Item 9 and 10 - TIA
Page 2 of 19
that for the multifamily land use considered, 15% of the daily traffic occurs in the morning (7am ‐ 8am) and
9% occurs just before noon (11am – 12pm). Therefore, the morning peak hour was used for analysis. The
peak just before noon was not used.
Based on the 2018 City of Southlake Traffic Count Report, existing turning movement volumes were grown
by 10% annually to estimate the background volumes for the buildout year (2021). These buildout
background volumes are shown in Figure 5.
Figure 1: Vicinity Map for Proposed Development
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234
Proposed Lane Configuration
Existing Lane Configuration
Legend
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
Figure 3Existing and Proposed Lane Configurations
N
NOT TO SCALE
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234
S
t
a
t
e
S
t
Division St
Federal Way
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
Figure 4Peak Hour Traffic Volumes
Existing (2019)
10 (23)
14 (39)
6 (18)
1
(
1
5
)
7
1
(
8
4
)
1
(
7
)
13 (18)
8 ( 9)
7 ( 7)
2
(
7
)
2
9
(
1
1
0
)
1
(
2
)
17 ( 77)
1 ( 1)
16 (138)
6
(
1
1
)
6
5
4
(
7
7
1
)
2
8
(
6
0
)
6
(
1
9
)
1 (18)
0 ( 1)
1 (20)
3
(
1
)
7
1
2
(
8
6
0
)
4
3
(
6
8
)
0
(
7
)
2
(
4
)
6
8
3
(
9
1
4
)
6
(
2
)
3 (9)
0 (1)
8 (4)
9
(
4
)
7
8
4
(
9
4
8
)
1
0
(
4
)
1 ( 8)
2 (10)
7 (19)
12 (56)
1 ( 7)
9
(
5
9
)
6
7
(
4
1
)
8
(
9
)
7 (21)
15 (53)
32 (38)
8
(
9
2
)
1
9
(
7
7
)
4
(
1
2
)
N
NOT TO SCALE
Study Intersection
Legend
AM (PM) Peak Hour Volume
1
1
,
4
5
8
1
1
,
7
4
6
(Ref # 65N & 65S)
Carroll from FM 1709 to SH 114
Daily Counts from 2017 Southlake Year B
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234 Figure 5Peak Hour Traffic Volumes
Buildout Background (2021)
S
t
a
t
e
S
t
Division St
Federal Way
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
12 (27)
16 (47)
7 (21)
1
(
1
8
)
8
5
(
1
0
1
)
1
(
8
)
15 (21)
9 (10)
8 ( 8)
2
(
8
)
3
5
(
1
3
3
)
1
(
2
)
8 (22)
14 (67)
1 ( 8)
1
0
(
7
1
)
8
1
(
4
9
)
9
(
1
0
)
8 (25)
18 (64)
38 (45)
9
(
1
1
1
)
2
2
(
9
3
)
4
(
1
4
)
2
(
4
)
8
2
6
(
1
,
1
0
5
)
7
(
2
)
3 (10)
0 ( 1)
9 ( 4)
1
0
(
4
)
9
4
8
(
1
,
1
4
7
)
1
2
(
4
)
1 ( 9)
2 (12)
20 ( 93)
1 ( 1)
19 (166)
7
(
1
3
)
7
9
1
(
9
3
2
)
3
3
(
7
2
)
7
(
2
2
)
1 (21)
0 ( 1)
1 (24)
3
(
1
)
8
6
1
(
1
,
0
4
0
)
5
2
(
8
2
)
0
(
8
)
N
NOT TO SCALE
Study Intersection
Legend
AM (PM) Peak Hour Volume
Page 7 of 19
Trip Generation
The number of trips generated by a development is a function of the type and quantity of the land use within
the development. The number of vehicle trips generated by a proposed development can be estimated based
on the trip generation rates and equations provided in the publication entitled Trip Generation Manual, Tenth
Edition, by the Institute of Transportation Engineers (ITE). Estimates of the number of trips generated by the
development alternatives were made for typical weekdays and AM and PM peak hours.
The trip generation equations, directional splits, and the estimated trips are shown in Table 1.
Table 1: Trip Generation Characteristics for Proposed Development
Land Use
(ITE Land Use) ITE Code Variable
(X) Average Weekday AM Peak Hour PM Peak Hour
Equations1
Multifamily
Housing (Mid Rise) 221 Dwelling
Units T = 5.45(X) – 1.75 Ln(T) = 0.98 Ln(X)‐0.98 Ln(T) = 0.96 Ln(X)‐1.00
Directional Splits2
Multifamily
Housing (Mid Rise) 221 Dwelling
Units 50/50 26/74 61/39
Trips Generated
Land Use Variable
Amount
Variable
(X) Total Enter Exit Total Enter Exit Total Enter Exit
Multifamily
Housing (Mid Rise) 350 Dwelling
Units 1,906 953 953 117 30 87 147 89 58
Total New Trips 1,906 953 953 117 30 87 147 89 58
1 T = Trip Ends; 2 XX / YY = % entering vehicles / % exiting vehicles
Trip Distribution and Assignment
The existing traffic volumes were reviewed along with the location of the proposed development to
determine the directions from which traffic would approach and depart the development. The directional
distribution used for analysis assumes that 30% of the trips that access the site come from the south, and
70% from the north. Traffic volumes predicted to be generated by the proposed development (Table 1) were
assigned to the area roadways and site access points based on the directional distribution described above.
Assignment percentages for entering and exiting peak hour trips are shown in Figure 6 and Figure 7
respectively. This traffic assignment is conservative because all site traffic has been assigned to the proposed
driveways on the parking facilities developed with the proposed development. None of the site traffic has
been assumed to park on the street. The resulting site generated peak hour trips are shown in Figure 8
(entering) and Figure 9 (exiting). Total site generated peak hour traffic volumes are shown in Figure 10.
Total Traffic Volumes
The projected total traffic volumes in the buildout year (2021) were calculated by adding the site generated
traffic volumes to the background traffic volumes. The projected total traffic volumes at the study
intersections under buildout conditions are shown in Figure 11.
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234 Figure 6
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
2
5
%
(
2
5
%)
2
5
%
(
2
5
%)
2
0
%
(
2
0
%)
1
0
%
(
1
0
%)
1
0
%
(
1
0
%)
1
0
%
(
1
0
%)
1
3
%
(
1
3
%)
1
7
%
(
1
7
%)
8
%
(
8
%)
2
%
(
2
%)
12% (12%)
8% ( 8%)
12% (12%)
10% (10%)
13% (13%)
12% (12%)
12% (12%)
13% (13%)
8% (8%)
10% (10%)
10% (10%)
12% (12%)
1
0
%
(
1
0
%)
5
%
(
5
%)
1
0
%
(
1
0
%)
5
%
(
5
%)
2
0
%
(
2
0
%)
N
NOT TO SCALE
Entering
Assumed Directional Distribution & Assignment Percentages
Study Intersection
Legend
AM (PM) Peak Hour Percentage
20%50%
30%
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234 Figure 7
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
15% (15%)
10% (10%)
1
5
%
(
1
5
%)
1
0
%
(
1
0
%)
10% (10%)
2
0
%
(
2
0
%)
3
%
(
3
%)
20% (20%)
18% (18%)
27% (27%)
3
%
(
3
%)
N
NOT TO SCALE
Exiting
Assumed Directional Distribution & Assignment Percentages
1
0
%
(
1
0
%)
5% (5%)
1
0
%
(
1
0
%)
1
0
%
(
1
0
%)
1
3
%
(
1
3
%)
12% (12%)
1
0
%
(
1
0
%)
1
2
%
(
1
2
%)
10% (10%)
5% (5%)
1
8
%
(
1
8
%)
3
%
(
3
%)
27% (27%)
1
8
%
(
1
8
%)
5
%
(
5
%)
10% (10%)
1
7
%
(
1
7
%)
5
%
(
5
%)
5% (5%)
Study Intersection
Legend
AM (PM) Peak Hour Percentage
40%30%
30%
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234 Figure 8
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
N
