFLUENCE WITH BIG BEAR CREEK LEGEND 0.2% ANNUAL CHANCE FLOOD -- -- 1 % ANNUAL CHANCE FLOOD — — 2% ANNUAL CHANCE FLOOD — — — — — — — — — 10% ANNUAL CHANCE FLOOD STREAM BED CROSS SECTION LOCATION 8000 9000 10000 660 CD >- 650 CD wil U 620 w c� I— cf) LLJ Q 610 = d 0 w c� CD Q w f— Q w w I m Appendix C — Hydrologic Data HTeaO — Southlake, TX October 28, 2021 9/28/21, 3:06 PM Precipitation Frequency Data Server NOAA Atlas 14, Volume 11, Version 2 Location name: Roanoke, Texas, USA* Latitude: 32.95220, Longitude:-97.19650 h% Elevation: 705.85 ft** source: ESRI Maps ** source: USGS §`Ai POINT PRECIPITATION FREQUENCY ESTIMATES Sanja Perica, Sandra Pavlovic, Michael St. Laurent, Carl Trypaluk, Dale Unruh, Orlan Wilhite NOAA, National Weather Service, Silver Spring, Maryland PF tabular PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches)' Average recurrence interval (years) Duration ... ... .... ... 1 2 5 10 25 50 100 200 500 1000 5 7in ^0 409 0.477 0.589 0 681 0 807mm O^902 $g9942 ^ 1 10 W „1 23 1 34 (0.310 0 540) (0 365 0 626) (0 449-0 774), (0 511 0.905) (0 586-1.10) (0 638 1 26) (0. �) (0 739-1 60) (0 802 1.85) (0 847 2 04) 10-min 0 655 0 765 0.944 1.09 1.30 1.45 1 61 1 76 1.96 2 12 (0.496-0.865) (0 m585 1.00) (0 719 1 m24) (0 820-1.45) (0.942 1.77) (1 03-2.02) (1.11-2p29) (1 18 2.56) (1 28-2.94) (1 34-3.23) 0.814 0.950 1.18 1.36 1.61 1.80 1.98 2.17 2.44 2.65 [15-min ^ . (0.616-1 A8) (0.729-1.25) (O.M898-1 55) jl' .02-1.81)m (1.17-2.19) (1.27-2.50) (1.337-2.82) (1.46-3.17) (1.59-3.65) (1.67-4.04) 1.13 1.32 63 1.88 2.22 2.47 2.73 3.00 3.37 3.66 �mi "(12 1.73) 2.14) (1.41-2.50) (1.61-3.01) (1.75-3.43) (1.88-3.88) (2.02-4.36) (2.19-5.05) (2.32-5.60) 1.47 1.72 2.12 2.45 2.90 3.24 3.59 3.97 4.48 4.89 [���]F (1.11-1.94) (1.31-2.25) (1.61-2.78) (1.84-3.26) (2.10-3.94) (2.29-4.51) (2.48-5.11) (2.67-5.77) (2.91-6.71) (3.09-7.47) 1.80 2.12 2 64 3.08 3.69 4.16 4.64 5.17 5 91 6.49 2-hr (1.38-2.35) (1.63-2.74) (2 03„3.43) 11 (2.33-4.05) „m(2.70-4.96) „(2.96-5.72) (3.23-6.53) 11„m(3.50-7.43) (3 86 8 72) 11 (4.14-9.78) 3-hr 1.99 2.37 2.97 I 3.48 4.19 4.75 �� m5.34 5.97 68� 7.58 (1.53-2.59) (1.83-3.04) (2.29-3m83) (2.65-4.54) (3.09-5.60) (3.41-6.49) (3.73-7.45) (406-8.51) (4.51-10.1) (4.85-11.3) [��F-236 2.82 3 56 4 20 5.10 5.81 6 57 7.39 8.54 9.47 (1.83-3.02) (2.20-3.57) (2 78-4 54) (3 22 5 42) (3.79-6.74) (4 20_7 84) (4 62 9,04) (5 rr06-10 4) (5.64-12.3) (6.09-13.9) 12-hr IF 2 77 3.33 4.22 4.98 6.06 6.92 7 82 16.2 11.3 ., (2.17-3 52) (2 62-4.17) (3 LL32-5-33) (3 87-6 37)KK rr(4 55-7.92) (5 04 9.22) (5.54-10.6) [697_171(6.77-14.5) (7 31-16.4) j 24-hr 3.24 3.90 4.93 5.83 7.09 8 09 9714 10 3 11 9 13.2 ( 6.16) mm(4.56-7.36) pp(5.36-9.14) (5m94m10 6) (6 m53 12 3) (7.15-14.1) (7.97 16 7) (8.59 18.8) �_...