Item 4H MemoCITY OF SOUTHLAKE Item 4H MEMORANDUM (June 15, 2021) To: Shana Yelverton, City Manager From: Rob Cohen, Director of Public Works Subject: Approve Supplement Agreement No. 1 with Freeman-Millican, Inc. (FMI) to provide engineering design services to construct utility and paving improvements along Shady Oaks Drive between Fox Glen and Durham Elementary School in an amount not to exceed $29,000. Action Requested: Approve Supplement Agreement No. 1 with Freeman-Millican, Inc. (FMI) to provide engineering design services to construct utility and paving improvements along Shady Oaks Drive between Fox Glen and Durham Elementary School in an amount not to exceed $29,000. Background Information: The purpose of this project is to upgrade the existing 6" diameter water line to a 12" diameter water line to improve system flow and water supply enhancement. There is also the installation of an 8" sewer line to provide sewer service via gravity flow and eliminate the need for lift stations and energy costs for pumping. In addition, new pavement overlay will replace the existing pavement within the project limits. The project limits are Shady Oaks Drive between Fox Glen and Durham Elementary School. Delays were attributed to roadway construction on North White Chapel Boulevard and waiting until construction was complete there. This was done to avoid having two north -south thoroughfares in proximity under construction simultaneously. In FY 2020, FMI was assigned to complete the project in the amount of $42,500. However, discrepancies were noted regarding the location of right-of-way boundaries. This information needs to be confirmed for right-of-way or easement acquisition. Plans are 95% complete and once the property boundaries are verified, the need for easement acquisition will be confirmed and the project will be finalized and prepared for bidding and construction. Under Supplement Agreement No. 1 with FMI, the scope of services include providing survey services for data collection and property research and subsurface utility investigations in an amount not to exceed $29,000. The additional scope will allow the project to evaluate the need for easement acquisition and complete the final Page 1 of 2 Item 4H design phase. Improvements to Shady Oaks Drive were identified as part of the City's Water System Master Plan and Waste Water System Master Plan. Financial Considerations: Funding for this agreement is budgeted as part of the approved Capital Improvement Program. This agreement is within the project budget. Strategic Link: This item links to the City's Strategy Map strategic focus areas of Safety & Security, Infrastructure, and Performance Management & Service Delivery. It specifically relates to the City's Corporate Objectives, Cl- Achieve The Highest Standards Of Safety & Security, B6: Optimize Use Of Technology, and F2: Invest To Provide & Maintain High Quality Public Assets. The Critical Business Outcomes is, CBO5: Improve Quality Of Life Through Progressive Implementation Of Southlake's Comprehensive Plan Recommendations. Citizen Input/ Board Review: None. Legal Review: The proposed agreement is a standard agreement that the City Attorney has reviewed and approved. Alternatives: The City Council may approve or deny the agreement. Staff Recommendation: Approve Supplement Agreement No. 1 with Freeman-Millican, Inc. (FMI) to provide engineering design services to construct utility and paving improvements along Shady Oaks Drive between Fox Glen and Durham Elementary School in an amount not to exceed $29,000. Supporting Documents: Attachment A: Supplement Agreement No. 1 Attachment B: FY 2020 Engineering Services Agreement Staff Contact: Rob Cohen, Director of Public Works Kevin Ferrer, P.E., Deputy City Engineer Kevin Taylor, P.E., Civil Engineer Page 2 of 2