NOT TO SCALE
Entering
Site Generated Peak Hour Trips
8
(
2
3
)
8
(
2
2
)
6
(
1
8
)
3
(
9
)
3
(
1
0
)
3
(
9
)
4
(
1
2
)
5
(
1
5
)
2
(
8
)
1
(
2
)
2
(
4
)
6
(
1
8
)
4 (11)
4 (12)
2 (8)
4 (11)
2 ( 8)
4 (10)
3
(
9
)
2
(
5
)
3
(
1
0
)
3 (9)
4 (12)
3 (11)
3 (9)
3 (9)
3 (11)
Study Intersection
Legend
AM (PM) Peak Hour Trips
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234 Figure 9
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
N
NOT TO SCALE
Exiting
Site Generated Peak Hour Trips
13 (9)
8 (6)
1
2
(
9
)
8
(
6
)
8 (6)
1
8
(
1
1
)
3
(
2
)
18 (12)
16 (10)
23 (16)
3
(
2
)
8
(
6
)
4 (3)
8
(
6
)
9
(
6
)
1
1
(
8
)
10 (7)
9
(
6
)
1
0
(
7
)
9 (6)
5 (3)
1
6
(
1
0
)
3
(
2
)
23 (16)
1
6
(
1
0
)
4
(
3
)
8 (6)
1
5
(
1
0
)
4
(
3
)
4 (3)
Study Intersection
Legend
AM (PM) Peak Hour Trips
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
Figure 10
N
NOT TO SCALE
Peak Hour Traffic Volumes
Total Site Generated
8
(
2
3
)
8
(
2
2
)
13 (9)
8 (6)
1
2
(
9
)
1
4
(
2
4
)
8 (6)
1
8
(
1
1
)
3
(
9
)
3
(
2
)
18 (12)
3
(
1
0
)
3
(
9
)
16 (10)
23 (16)
4
(
1
2
)
5
(
1
5
)
3
(
2
)
2
(
8
)
1
(
2
)
8
(
6
)
4 (3)
2
(
4
)
1
4
(
2
4
)
9
(
6
)
1
1
(
8
)
4 (11)
4 (12)
10 (7)
2 (8)
9
(
6
)
1
0
(
7
)
9 ( 6)
4 (11)
2 ( 8)
4 (10)
5 (3)
1
9
(
1
9
)
2
(
5
)
6
(
1
2
)
3 ( 9)
23 (16)
1
6
(
1
0
)
4
(
3
)
4 (12)
3 (11)
3 ( 9)
11 (15)
1
5
(
1
0
)
4
(
3
)
3 (11)
4 ( 3)
Study Intersection
Legend
AM (PM) Peak Hour Volume
SUITE 1660
972-248-3006 FAX 972-248-3855
3030 LBJ FREEWAY
TBPE FIRM F-450
DALLAS, TEXAS 75234
S
t
a
t
e
S
t
Division St
Federal Way
E Dwy
N
W
D
w
y
W Dwy
S
W
D
w
y
Southcrest Ct
C
a
r
r
o
l
l
A
v
e
S
E
D
w
y
N
E
D
w
y
Figure 11
N
NOT TO SCALE
Peak Hour Traffic Volumes
Buildout Total (2021)
12 (27)
16 (47)
7 (21)
9
(
4
1
)
9
3
(
1
2
3
)
1
(
8
)
28 (30)
9 (10)
16 (14)
2
(
8
)
4
7
(
1
4
2
)
1
(
2
)
8 (22)
14 (67)
1 ( 8)
2
4
(
9
5
)
8
1
(
4
9
)
9
(
1
0
)
16 (31)
18 (64)
38 (45)
9
(
1
1
1
)
2
2
(
9
3
)
4
(
1
4
)
2
(
4
)
8
4
4
(
1
,
1
1
6
)
1
0
(
1
1
)
3
(
2
)
21 (22)
0 ( 1)
9 ( 4)
1
0
(
4
)
9
5
1
(
1
,
1
5
7
)
1
5
(
1
3
)
1 ( 9)
2 (12)
36 (103)
1 ( 1)
42 (182)
7
(
1
3
)
7
9
5
(
9
4
4
)
3
8
(
8
7
)
7
(
2
2
)
1 (21)
0 ( 1)
1 (24)
3
(
1
)
8
6
4
(
1
,
0
4
2
)
5
4
(
9
0
)
1
(
1
0
)
4
7
(
1
4
7
)
4 (3)
2
(
4
)
1
1
5
(
1
5
5
)
9
(
6
)
1
1
(
8
)
17 (27)
4 (12)
29 (14)
2 ( 8)
9
(
6
)
1
0
(
7
)
22 (22)
4 (11)
21 (15)
4 (10)
5 (3)
8
3
2
(
1
,
0
7
5
)
2
(
5
)
9
2
3
(
1
,
1
4
4
)
3 ( 9)
64 (277)
1
6
(
1
0
)
4
(
3
)
4 ( 12)
88 (167)
3 ( 9)
52 (276)
1
5
(
1
0
)
4
(
3
)
3 ( 11)
89 (159)
Study Intersection
Legend
AM (PM) Peak Hour Volume
Page 14 of 19
Intersection Capacity Analysis
The Level of Service (LOS) of an intersection is a qualitative measure of capacity and operating conditions and
is directly related to vehicle delay. LOS is given a letter designation from A to F, with LOS A representing very
short delays and LOS F representing very long delays or over‐capacity conditions. Table 2 shows the LOS
criteria for signalized and unsignalized intersections and approaches.
Table 2: Level of Service Criteria for Intersections & Approaches
Level‐of‐
Service
(LOS)
Control Delay
(seconds/vehicle)
Signalized
Control Delay
(seconds/vehicle)
Unsignalized
A 10.0 or less 10.0 or less
B 10.1 to 20.0 10.1 to 15.0
C 20.1 to 35.0 15.1 to 25.0
D 35.1 to 55.0 25.1 to 35.0
E 55.1 to 80.0 35.1 to 50.0
F Over 80.0
or Volume exceeds Capacity
Over 50.0
or Volume exceeds Capacity
SOURCE: Highway Capacity Manual, HCM 2010, Transportation Research Board, 2010
Capacity analyses were conducted using the Synchro 10 traffic analysis software package for the
study area intersections under the analysis scenarios listed in Table 3:
Table 3: Intersection Capacity Analysis Scenarios
Scenario Lane Configurations Traffic Volumes
2019 Existing Existing 2019 Existing (Figure 4)
2021 Buildout Background Existing 2021 Buildout Background (Figure 5)
2021 Buildout Total Proposed 2021 Buildout Total (Figure 11)
Page 15 of 19
Intersection capacity analysis results are presented in Table 4.
Table 4: Capacity Analysis Results
Scenario AM Peak Hour LOS PM Peak Hour LOS
Int. EB WB NB SB Int.EB WB NB SB
1: Carroll Ave & Federal Way Signalized
2019 Existing A A A A A B B B B B
2021 Buildout Background A A A A A B B B B B
2021 Buildout Total A A A A A B B B C B
3: Carroll Ave & Division St Unsignalized – TWSC
2019 Existing ‐ 1 C D A* A* ‐
1 D D B* B*
2021 Buildout Background ‐
1 C E B* B* ‐
1 F E B* C*
2021 Buildout Total ‐
1 D C
2 B* B* ‐ 1 F E C* B*
2021 Buildout Total –
Add WB Right Turn Lane ‐ 1 D C B* B* ‐
1 F D C* B*
5: State St & Division St Unsignalized – AWSC
2019 Existing A A A A A A A A A A
2021 Buildout Background A A A A A A A A A A
2021 Buildout Total A A A A A A A A A A
7: State St & Federal Way Unsignalized – AWSC
2019 Existing A A A A A A A A A A
2021 Buildout Background A A A A AA A A B A
2021 Buildout Total A A A A AA A A B A
2: Carroll Ave & W Dwy Unsignalized – OWSC
2021 Buildout Total ‐
1 ‐ B**A ‐‐1 ‐ B** A ‐
4: NW Dwy & Division St Unsignalized – TWSC
2021 Buildout Total ‐
1 A A*A ‐‐1 AA* A ‐
6: State St & E Dwy Unsignalized – TWSC
2021 Buildout Total ‐
1 A ‐A* A‐1 B‐ A* A
8: Federal Way & SW Dwy Unsignalized – TWSC
2021 Buildout Total ‐
1 A* A
‐ A‐1 A* A
‐ B
9: NE Dwy & Federal Way Unsignalized – TWSC
2021 Buildout Total ‐
1 A A*A ‐‐1 AA* A ‐
10: Federal Way & SE Dwy Unsignalized – TWSC
2021 Buildout Total ‐
1 A* A
‐ A‐1 A* A
‐ B
1 HCM methodology does not provide intersection‐wide delay/LOS for TWSC analysis
2 Additional westbound right turns reduced the average delay – thereby improving LOS from E to C.
* LOS for Left Turn Movement
** LOS for Right Turn Movement
As shown in Table 4, all intersections and most approaches operate at level of service C or better in all
scenarios. In the 2021 Buildout Total scenario, the addition of westbound right‐turning traffic volumes
decreases the average vehicle delay, and thereby improves the level of service from E to C. The westbound
approach of Carroll Avenue at Division Street has enough width to be restriped in order to add a right turn
only lane. The addition of this right turn lane would slightly reduce the approach delay. However, the stop‐
controlled approaches (EB & WB) of Division Street at Carroll Avenue operate at poor levels of service due to
the delay associated with crossing against conflicting Carroll Avenue traffic. This is not due to lack of capacity,
but to lack of available gaps for left‐turning and through‐moving vehicles.