__h ..5 -. m. j 2-day 3 76 4.50 5.67 6.68 812 9.27 105 11 8 13.7__j 15.2 m. (3 00 4.66) , (3.60-5.50) (4.54-6.99) (5.28-8.34)mm (6 20-10.3) (6.87 12.0) (7.56 13.9) (8 27-15.9) (9.22-18.9) (9.95-21.4) j 3-day ]F 4.09 4.89 6.15 7.25 8.81 10.1 11.4 12.8 14.9 16.5 i.... _m 3.28 5.04) (3.94 5.94) 11 (4.96-7.54) (5.76-8.99) Il (6.76-11.1) (7.50 13.0) (8.24-15.0) (9.02-17.1) 1 (10.1-20.4) (10.9 23.0) 1,7 4-day 4.32 5.18 6.52 7.68 9.34 10.7 12.1 13.6 15.8 17.6 (3.48-5.30) 11 (4.18-6.25) (5.28-7.94) (6.13-9.47) (7.20-11.8) (7.99-13.7) m(8.79-15.8) (9.63-18.1) (10.8-21.6) (11.6-24.4) 7-day 4.80 5.78 7.30 8.62 10.5 12.1 13.7 15.5 18.0 20.0 (3.90-5.84) (4.70-6.90) (5.96-8.81) (6.94-10.5) (8.18-13.1) (9.09-15.3) (10.0-17.7) (11 A-20.3) (12.3-24.2) (13.3-27.4) ��7d7a7yj- 5.23 6.29 7.95 9.40 11.5 13.1 14.9 16.8 19.6 21.8 (4.27-6.31) (5.15-7.48) (6.53-9.55) (7.60-11.4) F .95-14.2) (9.94-16.6) (10.9-19m1) (12.0-22.0) (13.4-26.1) (14.5-29.6) j 20-day 6.75 7.98 9.95 11.6 14.07 F-15.87F 17.8 19--97F 23.07F 25.5 (5.57-805) (6.63-9.42) (8.26-11.8) (9.49-14.0) (11.0-17.1) (12.1-19M6) (13.1-22.5) (14.3-25.6) (15.9-30.3) (17.1-34.1) j 3078 03 9.41 11.6 13 5 16.1 18.1 20.222.5 25 8 28.6 (6 67 9m52)w 2788-11 J- (9.72-13.7) 1 (11 1 16 1) (12 7 19.5) (13 rr8-22.3) (15 0 25 3) (16,3-28.7) (17 9 33.7) (19 2-37.8) 33.8 ay 27.1 30_ M r7. _n �^ 5) (169^26�8) (18 3 30 (8.21 11 6) (9.66 13.4) j 60 day 11.4 13.3 16.4 19.0 22 7 25.5 28.5 31.5 35.6 38 8 (9.58 13.4)pp mm(11m3-15.5) (13 8 19.1) mm(15.8 22.4) (18 1 27p2) (19.8-31.1) _(21 4-35.2) (22.9-39.6)m (24."- .7) (26.3 50 6) Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS). ambers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval. The probability that precipitation frequency ;timates (for a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5%. Estimates at )per bounds are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PIMP values. ease refer to NOAA Atlas 14 document for more information. https://hdsc. nws.noaa.gov/hdsc/pfds/pfds_printpage.htmI?lat=32.9522&Ion=-97.1965&data=depth&units=engIish&series=pds 1 /4 9/28/21, 3:06 PM Precipitation Frequency Data Server PF graphical Average reckirronce int jYE 2 5 10 25 50 100 200 500 1000 Duration — 5--rnin — 2-day — I 0-min — 3-day I "un 4-day 30-niin 7-day 60-inin 1 G-day 24rir 20-day 3-hr. 30-day 6-hr 45-day 12-4ir 6'"ay 24-hr Maps & aerials Small scale terrain Large scale terrain https://hdsc.nws.noaa.gov/hdsc/pfds/pfds printpage.html?lat=32.9522&lon=-97.1965&data=depth&units=english&series=pds 2/4 9/28/21, 3:06 PM Precipitation Frequency Data Server IF�T+1!i��i e • https://hdsc.nws.noaa.gov/hdsc/pfds/pfds_printpage.htmI?Iat=32.9522&Ion=-97.1965&data=depth&units=engIish&series=pds 3/4 9/28/21, 3:06 PM Precipitation Frequency Data Server US Department of Commerce National Oceanic and Atmospheric Administration National Weather Service National Water Center 1325 East West Highway Silver Spring, MID 20910 Questions?: HDSC.Questions,@Doaa..gov Disclaimer https://hdsc.nws.noaa.gov/hdsc/pfds/pfds printpage.html?lat=32.9522&lon=-97.1965&data=depth&units=english&series=pds 4/4 EXISTING TRAVEL TIME CALCULATIONS Basin Data Overland Flow Shallow Concentrated Flow Channel/Street Flow Basin Name a cu ate Longest Flowpath (ft) LengthSlope (ft) (ft/ft) Surface Type Manning's n To (min) LengthSlope (ft) (ft/ft) Surface Type K Ts (min) LengthSlope (ft) (ft/ft) Manning's n Area (ft�) WP (ft) ChannelTime Velocity (Us) To (min) of Cone. Calc. (min) Lag Time (min) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) X-Section Type (15) (16) (17) (19) (20) (21) A 365 100 0.030 Dense —Grass 0.240 11.44 265 0.045 unpaved 16.1 1.29 0 0.050 Channel 3.00 0.00 Total To (min)= 11.44 Total Ts (min)= 1.29 Total To (min)= 0.00 12.73 7.6 OS-1 10819 100 0.020 Dense —Grass 0.240 13.45 320 0.063 unpaved 16.1 1.32 1177 0.050 Channel 3.00 6.54 2156 0.013 Conduit 6.00 5.99 7066 0.050 Channel 3.00 39.26 Total To (min)= 13.45 Total Ts (min)= 1.32 Total To (min)= 51.78 66.56 39.9 Lag —Time —Calculations Existing CN Calculations 309 A 0.320519 Open Space B 61 19.55166 306 A 0.130686 Open Space C 74 9.670764 308 A 0.366179 Open Space D 80 29.29432 193 OS-1 0.0150403 Commercial A 89 1.338587 195 OS-1 0.117734 Commercial A 89 10.47833 200 OS-1 0.131635 Commercial A 89 11.71552 205 OS-1 0.485397 Commercial B 92 44.65652 213 OS-1 0.484185 Commercial B 92 44.54502 214 OS-1 0.395292 Commercial B 92 36.36686 219 OS-1 0.0025773 Commercial B 92 0.237112 220 OS-1 0.118572 Commercial B 92 10.90862 300 OS-1 0.0609226 Commercial B 92 5.604879 190 OS-1 0.890755 Commercial C 94 83.73097 192 OS-1 2.42296 Commercial C 94 227.7582 194 OS-1 2.885 Commercial C 94 271.19 196 OS-1 _ 0.000721 Commercial C 94 0.067774 197OS-1 2.14727 Commercial C 94 201.8434 199 OS-1 2.56355 Commercial C 94 240.9737 201 OS-1 1.19188 Commercial C 94 1120367 202 OS-1 2.12288 Commercial C 94 199.5507 203' OS-1 0.466663 Commercial C 94 43.86632 207 OS-1 0.760636 Commercial C 94 71.49978 208 OS-1 + 2.0053999 Commercial C 94 188.5076 210 OS-1 0.248666 Commercial C 94 23.3746 215 OS-1 1.4568599 Commercial C 94 136.9448 217 OS-1 0.214247 Commercial C 94 20.13922 222i OS-1 3.4768801 Commercial C 94 326.8267 225 OS-1 0.128841 Commercial C 94 12.11105 226 OS-1 3.6589401 Commercial C 94 343..9404 253 OS-1 4.13831 Commercial C 94 389.0011 298' OS-1 0.412731 Commercial C 94 38.79671 305 OS-1 0.551678 Commercial C 94 51.85773 189 OS-1 2.9697399 Commercial D 95 2821253 198 OS-1 2.17398 Commercial D 95 206.5281 204 OS-1 0.527528 Commercial D 95 50.11516 206 OS-1 9.4230804 Commercial D 95 895.1926 209 OS-1 10.4863005 Commercial D 95 996.1985 211 OS-1 0.703521 Commercial D 95 66.8345 212'' OS-1 1.27714 Commercial D 95 1213283 216 OS-1 0.93374 Commercial D 95 88.7053 Existing CN Calculations 221OS-1 0.504011Cnnnmercia| D 95 47.88105 2240S-1 0.690119 Commercial D 95 65.56131 252US'1 1.37475Connmerda| D 95 130.6013 29905-1 0.559841[onnmercia| D 95 53.1849 188OS'1 8.0878801 Mobile home 8 85 687.4698 185OS-1 1.32226 Mobile home C 90 119.0034 179US'1 0.U2477S4 Mobile home D 92 2.279337 35 0S1 0945823 Open Space A 39 368871 246 OS-1 20357101 Open Space A 39 7939269 258 OS-1 08962874 Open Space 8 61 5.873531 260 OS-1 0.149101 Open Space B 61 9095161 273 OS-1 0306096 Open Space B 61 1867186 287 OS-1 0133697 Open Space B 61 8155517 241 OS-1 113085 Open Space C 74 836829 264 OS-1 97018404 Open Space C 74 7179362 269 OS-1 0611525 Open Space C 74 4525285 274 OS-1 108527 Open Space C 74 8030998 243 OS-1 O023724 Open S D OU 189792 262 OS-1 0638384O Space D 80 5107072 265 OS-1 0'.200344 Open Space 80 16.02752 266 OS-1 178627 Open Space D 80 1439016 