Page 16 of 19
As shown earlier in Figure 9, it was assumed that due to the existing poor level of service, drivers exiting the
north driveway to go south on Carroll Avenue would prefer to avoid making a left turn at the stop‐controlled
westbound approach of Division Street and would instead turn left at the signalized westbound approach of
Federal Way. If Carroll Avenue at Division Street were signalized in the future, levels of service would likely
be similar to those at Carroll Avenue at Federal Way. In that case, drivers exiting the north driveway to go
south on Carroll Avenue would likely turn left from Division Street. In this way, signalization of Carroll Avenue
at Division Street would draw traffic away from the westbound approach of Carroll Avenue at Federal Way.
It is possible that other preferred area routes would be similarly affected.
Right Turn Lane Analysis
According to Southlake Driveway Ordinance No. 634:
“5.4 AUXILIARY LANES – a. WHEN REQUIRED: As a condition of a Driveway Permit, the
Applicant shall provide a deceleration lane for any driveway located on an arterial street if
the right turn ingress volume exceeds 50 vehicles in the design hour…”
Carroll Avenue is the only arterial street with a proposed driveway. Table 5 summarizes the predicted right
turn volumes under (2021) buildout total traffic conditions (Figure 11) at the proposed West Driveway on
Carroll Avenue.
Table 5: Right Turn Deceleration Lane Analysis Results
Intersection Scenario Approach Speed Limit
[mph]
Volume [vph]
AM (PM)
Threshold
[vph]
Exceeds Threshold?
AM (PM)
Carroll Avenue at
West Driveway
2021 Buildout
Total NB 30 2 (5) 50 No (No)
As shown in Table 5, a right turn deceleration lane is not needed at the proposed West Driveway on Carroll
Avenue.
Access Spacing
According to Southlake Driveway Ordinance No. 634, a driveway on an arterial road needs to meet the
following criteria described in Table 6:
Table 6: Access Spacing Analysis Results
Distance to Required
[Feet]
Proposed
[Feet]
Meets Required
Distance?
Intersection 200 ~250' Yes
Centerline of Other Driveway(s) 250 ~420' Yes
As shown in Table 6, the proposed West driveway location will meet to the required access spacing distances.
Page 17 of 19
Sight Distance Evaluation
As part of this traffic analysis, the available and desired intersection sight distances for motorists accessing
adjacent streets from the proposed site were analyzed. The sight distances desired at each site exit driveway
were estimated using the procedures developed by the American Association of State Highway and
Transportation Officials (AASHTO) and published in the 2011 edition of A Policy on Geometric Design of
Highways and Streets. At each driveway, the motorist should be able to see if and when adequate gaps exist
to perform their desired maneuver. Table 7 presents the desired and available sight distance at the proposed
site access point.
Table 7:Analysis of Intersection Sight Distances
Major Roadway: Carroll Ave Division St State St Federal Way
Minor Roadway: West Dwy. North Dwy. East Dwy. South Dwy.
Posted Speed Limit: 30 mph 30 mph 30 mph 30 mph
Design Vehicle: Passenger Car
Desired Sight Distance to the Left: 290' 290' 290' 290'
Available Sight Distance to the Left: 670'
330' 470' 165'
Sight Distance Available > Desired: Yes Yes Yes No
Desired Sight Distance to the Right: N/A
1 335' 335' 335'
Available Sight Distance to the Right: N/A
1 185' 1,050' 330'
Sight Distance Available > Desired: N/A1 No Yes No
1 Right in/Right out driveway
At the time of the field visit to the site and under the existing roadway conditions, desired sight distance is
predicted to be available for the exiting traffic from the proposed development at driveways on Carroll
Avenue and State Street. Though desired sight distance is not predicted to be available on Division Street or
Federal Way, stopping sight distance is predicted to be available for traffic on all approaches that pass a
proposed driveway.
Intersection sight distance methodology assumes that through traffic is travelling at the speed limit.
However, vehicles on Division Street and Federal Way near the proposed driveways will be turning from cross
streets or accelerating from a stop – travelling below the speed limit of 30 mph. Available intersection sight
distances at the proposed locations of the north and south driveways are adequate for these conditions.
Proposed driveway configurations will be similar to other midblock access points throughout Southlake Town
Square:
the driveway for the East Park garage on Federal Way (southwest of the movie theater),
the north/south street on Prospect Street between Charming Charlie and Tempur‐Pedic,
the driveways on the north side of Main Street between Carroll Avenue and State Street, and
the driveways on Main Street between Grand Avenue and Central Avenue.
Note that, as with the existing driveways listed above, while on‐street parking could partially obstruct lines
of sight at any driveway, the sight triangles are free from fixed obstructions such as buildings and landscaping.
Lee Engineering recommends maintaining intersection sight triangles free from fixed obstructions at the
proposed driveways.
Page 19 of 19
APPENDIX
ITE Land Use 221:
Traffic Counts:
Synchro Reports:
P. 1 - 6
P. 7 - 10
P. 11 - 52
Appendix - p. 1 of 52
Appendix - p. 1 of 52
Appendix - p. 2 of 52
Appendix - p. 2 of 52
Appendix - p. 3 of 52
Appendix - p. 3 of 52
Appendix - p. 4 of 52
Appendix - p. 4 of 52
Appendix - p. 5 of 52
Appendix - p. 5 of 52
Appendix - p. 6 of 52
Appendix - p. 6 of 52
GRAM Traffic NTX Inc.
1120 W. Lovers Lane
Arlington, Texas, United States 76013
817.265.8968
Count Name: 1 - CARROLL
AVE @ FEDERAL WAY
Site Code:
Start Date: 09/19/2019
Page No: 1
Turning Movement Data
Start Time
N CARROLL AVE FEDERAL WAY N CARROLL AVE FEDERAL WAY
Southbound Westbound Northbound Eastbound
Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total
Int.
Total
6:30 AM 4 97 0 0 101 4 0 3 0 7 0 105 4 0 109 0 0 0 0 0 217
6:45 AM 5 117 0 0 122 2 0 1 0 3 0 108 3 0 111 0 1 0 0 1 237
Hourly Total 9 214 0 0 223 6 0 4 0 10 0 213 7 0 220 0 1 0 0 1 454
7:00 AM 6 109 0 0 115 4 0 3 0 7 0 125 5 0 130 0 0 0 0 0 252
7:15 AM 10 152 0 0 162 5 0 2 0 7 0 151 6 0 157 0 0 0 0 0 326
7:30 AM 3 179 1 0 183 3 0 5 0 8 1 152 11 1 165 0 0 0 0 0 356
7:45 AM 18 172 1 0 191 2 0 3 0 5 3 182 4 1 190 0 0 1 0 1 387
Hourly Total 37 612 2 0 651 14 0 13 0 27 4 610 26 2 642 0 0 1 0 1 1321
8:00 AM 9 176 0 0 185 3 0 5 0 8 0 162 4 2 168 0 0 0 0 0 361
8:15 AM 13 185 1 0 199 8 1 4 0 13 2 158 9 2 171 1 0 0 0 1 384
*** BREAK *** - - - - - - - - - - - - - - - - - - - - -
Hourly Total 22 361 1 0 384 11 1 9 0 21 2 320 13 4 339 1 0 0 0 1 745
4:30 PM 12 230 1 1 244 33 0 15 0 48 1 138 18 5 162 3 0 7 0 10 464
4:45 PM 14 206 1 0 221 30 1 15 0 46 5 192 16 4 217 4 1 4 0 9 493
Hourly Total 26 436 2 1 465 63 1 30 0 94 6 330 34 9 379 7 1 11 0 19 957
5:00 PM 19 233 0 2 254 46 0 22 0 68 2 216 13 7 238 6 0 6 0 12 572
5:15 PM 19 212 0 3 234 33 0 22 0 55 3 201 19 3 226 1 0 4 0 5 520
5:30 PM 16 209 0 2 227 29 0 18 0 47 1 162 12 5 180 7 0 6 0 13 467
5:45 PM 22 219 0 0 241 24 0 12 0 36 0 194 12 4 210 2 0 3 0 5 492
Hourly Total 76 873 0 7 956 132 0 74 0 206 6 773 56 19 854 16 0 19 0 35 2051
6:00 PM 18 211 0 1 230 32 0 13 0 45 0 180 11 8 199 2 0 6 0 8 482
6:15 PM 6 169 0 2 177 25 0 8 0 33 0 158 13 3 174 5 0 1 0 6 390
Grand Total 194 2876 5 11 3086 283 2 151 0 436 18 2584 160 45 2807 31 2 38 0 71 6400
Approach % 6.3 93.2 0.2 0.4 - 64.9 0.5 34.6 0.0 - 0.6 92.1 5.7 1.6 - 43.7 2.8 53.5 0.0 - -
Total % 3.0 44.9 0.1 0.2 48.2 4.4 0.0 2.4 0.0 6.8 0.3 40.4 2.5 0.7 43.9 0.5 0.0 0.6 0.0 1.1 -
Lights 193 2843 5 11 3052 280 2 148 0 430 18 2558 156 45 2777 31 1 38 0 70 6329
% Lights 99.5 98.9 100.0 100.0 98.9 98.9 100.0 98.0 - 98.6 100.0 99.0 97.5 100.0 98.9 100.0 50.0 100.0 - 98.6 98.9
Mediums 1 23 0 0 24 3 0 2 0 5 0 21 4 0 25 0 1 0 0 1 55
% Mediums 0.5 0.8 0.0 0.0 0.8 1.1 0.0 1.3 - 1.1 0.0 0.8 2.5 0.0 0.9 0.0 50.0 0.0 - 1.4 0.9
Articulated
Trucks 0 10 0 0 10 0 0 1 0 1 0 5 0 0 5 0 0 0 0 0 16
% Articulated
Trucks 0.0 0.3 0.0 0.0 0.3 0.0 0.0 0.7 - 0.2 0.0 0.2 0.0 0.0 0.2 0.0 0.0 0.0 - 0.0 0.3
Appendix - p. 7 of 52
Appendix - p. 7 of 52
GRAM Traffic NTX Inc.