272 OS-1 0407678 Open Space D 80 32.61424 28U OS- l 0557376O Space D 80 4459008 286OS'1 U.54S814 Open Space D 80 43.66512 Existing CN Calculations 302 OS-1 0.750463 Open Space D 80 60.03704 303 OS-1 0.849996 Open Space D 80 67.99968 263 OS-1 0.873542 Open Space Water 98 85.60712 232 OS-1 0.673722 Parks/recreation A 39 26.27516 231 OS-1 0.64981 Parks/recreation C 74 48.08594 16' OS-1 1.07525 ROW A 83 89.24575 1 OS-1 1.54544 ROW B 89 137.5442 2 OS-1 24.9106007 ROW B 89 2217.043 11 OS-1 0.2716 ROW B 89 24.1724 17' OS-1 2.62356 ROW B 89 2334968 20 OS-1 7.1996999 ROW B 89 640.7733 21' OS-1 1.2079099 ROW B 89 107.504 29 OS-1 0.0065058 ROW B 89 0.579016 30 OS-1 11.5105 ROW B 89 1024.435 3 OS-1 0.658251 ROW C 92 60.55909 5 OS-1 0.0907257 ROW C 92 8.346764 6 OS-1 4.4772902 ROW C 92 411.9107 8 OS-1 2.5950501 ROW C 92 2387446 10 OS-1 26.5035992 ROW C 92 2438.331 304 OS-1 0.528579 ROW C 92 48.62927 0 OS-1 0.490802 ROW D 93 45.64459 4' OS-1 1.26943 ROW D 93 118.057 7 OS-1 . 1.97677 ROW D 93 183.8396 9 OS-1 0.94677 ROW D 93 88.04961 12 OS-1 0.576872 ROW D 93 53.6491 13 OS-1 1.20357 ROW D 93 111.932 14 OS-1 0.0162683 ROW D 93 1.512952 15 OS-1 1.3886 ROW D 93 1291398 18 OS-1 0.900888 ROW D 93 83.78258 19 OS-1 0.720986 ROW D 93 67.0517 22 OS-1 1.9164701 ROW D 93 178.2317 23' OS-1 3.0310199 ROW D 93 281.8849 24 OS-1 0.771433 ROW D 93 71.74327 25 OS-1 1.32793 ROW D 93 1234975 26 OS-1 0.976538 ROW D 93 90.81803 27i OS-1 1.53385 ROW D 93 1426481 28 OS-1 2.23507 ROW D 93 207.8615 31 OS-1 2.4072299 ROW D 93 2238724 49 OS-1 0.17002 Single family A 61 10.37122 54 OS-1 2.4640801 Single family A 61 1503089 250 OS-1 5.7163301 Single family A 61 348.6961 38' OS-1 0.925961 Single family B 75 69.44708 39 OS-1 0.0003308 Single familv B 75 0.02481 Existing CN Calculations 56 OS-1 83401003 Single family 8 75 6255075 68 OS-1 61704303 Single family B 75 4627823 73 OS-1 696907 Single family 8 75 5226803 78 OS-1 0369321 Single family 8 75 3769908 82 OS-1 0094499Single family B 75 7087425 85 OS-1 Z91O4599Single funni| B 75 2188845 92 OS-1 2.1430099 Single family 8 75 1607257 96 OS-1 710992 Single family B 75 533244 106 OS-1 00760451 Single family 8 75 5.703383 110 OS-1 22469299 Single family B 75 1685197 116 OS-1 0.157509 Single family 8 75 1181318 120 OS-1 121556 Single family B 75 91167 127 OS-1 156513004 Single family B 75 1173848 1300S1 O599598Single family B 75 4496985 135 OS-1 30098 Single family 8 75 225735 139 OS-1 42119398 Single family B 75 3158955 141 OS-1 2.5064499 Single family B 75 1879837 146 OS-1 74602499 Single family B 75 5595187 151 OS-1 35511899 Single family 8 75 2663392 155 OS-1 22399299 Single family B 75 1672447 158 OS-1 25.5475006 Single family 8 75 1916063 162 OS-1 306867 Single family B 75 2301503 166OS'1 1.1S777Single fanoi|v B 75 86.82275 Existing CN Calculations 168 OS-1 45.0410004 Single family B 75 3378.075 172 OS-1 1.20728 Single family B 75 90.546 173 OS-1 8.9081898 Single family B 75 668.1142 176i OS-1 1.04401 Single family B 75 78.30075 181 OS-1 3.1614399 Single family B 75 237.108 183I OS-1 0.0532236 Single family B 75 3.99177 233 OS-1 1.5909899 Single family B 75 119.3242 