1120 W. Lovers Lane
Arlington, Texas, United States 76013
817.265.8968
Count Name: 2 - CARROLL
AVE @ DIVISION ST
Site Code:
Start Date: 09/19/2019
Page No: 1
Turning Movement Data
Start Time
N CARROLL AVE DIVISION ST N CARROLL AVE SOUTHCREST CT
Southbound Westbound Northbound Eastbound
Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total
Int.
Total
6:30 AM 2 94 0 0 96 1 0 3 0 4 0 108 3 0 111 0 0 0 0 0 211
6:45 AM 2 124 0 0 126 0 0 2 0 2 0 108 4 0 112 0 0 1 0 1 241
Hourly Total 4 218 0 0 222 1 0 5 0 6 0 216 7 0 223 0 0 1 0 1 452
7:00 AM 2 115 0 0 117 1 0 1 0 2 0 121 4 0 125 0 0 0 0 0 244
7:15 AM 3 156 1 0 160 1 0 1 0 2 2 154 1 0 157 0 0 0 0 0 319
7:30 AM 1 192 2 0 195 3 0 1 0 4 0 162 1 0 163 0 0 1 0 1 363
7:45 AM 3 200 3 0 206 1 0 0 0 1 0 186 3 0 189 0 0 0 0 0 396
Hourly Total 9 663 6 0 678 6 0 3 0 9 2 623 9 0 634 0 0 1 0 1 1322
8:00 AM 4 196 2 0 202 2 0 1 0 3 0 171 1 0 172 0 0 0 0 0 377
8:15 AM 2 196 2 1 201 2 0 1 0 3 2 164 1 0 167 1 0 1 0 2 373
8:30 AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
*** BREAK *** - - - - - - - - - - - - - - - - - - - - -
Hourly Total 6 392 4 1 403 4 0 2 0 6 2 335 2 0 339 1 0 1 0 2 750
4:30 PM 0 240 0 0 240 4 0 2 0 6 0 155 0 0 155 1 0 1 0 2 403
4:45 PM 0 220 0 0 220 3 0 2 0 5 2 221 0 0 223 3 0 5 0 8 456
Hourly Total 0 460 0 0 460 7 0 4 0 11 2 376 0 0 378 4 0 6 0 10 859
5:00 PM 0 256 2 0 258 0 0 3 0 3 1 254 1 0 256 2 0 2 0 4 521
5:15 PM 2 230 2 1 235 1 1 2 0 4 1 237 1 0 239 0 0 2 0 2 480
5:30 PM 2 242 0 2 246 0 0 2 0 2 0 202 0 0 202 3 0 1 0 4 454
5:45 PM 1 234 1 2 238 1 0 0 0 1 0 211 0 0 211 4 0 1 0 5 455
Hourly Total 5 962 5 5 977 2 1 7 0 10 2 904 2 0 908 9 0 6 0 15 1910
6:00 PM 2 226 0 0 228 2 0 3 0 5 0 201 1 0 202 1 0 2 0 3 438
6:15 PM 0 197 0 0 197 0 0 1 0 1 0 198 1 0 199 0 0 1 0 1 398
Grand Total 26 3118 15 6 3165 22 1 25 0 48 8 2853 22 0 2883 15 0 18 0 33 6129
Approach % 0.8 98.5 0.5 0.2 - 45.8 2.1 52.1 0.0 - 0.3 99.0 0.8 0.0 - 45.5 0.0 54.5 0.0 - -
Total % 0.4 50.9 0.2 0.1 51.6 0.4 0.0 0.4 0.0 0.8 0.1 46.5 0.4 0.0 47.0 0.2 0.0 0.3 0.0 0.5 -
Lights 26 3080 15 6 3127 22 1 25 0 48 8 2826 19 0 2853 15 0 17 0 32 6060
% Lights 100.0 98.8 100.0 100.0 98.8 100.0 100.0 100.0 - 100.0 100.0 99.1 86.4 - 99.0 100.0 - 94.4 - 97.0 98.9
Mediums 0 31 0 0 31 0 0 0 0 0 0 18 2 0 20 0 0 1 0 1 52
% Mediums 0.0 1.0 0.0 0.0 1.0 0.0 0.0 0.0 - 0.0 0.0 0.6 9.1 - 0.7 0.0 - 5.6 - 3.0 0.8
Articulated
Trucks 0 7 0 0 7 0 0 0 0 0 0 9 1 0 10 0 0 0 0 0 17
% Articulated
Trucks 0.0 0.2 0.0 0.0 0.2 0.0 0.0 0.0 - 0.0 0.0 0.3 4.5 - 0.3 0.0 - 0.0 - 0.0 0.3
Appendix - p. 8 of 52
Appendix - p. 8 of 52
GRAM Traffic NTX Inc.
1120 W. Lovers Lane
Arlington, Texas, United States 76013
817.265.8968
Count Name: 3 - STATE ST @
DIVISION ST
Site Code:
Start Date: 09/19/2019
Page No: 1
Turning Movement Data
Start Time
STATE ST DIVISION ST STATE ST DIVISION ST
Southbound Westbound Northbound Eastbound
Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total
Int.