236'- OS-1 1.22426 Single family B 75 918195 239 OS-1 0.659347 Single family B 75 49.45103 251OS-1 2.1974599 Single family B 75 164.8095 277 OS-1 1.15992 Single family B 75 86.994 279 OS-1 0.731411 Single family B 75 54.85583 285 OS-1 0.072134 Single family B 75 5.41005 289 OS-1 0.269797 Single family B 75 20.23478 37 OS-1 4.2251401 Single family C 83 350.6866 40 OS-1 0.850309 Single family C 83 70.57565 47 OS-1 1.51414 Single family C 83 125.6736 53 OS-1 6.0002298 Single family C 83 4980191 58 OS-1 0.329147 Single family C 83 27.3192 61' OS-1 0.0037724 Single family C 83 0.313109 64 OS-1 1.32408 Single family C 83 109.8986 70 OS-1 1.40039 Single family C 83 1162324 74 OS-1 0.766809 Single family C 83 63.64515 76' OS-1 7.4305401 Single family C 83 616.7348 80 OS-1 0.329656 Single family C 83 27.36145 86' OS-1 5.8403602 Single family C 83 4847499 89 OS-1 9.0230799 Single family C 83 748.9156 91 OS-1 0.42382 Single family C 83 35.17706 94 OS-1 0.017149 Single family C 83 1.423367 99' OS-1 3.35377 Single family C 83 278.3629 102 OS-1 1.15479 Single family C 83 95.84757 103' OS-1 2.2816899 Single family C 83 189.3803 105 OS-1 0.155415 Single family C 83 12.89945 107' OS-1 1.98798 Single family C 83 1650023 111 OS-1 5.9538002 Single family C 83 494.1654 115 OS-1 0.0294119 Single family C 83 2.441188 117 OS-1 0.705256 Single family C 83 58.53625 122 OS-1 3.9525399 Single family C 83 328.0608 123 OS-1 14.1892004 Single family C 83 1177.704 131 OS-1 7.7927899 Single family C 83 6468016 132 OS-1 6.4439101 Single family C 83 534.8445 136 OS-1 0.93854 Single family C 83 77.89882 142 OS-1 0.283777 Single family C 83 23.55349 Existing CN Calculations 148 OS-1 0375396 Single family [ 83 31.15787 153 OS-1 190396 Single family C 83 1580287 161OS-1 6438729OSingle family C 83 5344146 164OS1 19U27OO1Single family [ 83 1579307 170 OS-1 1.22877 Single family [ 83 1019879 175 OS-1 2.6995599 Single family C 83 2240635 178OS1 O01O452Single family [ 83 0867516 240 OS-1 0401068 Single family [ 83 33.28864 255 OS-1 U6D7U24Single family C 83 5702299 278 OS-1 0838162 Single family [ 83 6956745 32 OS-1 00015609 Single family D 87 0.135798 36 OS-1 077603 Single family D 87 67.51461 42 OS-1 22734399 Single family D 87 1977893 44 OS-1 33283 Single family D 87 2895621 48 US1 25315199 Single family D 87 2202422 51 OS-1 52151399 Single family D 87 4537172 55 OS-1 00145538 Single family D 87 1.266181 59 OS-1 0.10277 Single family D 87 894099 62 OS-1 0640069 Single family D 87 55686 65 OS-1 036664 Single family D 87 3189768 69 OS-1 084539 Single family D 87 73.54893 77DS1 O643915Single family D 87 5602861 83OS'l U.97]3S9Single fanni|v D 87 84.68223 PROPOSED TRAVEL TIME CALCULATIONS Basin Data Overland Flow Shallow Concentrated Flow Channel/Street Flow Basin Name a cu ate Longest Flowpath (ft) (1) LengthSlope (ft) (2) (ft/ft) (3) Surface Type (4) Manning's n (5) To (min) (6) LengthSlope (ft) (7) (ft/ft) (8) Surface Type (9) K (10) Ts (min) (11) LengthSlope (ft) (12) (ft/ft) (13) Manning's n (14) X-Section Type Area (ft�) (15) WP (ft) (16) ChannelTime Velocity (Us) (17) To (min) (19) of Cone. Calc. (min) (20) Lag Time (min) (21) A 365 50 0.010 Concrete 0.015 1.11 Total To (min)= 1.11 315 0.020 paved 20.3 Total Ts (min)= 1.83 1.83 0 0.050 Channel 3.00 Total To (min)= 0.00 0.00 2.94 1.8 Lag —Time —Calculations CN Calculations 309 A 0.320519 Commercial B 92 29.48775 308 A 0.366179 Commercial D 95 34.78701 I m Appendix D — Hydraulic Data .