Total
6:30 AM 0 7 0 0 7 0 0 1 0 1 2 4 1 0 7 0 0 0 0 0 15
6:45 AM 0 8 1 0 9 1 0 0 0 1 0 2 0 0 2 1 1 0 0 2 14
Hourly Total 0 15 1 0 16 1 0 1 0 2 2 6 1 0 9 1 1 0 0 2 29
7:00 AM 1 6 0 0 7 0 1 0 0 1 0 3 1 0 4 1 2 0 0 3 15
7:15 AM 0 9 0 0 9 0 1 2 0 3 0 4 1 0 5 0 1 0 0 1 18
7:30 AM 0 9 0 0 9 0 3 1 0 4 0 3 1 0 4 3 0 1 0 4 21
7:45 AM 0 21 1 0 22 1 8 2 0 11 1 10 0 0 11 1 4 4 0 9 53
Hourly Total 1 45 1 0 47 1 13 5 0 19 1 20 3 0 24 5 7 5 0 17 107
8:00 AM 0 23 0 0 23 2 1 3 0 6 1 9 0 0 10 5 3 1 0 9 48
8:15 AM 1 18 0 0 19 3 2 4 0 9 0 7 0 0 7 4 1 1 0 6 41
8:30 AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
*** BREAK *** - - - - - - - - - - - - - - - - - - - - -
Hourly Total 1 41 0 0 42 5 3 7 0 15 1 16 0 0 17 9 4 2 0 15 89
4:30 PM 0 21 1 0 22 5 5 5 0 15 1 25 2 0 28 1 1 0 0 2 67
4:45 PM 2 21 4 0 27 5 7 4 0 16 3 24 0 0 27 8 3 0 0 11 81
Hourly Total 2 42 5 0 49 10 12 9 0 31 4 49 2 0 55 9 4 0 0 13 148
5:00 PM 2 22 5 0 29 5 17 8 0 30 3 32 1 0 36 1 4 4 0 9 104
5:15 PM 2 18 2 0 22 3 10 8 0 21 1 31 0 0 32 6 1 1 0 8 83
5:30 PM 1 23 4 0 28 5 5 3 0 13 0 23 1 0 24 3 1 2 0 6 71
5:45 PM 1 17 5 0 23 6 6 7 0 19 1 18 0 0 19 0 1 1 0 2 63
Hourly Total 6 80 16 0 102 19 38 26 0 83 5 104 2 0 111 10 7 8 0 25 321
6:00 PM 2 16 1 0 19 6 9 4 0 19 1 30 1 0 32 2 1 0 0 3 73
6:15 PM 2 10 2 0 14 5 5 1 0 11 0 17 1 0 18 2 1 0 1 4 47
6:30 PM 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0 0 0 1
Grand Total 14 249 26 0 289 47 80 53 0 180 14 243 10 0 267 38 25 15 1 79 815
Approach % 4.8 86.2 9.0 0.0 - 26.1 44.4 29.4 0.0 - 5.2 91.0 3.7 0.0 - 48.1 31.6 19.0 1.3 - -
Total % 1.7 30.6 3.2 0.0 35.5 5.8 9.8 6.5 0.0 22.1 1.7 29.8 1.2 0.0 32.8 4.7 3.1 1.8 0.1 9.7 -
Lights 14 249 26 0 289 46 79 51 0 176 14 242 9 0 265 38 25 15 1 79 809
% Lights 100.0 100.0 100.0 - 100.0 97.9 98.8 96.2 - 97.8 100.0 99.6 90.0 - 99.3 100.0 100.0 100.0 100.0 100.0 99.3
Mediums 0 0 0 0 0 1 1 2 0 4 0 1 1 0 2 0 0 0 0 0 6
% Mediums 0.0 0.0 0.0 - 0.0 2.1 1.3 3.8 - 2.2 0.0 0.4 10.0 - 0.7 0.0 0.0 0.0 0.0 0.0 0.7
Articulated
Trucks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
% Articulated
Trucks 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Appendix - p. 9 of 52
Appendix - p. 9 of 52
GRAM Traffic NTX Inc.
1120 W. Lovers Lane
Arlington, Texas, United States 76013
817.265.8968
Count Name: 4 - STATE ST @
FEDERAL WAY
Site Code:
Start Date: 09/19/2019
Page No: 1
Turning Movement Data
Start Time
STATE ST FEDERAL WAY STATE ST FEDERAL WAY
Southbound Westbound Northbound Eastbound
Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total Left Thru Right U-Turn
App.
Total
Int.
Total
6:30 AM 0 1 5 0 6 0 2 2 0 4 2 3 0 0 5 2 2 3 0 7 22
6:45 AM 0 7 3 0 10 3 1 0 0 4 0 1 1 0 2 1 1 5 0 7 23
Hourly Total 0 8 8 0 16 3 3 2 0 8 2 4 1 0 7 3 3 8 0 14 45
7:00 AM 0 5 1 0 6 0 6 0 0 6 2 2 0 0 4 2 3 3 0 8 24
7:15 AM 1 4 4 0 9 0 2 0 0 2 0 4 0 0 4 1 5 7 0 13 28
7:30 AM 0 7 2 0 9 1 4 1 0 6 1 3 0 0 4 1 5 4 0 10 29
7:45 AM 3 21 3 0 27 0 1 1 0 2 2 7 1 0 10 2 4 7 0 13 52
Hourly Total 4 37 10 0 51 1 13 2 0 16 5 16 1 0 22 6 17 21 0 44 133
8:00 AM 5 18 1 0 24 0 4 4 0 8 1 4 2 0 7 2 4 10 0 16 55
8:15 AM 0 21 3 0 24 0 3 1 0 4 4 5 1 0 10 2 2 11 0 15 53
8:30 AM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
*** BREAK *** - - - - - - - - - - - - - - - - - - - - -
Hourly Total 5 39 4 0 48 0 7 5 0 12 5 9 3 0 17 4 6 21 0 31 108
4:30 PM 0 14 13 0 27 1 10 4 0 15 22 22 2 0 46 3 14 9 0 26 114
4:45 PM 1 11 14 0 26 1 15 4 0 20 15 15 2 0 32 7 10 8 0 25 103
Hourly Total 1 25 27 0 53 2 25 8 0 35 37 37 4 0 78 10 24 17 0 51 217
5:00 PM 0 11 20 0 31 1 9 7 0 17 33 24 5 0 62 4 16 8 0 28 138
5:15 PM 4 6 11 0 21 3 19 5 0 27 27 24 2 0 53 5 14 11 0 30 131
5:30 PM 4 13 14 0 31 2 13 3 0 18 17 14 3 0 34 5 13 11 0 29 112
5:45 PM 1 17 7 0 25 0 14 2 0 16 13 14 2 0 29 3 19 9 0 31 101
Hourly Total 9 47 52 0 108 6 55 17 0 78 90 76 12 0 178 17 62 39 0 118 482
6:00 PM 3 8 9 0 20 4 11 7 0 22 14 25 0 0 39 2 10 12 0 24 105
6:15 PM 1 4 9 0 14 1 11 1 0 13 11 14 1 0 26 3 11 2 0 16 69
6:30 PM 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Grand Total 23 168 119 0 310 17 125 42 0 184 164 181 22 0 367 45 133 120 0 298 1159
Approach % 7.4 54.2 38.4 0.0 - 9.2 67.9 22.8 0.0 - 44.7 49.3 6.0 0.0 - 15.1 44.6 40.3 0.0 - -
Total % 2.0 14.5 10.3 0.0 26.7 1.5 10.8 3.6 0.0 15.9 14.2 15.6 1.9 0.0 31.7 3.9 11.5 10.4 0.0 25.7 -
Lights 23 168 118 0 309 17 123 41 0 181 164 181 21 0 366 44 129 120 0 293 1149
% Lights 100.0 100.0 99.2 - 99.7 100.0 98.4 97.6 - 98.4 100.0 100.0 95.5 - 99.7 97.8 97.0 100.0 - 98.3 99.1
Mediums 0 0 1 0 1 0 2 1 0 3 0 0 1 0 1 1 3 0 0 4 9
% Mediums 0.0 0.0 0.8 - 0.3 0.0 1.6 2.4 - 1.6 0.0 0.0 4.5 - 0.3 2.2 2.3 0.0 - 1.3 0.8
Articulated
Trucks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 1
% Articulated
Trucks 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 - 0.0 0.0 0.8 0.0 - 0.3 0.1
Appendix - p. 10 of 52
Appendix - p. 10 of 52
Timings 2019 Existing AM Peak Hour.syn
1: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing AM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBL SBT
Lane Configurations
Traffic Volume (vph)1 0 16 1 17 6 6 654 43 712
Future Volume (vph)1 0 16 1 17 6 6 654 43 712
Turn Type Perm NA Perm NA Perm custom pm+pt NA pm+pt NA
Protected Phases 4 8 5216
Permitted Phases 4 8 8 5 2 6
Detector Phase 4488855216
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None Max
Act Effct Green (s)6.0 6.1 6.1 29.1 30.0 30.2 31.9
Actuated g/C Ratio 0.15 0.15 0.15 0.74 0.76 0.77 0.81
v/c Ratio 0.01 0.06 0.05 0.02 0.27 0.07 0.26
Control Delay 0.0 16.2 0.3 2.9 5.9 2.7 4.3
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 0.0 16.2 0.3 2.9 5.9 2.7 4.3
LOS A BA AAAA
Approach Delay 8.2 5.9 4.2
Approach LOS A A A
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 39.4
Natural Cycle: 55
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.27
Intersection Signal Delay: 5.1 Intersection LOS: A
Intersection Capacity Utilization 39.4%ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 11 of 52
Appendix - p. 11 of 52
HCM 6th TWSC 2019 Existing AM Peak Hour.syn
3: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.3
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 1 02803268361107849
Future Vol, veh/h 1 02803268361107849
Conflicting Peds, #/hr 0 000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free
RT Channelized - - None - - None - - Yield - - - None
Storage Length 0 -----100---100--
Veh in Median Storage, # - 0 - - 0 - - 0 - - - 0 -
Grade, % - 0 - - 0 - - 0 - - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 2 222222222222
Mvmt Flow 1 02803271961118259
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1218 1577 417 1163 1584 363 834 0 0 725 719 0 0
Stage 1 854 854 - 726 726 --------
Stage 2 364 723 - 437 858 --------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 --------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 --------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 136 109 585 150 107 634 795 - - 498 878 - -
Stage 1 320 373 - 382 428 --------
Stage 2 627 429 - 568 372 --------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 134 107 585 147 105 634 795 - - 821 821 - -
Mov Cap-2 Maneuver 134 107 - 147 105 --------
Stage 1 319 367 - 381 427 --------
Stage 2 622 428 - 558 366 --------
Approach EB WB NB SB
HCM Control Delay, s 18.2 25.6 0 0.1
HCM LOS C D
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)795 - - 134 585 186 821 - -
HCM Lane V/C Ratio 0.003 - - 0.008 0.004 0.062 0.014 - -
HCM Control Delay (s) 9.5 - - 32.1 11.2 25.6 9.5 - -
HCM Lane LOS A - - D B D A - -
HCM 95th %tile Q(veh) 0 - - 0 0 0.2 0 - -
Appendix - p. 12 of 52
Appendix - p. 12 of 52
HCM 6th AWSC 2019 Existing AM Peak Hour.syn
5: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.5
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 13 8 7 6 14 10 2 29 1 1 71 1
Future Vol, veh/h 13 8 7 6 14 10 2 29 1 1 71 1
Peak Hour Factor 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
Heavy Vehicles, %222222222222
Mvmt Flow 17 10 9 8 18 13 3 38 1 1 92 1
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 7.4 7.3 7.4 7.6
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %6% 46% 20% 1%
Vol Thru, %91% 29% 47% 97%
Vol Right, % 3% 25% 33% 1%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 32 28 30 73
LT Vol 2 13 6 1
Through Vol 29 8 14 71
RT Vol 1 7 10 1
Lane Flow Rate 42 36 39 95
Geometry Grp 1111
Degree of Util (X) 0.048 0.042 0.044 0.108
Departure Headway (Hd)4.131 4.143 4.037 4.091
Convergence, Y/N Yes Yes Yes Yes
Cap 860 854 875 871
Service Time 2.189 2.219 2.114 2.138
HCM Lane V/C Ratio 0.049 0.042 0.045 0.109
HCM Control Delay 7.4 7.4 7.3 7.6
HCM Lane LOS AAAA
HCM 95th-tile Q 0.2 0.1 0.1 0.4
Appendix - p. 13 of 52
Appendix - p. 13 of 52
HCM 6th AWSC 2019 Existing AM Peak Hour.syn
7: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.4
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 7 15 32 1 12 7 8 19 4 8 67 9
Future Vol, veh/h 7 15 32 1 12 7 8 19 4 8 67 9
Peak Hour Factor 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Heavy Vehicles, % 2 22222222222
Mvmt Flow 8 17 37 1 14 8 9 22 5 9 78 10
Number of Lanes 0 10010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1 1 1 1
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1 1 1 1
Conflicting Approach RightNB SB WB EB
Conflicting Lanes Right 1 1 1 1
HCM Control Delay 7.2 7.2 7.4 7.6
HCM LOS A A A A
Lane NBLn1EBLn1WBLn1SBLn1
Vol Left, %26% 13% 5% 10%
Vol Thru, %61% 28% 60% 80%
Vol Right, %13% 59% 35% 11%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 31 54 20 84
LT Vol 8718
Through Vol 19 15 12 67
RT Vol 4 32 7 9
Lane Flow Rate 36 63 23 98
Geometry Grp 1111
Degree of Util (X) 0.041 0.067 0.026 0.11
Departure Headway (Hd) 4.134 3.854 4.015 4.067
Convergence, Y/N Yes Yes Yes Yes
Cap 861 919 881 878
Service Time 2.185 1.92 2.087 2.106
HCM Lane V/C Ratio 0.042 0.069 0.026 0.112
HCM Control Delay 7.4 7.2 7.2 7.6
HCM Lane LOS AAAA
HCM 95th-tile Q 0.1 0.2 0.1 0.4
Appendix - p. 14 of 52
Appendix - p. 14 of 52
Appendix - p. 15 of 52
Appendix - p. 15 of 52
Timings 2019 Existing PM Peak Hour.syn
1: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing PM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBU SBL SBT
Lane Configurations
Traffic Volume (vph)18 1 138 1 77 19 11 771 7 68 860
Future Volume (vph)18 1 138 1 77 19 11 771 7 68 860
Turn Type Perm NA Perm NA Perm custom pm+pt NA custom pm+pt NA
Protected Phases 4 8 5 2 1 6
Permitted Phases 4 8 8 5 2 1 6
Detector Phase 44888552116
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None None Max
Act Effct Green (s)10.3 10.5 10.5 25.5 23.3 27.3 25.8
Actuated g/C Ratio 0.23 0.23 0.23 0.56 0.51 0.60 0.57
v/c Ratio 0.13 0.52 0.19 0.08 0.51 0.19 0.48
Control Delay 10.5 22.6 3.2 5.9 14.7 6.4 12.1
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 10.5 22.6 3.2 5.9 14.7 6.4 12.1
LOS BCAABAB
Approach Delay 10.5 15.7 14.4 11.7
Approach LOS B B B B
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 45.5
Natural Cycle: 60
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.52
Intersection Signal Delay: 13.2 Intersection LOS: B
Intersection Capacity Utilization 53.6%ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 16 of 52
Appendix - p. 16 of 52
HCM 6th TWSC 2019 Existing PM Peak Hour.syn
3: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.6
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 8 0 10 41949142349484
Future Vol, veh/h 8 0 10 41949142349484
Conflicting Peds, #/hr 0 000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free
RT Channelized - - None - - None - - Yield - - - None
Storage Length 0 -----100---100--
Veh in Median Storage, # - 0 - - 0 - - 0 - - - 0 -
Grade, % - 0 - - 0 - - 0 - - - 0 -
Peak Hour Factor 92 92 92 92 92 92 92 92 92 92 92 92 92
Heavy Vehicles, % 2 222222222222
Mvmt Flow 9 0 11 4 1 10 4 993 2 3 4 1030 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1551 2047 517 1531 2050 498 1034 0 0 996 993 0 0
Stage 1 1046 1046 - 1002 1002 --------
Stage 2 505 1001 - 529 1048 --------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 --------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 --------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 77 55 503 80 55 518 668 - - 334 692 - -
Stage 1 244 304 - 260 318 --------
Stage 2 518 319 - 501 303 --------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 73 54 503 77 54 518 668 - - 469 469 - -
Mov Cap-2 Maneuver 73 54 - 77 54 --------
Stage 1 243 299 - 258 316 --------
Stage 2 503 317 - 482 298 --------
Approach EB WB NB SB
HCM Control Delay, s 33.9 30 0 0.1
HCM LOS D D
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)668 - - 73 503 159 469 - -
HCM Lane V/C Ratio 0.007 - - 0.119 0.022 0.096 0.016 - -
HCM Control Delay (s) 10.4 - - 60.9 12.3 30 12.8 - -
HCM Lane LOS B - - F B D B - -
HCM 95th %tile Q(veh) 0 - - 0.4 0.1 0.3 0 - -
Appendix - p. 17 of 52
Appendix - p. 17 of 52
HCM 6th AWSC 2019 Existing PM Peak Hour.syn
5: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 8.2
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 18 9 7 18 39 23 7 110 2 7 84 15
Future Vol, veh/h 18 9 7 18 39 23 7 110 2 7 84 15
Peak Hour Factor 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81
Heavy Vehicles, %222222222222
Mvmt Flow 22 11 9 22 48 28 9 136 2 9 104 19
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 8 8.1 8.4 8.2
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %6% 53% 23% 7%
Vol Thru, %92% 26% 49% 79%
Vol Right, % 2% 21% 29% 14%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 119 34 80 106
LT Vol 7 18 18 7
Through Vol 110 9 39 84
RT Vol 2 7 23 15
Lane Flow Rate 147 42 99 131
Geometry Grp 1111
Degree of Util (X) 0.18 0.054 0.123 0.158
Departure Headway (Hd)4.404 4.659 4.482 4.351
Convergence, Y/N Yes Yes Yes Yes
Cap 817 769 801 826
Service Time 2.423 2.683 2.503 2.369
HCM Lane V/C Ratio 0.18 0.055 0.124 0.159
HCM Control Delay 8.4 8 8.1 8.2
HCM Lane LOS AAAA
HCM 95th-tile Q 0.7 0.2 0.4 0.6
Appendix - p. 18 of 52
Appendix - p. 18 of 52
HCM 6th AWSC 2019 Existing PM Peak Hour.syn
7: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2019 Existing PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 8.8
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 21 53 38 7 56 19 92 77 12 9 41 59
Future Vol, veh/h 21 53 38 7 56 19 92 77 12 9 41 59
Peak Hour Factor 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88
Heavy Vehicles, % 2 22222222222
Mvmt Flow 24 60 43 8 64 22 105 88 14 10 47 67