• — • TX October 28, 2021 190—Davis—Blvd Plan: Corrected —Existing 9/29/2021 BB-9 BB-9 642- Legend - WS 500-Year ws 160-Year 640- WS 50-Year WS 1 O-Year Ground 638 636 0 634- CU LU 632- 630- 628 626 0 200 400 600 800 1000 1200 Main Channel Distance (fit) c 0 0 w c 0 0 w 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 IRS = 7499 Equivalent to Effective XS 7412 07 J4 .06 1- .07 0 200 400 600 800 1000 1200 0 07 Station (fit) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 IRS = 7305 .06 JL .07 200 300 400 Station (ft) 610101 Legend WS 500-Year WS 100-Year WS 50-Year WS 10-Year ■ Ground Bank Sta 1400 ;:III17 Legend WS 500-Year WS 100-Year WS 50-Year WS 10-Year ■ Ground Bank Sta 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 7222 .07 JL .06I .07 650 Legend WS 500-Year 645 WS 100-Year WS 50-Year 640 WS 10-Year 0 > Ground w 635 Bank Sta 630 L 625 ---- 0 100 200 300 400 500 600 Station (ft) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 7091 .07 "�' .06 .07 646 Legend 644 WS 500-Year 642 ~ WS 100-Year 640 WS 50-Year 638 WS 10-Year 0 — 636 ■ Ground w 634 Bank Sta 632 630 628 r� 0 100 200 300 400 500 600 Station (ft) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 6928 .07 .06 .07 646 Legend 644 WS 500-Year 642 I MIAMI ~ WS 100-Year 640 WS 50-Year 638 WS 10-Year 0 — 636 ■ Ground w 634 Bank Sta 632 630 628 ,-- r� 0 100 200 300 400 500 600 Station (ft) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 6774 .07 J' .06 J14 ,07 "� 646 Legend 644 WS 500-Year 642 �r--'� WS 100- earY 640 WS 50-Year 638 WS 10-Year 0 — 636 ■ Ground w 634 Bank Sta 632 630 628 r� 0 100 200 300 400 500 600 Station (ft) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 6674 07 "�' .06.07 646 Legend 644- WS 500-Year 642 ~ WS 100-Year 640 WS 50-Year 638 WS 10-Year 0 _ 636 ■ Ground w 634 Bank Sta 632 630 628 0 100 200 300 400 500 600 Station (ft) 190_Davis_Blvd Plan: Corrected —Existing 9/29/2021 RS = 6490 Effective XS E .07 — >�<06�Q .07 680 Legend Is 670 WS 500-Year WS 100-Year 660 WS 50-Year WS 10-Year ° 650 ■ > Ground u w 640 MEN 11 Bank Sta 630 620 r r 0 200 400 600 800 1000 1200 Station (ft) I m Appendix E — Construction Plans .• — • TX October 28, 2021 LOT 5R2-R1 PARKER'PARKER'S CORNER INS NO. / C '01074.-SFr I P R, D,("" `'* STA i C OF Tl X L'"�s [)RAiNAG,E p(L'. EASEMENT N OWNER ��p���t} IN Eels'": ASSOCIATES REALTY L 0, P I l C 1. l I EX. STAI'E OF FEXAS � DRAINAGE 1 I LvIEE3.. L...U.D -- WXED USE / °4 518" CIRF BURY PARTNERS RED I1 / I I"� 1 I I `, A L ,U A c' �. ' 324 1.. } <i 14 / I C-) / Lu, b / < TM 0 I rY 0 3 00 pP po-' ER 9 334 KARTHIK DUMPSTER E REALTY LLC A Cl>r ` IN& AFC D2 ' E' ,F4257APPROX, LOCA7 ION OF �s TSt 0,P .I , ,C e IkL_€.,1 " tE tt r "RETAiN1NK,,, Ai, G OWNER s,. x,/\,ALL 'ell X ENCORE RETAIL err rV s . �. qb 15' BUILDING_ SETBACK- , � .�'� ;�''�� ASSOCIATES c I 10' BUILDING SETBACK 3.8, x IL I nHH1 a \ All '` "AND LANDSCAPE BUFFER , f 30 r 100 YR. FLOOD PLAIN 341 "/ � ` 24.00' 12' m d� I , rFF / �/ =v� � � "dam �� 320 A` k - - 06 L A, � /, �?.aL� ZONE "AE € �a�a,,R ZONE ..X.. , T I I PARKING STRIPE 341 PARKERx — a S CORNER 7.15'iJ"TILITY VOL. 88 1 0 PG, 497 w--- d P,R I 1 L. ;" 7 l I L Y �r E W , v e �s � 328 ., .3 F.') VOL.0 E. 50, t"' a.�". ^� N89%25 s 447wI"" I SITE DATA TABLE EXISTING ZONING SP-2 - GENERALIZED SITE PLAN DISTRICT PROPOSED ZONING SP-2 - GENERALIZED SITE PLAN DISTRICT LAND USE DESIGNATION MIXED USE NUMBER OF PROPOSED LOTS 1 ASSESSOR PARCEL NUMBER 07887620 GROSS LOT AREA 60,061 SF (1.379 AC) AREA OF OPEN SPACE 31,907 SF (0.730 AC) PERCENTAGE OF OPEN SPACE 53.12% AREA OF IMPERVIOUS COVER 28,154 SF (0.649 AC) PERCENTAGE OF IMPERVIOUS COVER 46.88% BUILDING AREA 2,250 SF NUMBER OF STORIES 1 BUILDING HEIGHT 15' PROPOSED FLOOR AREA 2,250 SF REQUIRED PARKING (1 PER 100SF) 23 PROPOSED PARKING STANDARD 31 HANDICAP 2 TOTAL 33 REQUIRED LOADING SPACE 0 PROVIDED LOADING SPACE 0 AREA OUTSIDE STORAGE N/A PRCENTAGE OF OUTSIDE STORAGE N/A FLOOD ZONE CLASSIFICATION ZONE 'X' & ZONE 'AE' FLOOD ZONE MAP 48439CO090L & 48439CO095K ANTICIPATED SCHEDULE OF DEVELOPMENT CONSTRUCTION START: CONSTRUCTION END: MARCH 2O22 NOVEMBER 2022 ENGINEER BOWMAN CONSULTING GROUP, LTD 1120 S. Capital of Texas Hwy Building #3, Austin, Texas 78746 [Phone] 972.497.2990 Contact: Ryan Safford, P.E. DEVELOPER GKP INVESTMENTS, LLC 1685 Carlyle Ct., Westlake, TX 76262 [Phone] 817.789.9091 Contact: Todd Bockenfeld LOT 5T 4 PARKER'S CORNER >;p,eS x 8 ad r Lt 49 P, E .C,T . 72+22 BUILDING SETBACK FRONT (DAVIS BLVD.) 50' REAR 10, SIDE 15' LANDSCAPE BUFFER FRONT (DAVIS BLVD.) 10, REAR 10, SIDE 10' (S) / 5' (N) SITE NOTES " m DUMPSTERr� 63 /FV 0vILv11 -4v vL_ I vw�. I::IO(N E R LYNBA HOLDINGS, LLC 0,P,. F, T ,I .-F. L._,i` D,=MIXED USE PROPOSED LEGEND •••'• C CONCRETE SIDEWALK PROPERTY LINE STD. 6" CONCRETE CURB PARKING SPACE COUNT STD. DUTY CONCRETE HEAVY DUTY CONCETE 1. ALL DIMENSIONS SHOWN ARE TO THE FACE OF CURB, PROPERTY LINE OR CENTERLINE OF STRIPING UNLESS OTHERWISE NOTED. 2. A PRE -CONSTRUCTION MEETING WITH CITY ENGINEER SHALL BE HELD PRIOR TO CONSTRUCTION COMMENCEMENT. 3. THE CITY OF SOUTHLAKE SHALL BE GIVEN AT LEAST 48 HOURS NOTICE PRIOR TO PERFORMING ANY INSPECTIONS. 4. TRAFFIC CONTROL SHALL BE IN ACCORDANCE WITH THE PROJECT PLANS, THE CURRENT EDITION OF THE TxDOT DESIGN STANDARDS AND THE LATEST MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD). 5. ALL MECHANICAL EQUIPMENT TO BE ROOF MOUNTED AND SCREENED FROM HE STREET. 6. CONTRACTOR TO PROVIDE AS-BUILTS OF ALL IMPROVEMENTS TO THE SITE. AS-BUILTS TO INCLUDE HORIZONTAL AND VERTICAL LOCATIONS OF ALL UNDERGROUND UTILITIES INCLUDING, BUT NOT LIMITED TO, PIPES, FITTINGS, STRUCTURES, AND OTHER APPURTENANCES. ELEVATIONS OF PIPES AT CROSSING POINTS MUST BE SUFFICIENT TO IDENTIFY MINIMUM SEPARATION OF UTILITIES. IN ADDITION TO THE AFOREMENTIONED CRITERIA AS-BUILTS MUST MEET ALL LOCAL AND JURISDICTIONAL REQUIREMENTS FOR CERTIFICATION OF CONSTRUCTION. 