Number of Lanes 0 10010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1 1 1 1
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1 1 1 1
Conflicting Approach RightNB SB WB EB
Conflicting Lanes Right 1 1 1 1
HCM Control Delay 8.6 8.4 9.4 8.2
HCM LOS A A A A
Lane NBLn1EBLn1WBLn1SBLn1
Vol Left, %51% 19% 9% 8%
Vol Thru, %43% 47% 68% 38%
Vol Right, %7% 34% 23% 54%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 181 112 82 109
LT Vol 92 21 7 9
Through Vol 77 53 56 41
RT Vol 12 38 19 59
Lane Flow Rate 206 127 93 124
Geometry Grp 1111
Degree of Util (X) 0.266 0.164 0.122 0.151
Departure Headway (Hd) 4.657 4.646 4.732 4.392
Convergence, Y/N Yes Yes Yes Yes
Cap 771 770 756 815
Service Time 2.691 2.685 2.774 2.43
HCM Lane V/C Ratio 0.267 0.165 0.123 0.152
HCM Control Delay 9.4 8.6 8.4 8.2
HCM Lane LOS AAAA
HCM 95th-tile Q 1.1 0.6 0.4 0.5
Appendix - p. 19 of 52
Appendix - p. 19 of 52
Appendix - p. 20 of 52
Appendix - p. 20 of 52
Timings 2021 Background AM Peak Hour.syn
1: Carroll Ave & Federal Way 11/21/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background AM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBL SBT
Lane Configurations
Traffic Volume (vph)1 0 19 1 20 7 7 791 52 861
Future Volume (vph)1 0 19 1 20 7 7 791 52 861
Turn Type Perm NA Perm NA Perm custom pm+pt NA pm+pt NA
Protected Phases 4 8 5216
Permitted Phases 4 8 8 5 2 6
Detector Phase 4488855216
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None Max
Act Effct Green (s)6.1 6.2 6.2 28.8 29.6 29.9 31.7
Actuated g/C Ratio 0.16 0.16 0.16 0.73 0.76 0.76 0.81
v/c Ratio 0.01 0.07 0.06 0.02 0.32 0.09 0.32
Control Delay 0.0 16.1 0.3 3.0 6.5 2.8 4.7
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 0.0 16.1 0.3 3.0 6.5 2.8 4.7
LOS A BA AAAA
Approach Delay 8.2 6.4 4.6
Approach LOS A A A
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 39.2
Natural Cycle: 55
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.32
Intersection Signal Delay: 5.5 Intersection LOS: A
Intersection Capacity Utilization 43.5%ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 21 of 52
Appendix - p. 21 of 52
HCM 6th TWSC 2021 Background AM Peak Hour.syn
3: Carroll Ave & Federal Way 11/21/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.3
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 1 029032826711294810
Future Vol, veh/h 1 029032826711294810
Conflicting Peds, #/hr 0 000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free
RT Channelized - - None - - None - - Yield - - - None
Storage Length 0 -----100---100--
Veh in Median Storage, # - 0 - - 0 - - 0 - - - 0 -
Grade, % - 0 - - 0 - - 0 - - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 2 222222222222
Mvmt Flow 1 029032869711399811
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1471 1905 505 1404 1914 438 1009 0 0 877 869 0 0
Stage 1 1032 1032 - 877 877 --------
Stage 2 439 873 - 527 1037 --------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 --------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 --------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 89 68 512 99 67 567 683 - - 398 771 - -
Stage 1 249 308 - 310 364 --------
Stage 2 567 366 - 502 307 --------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 87 67 512 97 66 567 683 - - 719 719 - -
Mov Cap-2 Maneuver 87 67 - 97 66 --------
Stage 1 248 302 - 309 363 --------
Stage 2 562 365 - 490 301 --------
Approach EB WB NB SB
HCM Control Delay, s 23.7 37.9 0 0.1
HCM LOS C E
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)683 - - 87 512 122 719 - -
HCM Lane V/C Ratio 0.003 - - 0.012 0.004 0.104 0.019 - -
HCM Control Delay (s) 10.3 - - 46.9 12.1 37.9 10.1 - -
HCM Lane LOS B - -EBEB - -
HCM 95th %tile Q(veh) 0 - - 0 0 0.3 0.1 - -
Appendix - p. 22 of 52
Appendix - p. 22 of 52
HCM 6th AWSC 2021 Background AM Peak Hour.syn
5: State St & Federal Way 11/21/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.6
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 15 9 8 7 16 12 2 35 1 1 85 1
Future Vol, veh/h 15 9 8 7 16 12 2 35 1 1 85 1
Peak Hour Factor 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
Heavy Vehicles, %222222222222
Mvmt Flow 19 12 10 9 21 16 3 45 1 1 110 1
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 7.5 7.4 7.5 7.8
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %5% 47% 20% 1%
Vol Thru, %92% 28% 46% 98%
Vol Right, % 3% 25% 34% 1%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 38 32 35 87
LT Vol 2 15 7 1
Through Vol 35 9 16 85
RT Vol 1 8 12 1
Lane Flow Rate 49 42 45 113
Geometry Grp 1111
Degree of Util (X) 0.057 0.048 0.052 0.129
Departure Headway (Hd)4.165 4.193 4.08 4.118
Convergence, Y/N Yes Yes Yes Yes
Cap 851 841 864 864
Service Time 2.236 2.285 2.171 2.174
HCM Lane V/C Ratio 0.058 0.05 0.052 0.131
HCM Control Delay 7.5 7.5 7.4 7.8
HCM Lane LOS AAAA
HCM 95th-tile Q 0.2 0.2 0.2 0.4
Appendix - p. 23 of 52
Appendix - p. 23 of 52
HCM 6th AWSC 2021 Background AM Peak Hour.syn
7: State St & Federal Way 11/21/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.6
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 8 18 38 1 14 8 9 22 4 9 81 10
Future Vol, veh/h 8 18 38 1 14 8 9 22 4 9 81 10
Peak Hour Factor 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Heavy Vehicles, % 2 22222222222
Mvmt Flow 9 21 44 1 16 9 10 26 5 10 94 12
Number of Lanes 0 10010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1 1 1 1
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1 1 1 1
Conflicting Approach RightNB SB WB EB
Conflicting Lanes Right 1 1 1 1
HCM Control Delay 7.3 7.3 7.5 7.8
HCM LOS A A A A
Lane NBLn1EBLn1WBLn1SBLn1
Vol Left, %26% 12% 4% 9%
Vol Thru, %63% 28% 61% 81%
Vol Right, %11% 59% 35% 10%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 35 64 23 100
LT Vol 9819
Through Vol 22 18 14 81
RT Vol 4 38 8 10
Lane Flow Rate 41 74 27 116
Geometry Grp 1111
Degree of Util (X) 0.047 0.08 0.03 0.132
Departure Headway (Hd) 4.182 3.893 4.063 4.099
Convergence, Y/N Yes Yes Yes Yes
Cap 848 906 867 870
Service Time 2.247 1.976 2.153 2.147
HCM Lane V/C Ratio 0.048 0.082 0.031 0.133
HCM Control Delay 7.5 7.3 7.3 7.8
HCM Lane LOS AAAA
HCM 95th-tile Q 0.1 0.3 0.1 0.5
Appendix - p. 24 of 52
Appendix - p. 24 of 52
Appendix - p. 25 of 52
Appendix - p. 25 of 52
Timings 2021 Background PM Peak Hour.syn
1: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background PM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBU SBL SBT
Lane Configurations
Traffic Volume (vph)21 1 166 1 93 22 13 932 8 82 1040
Future Volume (vph)21 1 166 1 93 22 13 932 8 82 1040
Turn Type Perm NA Perm NA Perm custom pm+pt NA custom pm+pt NA
Protected Phases 4 8 5 2 1 6
Permitted Phases 4 8 8 5 2 1 6
Detector Phase 44888552116
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None None Max
Act Effct Green (s)11.2 11.5 11.5 25.1 22.9 27.2 25.5
Actuated g/C Ratio 0.24 0.25 0.25 0.54 0.50 0.59 0.55
v/c Ratio 0.14 0.58 0.21 0.10 0.64 0.25 0.59
Control Delay 10.2 23.9 4.3 6.5 19.0 7.3 15.7
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 10.2 23.9 4.3 6.5 19.0 7.3 15.7
LOS BCAABAB
Approach Delay 10.2 16.9 18.6 15.0
Approach LOS B B B B
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 46.1
Natural Cycle: 60