7. ALL AFFECTED SIDEWALKS, RAMPS AND CROSSWALKS, WILL BE BUILT AND INSPECTED TO MEET CURRENT ADA REQUIREMENTS. 8. BUILDING SETBACK DIMENSIONS MEASURED TO OUTERMOST ARCHITECTURAL FEATURE. CONTRACTOR TO REFER TO ARCHITECTURAL PLANS FOR BUILDING DIMENSIONS. 9. ALL CURB RADII ARE 3' UNLESS SHOWN OTHERWISE. 10. PRIOR TO INSTALLATION, CONTRACTOR MUST VERIFY LOCATIONS OF LIGHT POLES, LANDSCAPING AND UTILITIES. 11. CONTRACTOR TO REFER TO ARCHITECTURAL PLANS FOR BUILDING FOOTPRINT. 12. CONTRACTOR TO REFER TO PHOTOMETRIC PLAN FOR LIGHT POLE DETAILS. LANDSCAPE ARCHITECT OWNER EVERGREEN DESIGN GROUP, INC 15455 Dallas Pkwy, Suite 600 Addison, Texas 75001 [Phone] 800.680.6630 Contact: Rodney McNabb KARTHINK & ASSOCIATES REALTY LLC, LP 190 DAVIS BLVD. SOUTHLAKE, TX 76092 DEVELOPMENT COMPANY, T.,F. INS, NO, D201078783, p 0,P, T L L_.I I.L . MVX,_..,,..` U E 5/8"IRF--I� 1 EXISTING LEGEND IRON ROD WITH CAP FOUND 5/8 INCH IRON ROD WITH CAP STAMPED "SPOONER 5922" SET IRON ROD FOUND "X" CUT FOUND OFFICIAL PUBLIC RECORDS TARRANT COUNTY, TEXAS DEED RECORDS TARRANT COUNTY, TEXAS PLAT RECORDS TARRANT COUNTY, TEXAS CONTROL POINT PROPERTY CORNER MARKER FOUND - AS NOTED POWER POLE GUY WIRE LIGHT POLE TELEPHONE RISER GAS MARKER TREE (AS DESCRIBED) WATER METER WATER VALVE FIRE HYDRANT IRRIGATION CONTROL VALVE SIGN UTILITY PULL BOX OVERHEAD ELEC. - U.G. GAS U.G. WATER CONCRETE AREA C; L.z5c-} SPOT ELEVATION Er EDGE OF CONCRETE ELEVATION s"' GUTTER ELEVATION TOP OF CURB ELEVATION l w, - TOP OF BANK ELEVATION :>:C TOE OF BANK ELEVATION SUBJECT PROPERTY LINE EXISTING EASEMENT LINE - BUILDING SETBACK LINE TOP OF BANK TOE OF BANK CENTER OF CREEK CANOPY - COVERED AREA ELEVATIONS SHOWN HEREON ARE REFERENCED TO THE NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD88) AND WERE CALCULATED BY APPLYING VERTICAL SHIFTS DERIVED FROM GEOLID MODEL 2012A TO ELLIPSOID HEIGHTS CALCULATED FROM GPS/GLASS OBSERVATIONS REFERENCED TO THE NORTH AMERICAN DATUM OF 1983, 2011 ADJUSTMENT. CITY CASE NUMBER: ZA21-0049 �J WV RIM EL=654.04' TN EL=649.57' WV RIM EL=654.13' TN EL=649.37' ?' STRIPED - MEDIAN APHAKE-Jll uj 10' LANDSCAPE BUFFER WV RIM EL=656.34' TN EL=653.82' WV RIM EL=656.41' TN EL=653.29' O m O Z) Z .m, ADOPTA HIGHWAY SIGN 4L0VEGRASSLN_) �o J� 0 0 SITEW W _ SOU'iHIAKE BLVD. D N m N 0 o < 011 m O D m m MICHAEL DR. VICINITY MAP SCALE: NTS /THE LOCATION OF EXISTING UNDERGROUND UTILITIES ARE SHOWN IN AN APPROXIMATE WAY ONLY, THE CONTRACTOR SHALL DETERMINE THE EXACT LOCATION OF ALL EXISTING UTILITIES BEFORE COMMENCING WORK. CONTRACTOR AGREES TO BE FULLY RESPONSIBLE FOR ANY AND ALL DAMAGES WHICH MIGHT BE OCCASIONED BY THE CONTRACTORS FAILURE TO EXACTLY LOCATE AND PRESERVE ANY AND ALL UNDERGROUND UTILITIES. T rn (0 E o w N � V 10 1161 1 .� It o) 75 N N � r o rn lfi 3 X Cz O L.L E J O O CL o- Z -0 j o= 3: i) d � 7 mam) 0 3 _ Cz E cc "� 3 E X o oLL LU O O z 0- In ro N U) raMX C� 40k N F U) C c k11-1 _m< �1 Z o U W w o N C) /^\ F IIr X W Z rr w p V (J J U) Er O=w CZ 11) 0 Z o- > T _j W IIr U) > ap 0 _J O 0) Ir— DESIGN DRAWN CHKD PK PK RS JOB No. 070443-01-001 SHEET C1.0 I m Appendix F — Electronic Data .• — • TX October 28, 2021