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.64
Intersection Signal Delay: 16.6 Intersection LOS: B
Intersection Capacity Utilization 60.2%ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 26 of 52
Appendix - p. 26 of 52
HCM 6th TWSC 2021 Background PM Peak Hour.syn
3: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.9
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 9 0 12 4 1 10 4 1105 2 3 4 1147 4
Future Vol, veh/h 9 0 12 4 1 10 4 1105 2 3 4 1147 4
Conflicting Peds, #/hr 0 000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free
RT Channelized - - None - - None - - Yield - - - None
Storage Length 0 -----100---100--
Veh in Median Storage, # - 0 - - 0 - - 0 - - - 0 -
Grade, % - 0 - - 0 - - 0 - - - 0 -
Peak Hour Factor 92 92 92 92 92 92 92 92 92 92 92 92 92
Heavy Vehicles, % 2 222222222222
Mvmt Flow 10 0 13 4 1 11 4 1201 2 3 4 1247 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1872 2472 626 1848 2475 602 1251 0 0 1203 1201 0 0
Stage 1 1263 1263 - 1210 1210 --------
Stage 2 609 1209 - 638 1265 --------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 --------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 --------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 44 30 427 46 29 443 552 - - 246 577 - -
Stage 1 180 239 - 194 254 --------
Stage 2 449 254 - 431 239 --------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 41 29 427 44 28 443 552 - - 360 360 - -
Mov Cap-2 Maneuver 41 29 - 44 28 --------
Stage 1 179 234 - 193 252 --------
Stage 2 433 252 - 409 234 --------
Approach EB WB NB SB
HCM Control Delay, s 58.6 47.4 0 0.1
HCM LOS F E
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)552 - - 41 427 101 360 - -
HCM Lane V/C Ratio 0.008 - - 0.239 0.031 0.161 0.021 - -
HCM Control Delay (s) 11.6 - - 118.4 13.7 47.4 15.2 - -
HCM Lane LOS B - - F B E C - -
HCM 95th %tile Q(veh) 0 - - 0.8 0.1 0.5 0.1 - -
Appendix - p. 27 of 52
Appendix - p. 27 of 52
HCM 6th AWSC 2021 Background PM Peak Hour.syn
5: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 8.6
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 21 10 8 21 47 27 8 133 2 8 101 18
Future Vol, veh/h 21 10 8 21 47 27 8 133 2 8 101 18
Peak Hour Factor 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81
Heavy Vehicles, %222222222222
Mvmt Flow 26 12 10 26 58 33 10 164 2 10 125 22
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 8.2 8.5 8.8 8.6
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %6% 54% 22% 6%
Vol Thru, %93% 26% 49% 80%
Vol Right, % 1% 21% 28% 14%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 143 39 95 127
LT Vol 8 21 21 8
Through Vol 133 10 47 101
RT Vol 2 8 27 18
Lane Flow Rate 177 48 117 157
Geometry Grp 1111
Degree of Util (X) 0.221 0.065 0.151 0.194
Departure Headway (Hd)4.507 4.826 4.627 4.455
Convergence, Y/N Yes Yes Yes Yes
Cap 796 741 774 804
Service Time 2.535 2.862 2.659 2.485
HCM Lane V/C Ratio 0.222 0.065 0.151 0.195
HCM Control Delay 8.8 8.2 8.5 8.6
HCM Lane LOS AAAA
HCM 95th-tile Q 0.8 0.2 0.5 0.7
Appendix - p. 28 of 52
Appendix - p. 28 of 52
HCM 6th AWSC 2021 Background PM Peak Hour.syn
7: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Background PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 9.5
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 25 64 45 8 67 22 111 93 14 10 49 71
Future Vol, veh/h 25 64 45 8 67 22 111 93 14 10 49 71
Peak Hour Factor 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88
Heavy Vehicles, % 2 22222222222
Mvmt Flow 28 73 51 9 76 25 126 106 16 11 56 81
Number of Lanes 0 10010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1 1 1 1
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1 1 1 1
Conflicting Approach RightNB SB WB EB
Conflicting Lanes Right 1 1 1 1
HCM Control Delay 9.2 8.9 10.3 8.7
HCM LOS A A B A
Lane NBLn1EBLn1WBLn1SBLn1
Vol Left, %51% 19% 8% 8%
Vol Thru, %43% 48% 69% 38%
Vol Right, %6% 34% 23% 55%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 218 134 97 130
LT Vol 111 25 8 10
Through Vol 93 64 67 49
RT Vol 14 45 22 71
Lane Flow Rate 248 152 110 148
Geometry Grp 1111
Degree of Util (X) 0.331 0.205 0.151 0.187
Departure Headway (Hd) 4.808 4.844 4.945 4.568
Convergence, Y/N Yes Yes Yes Yes
Cap 743 735 720 780
Service Time 2.865 2.91 3.015 2.632
HCM Lane V/C Ratio 0.334 0.207 0.153 0.19
HCM Control Delay 10.3 9.2 8.9 8.7
HCM Lane LOS BAAA
HCM 95th-tile Q 1.5 0.8 0.5 0.7
Appendix - p. 29 of 52
Appendix - p. 29 of 52
Appendix - p. 30 of 52
Appendix - p. 30 of 52
Timings 2021 Total AM Peak Hour.syn
1: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBU SBL SBT
Lane Configurations
Traffic Volume (vph)1 0 42 1 36 7 7 795 1 54 864
Future Volume (vph)1 0 42 1 36 7 7 795 1 54 864
Turn Type Perm NA Perm NA Perm custom pm+pt NA custom pm+pt NA
Protected Phases 4 8 5 2 1 6
Permitted Phases 4 8 8 5 2 1 6
Detector Phase 44888552116
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None None Max
Act Effct Green (s)6.8 6.8 6.8 28.0 27.9 29.3 30.1
Actuated g/C Ratio 0.17 0.17 0.17 0.68 0.68 0.71 0.73
v/c Ratio 0.01 0.16 0.11 0.03 0.36 0.10 0.35
Control Delay 0.0 17.0 0.6 3.7 7.8 3.7 5.9
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 0.0 17.0 0.6 3.7 7.8 3.7 5.9
LOS ABAAAAA
Approach Delay 9.5 7.8 5.8
Approach LOS A A A
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 41.2
Natural Cycle: 55
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.36
Intersection Signal Delay: 6.8 Intersection LOS: A
Intersection Capacity Utilization 50.7%ICU Level of Service A
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 31 of 52
Appendix - p. 31 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
2: Carroll Ave & W Dwy
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0
Movement WBL WBR NBT NBR SBL SBT
Lane Configurations
Traffic Vol, veh/h 0 5 832 2 0 923
Future Vol, veh/h 0 5 832 2 0 923
Conflicting Peds, #/hr 0 00000
Sign Control Stop Stop Free Free Free Free
RT Channelized - None - None - None
Storage Length - 0 ----
Veh in Median Storage, # 0 - 0 - - 0
Grade, % 0 - 0 - - 0
Peak Hour Factor 96 96 96 96 96 96
Heavy Vehicles, % 2 22222
Mvmt Flow 0 5 867 2 0 961
Major/Minor Minor1 Major1 Major2
Conflicting Flow All - 435 0 0 - -
Stage 1 ------
Stage 2 ------
Critical Hdwy - 6.94 ----
Critical Hdwy Stg 1 ------
Critical Hdwy Stg 2 ------
Follow-up Hdwy - 3.32 ----
Pot Cap-1 Maneuver 0 569 - - 0 -
Stage 1 0 - - - 0 -
Stage 2 0 - - - 0 -
Platoon blocked, %- --
Mov Cap-1 Maneuver - 569 ----
Mov Cap-2 Maneuver ------
Stage 1 ------
Stage 2 ------
Approach WB NB SB
HCM Control Delay, s 11.4 0 0
HCM LOS B
Minor Lane/Major Mvmt NBT NBRWBLn1 SBT
Capacity (veh/h)- - 569 -
HCM Lane V/C Ratio - - 0.009 -
HCM Control Delay (s) - - 11.4 -
HCM Lane LOS - - B -
HCM 95th %tile Q(veh) - - 0 -
Appendix - p. 32 of 52
Appendix - p. 32 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
3: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.6
Movement EBL EBT EBR WBL WBT WBR NBU NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 1 029021328441011595110
Future Vol, veh/h 1 029021328441011595110
Conflicting Peds, #/hr 0 0000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free Free
RT Channelized - - None - - None - - - Yield - - - None
Storage Length 0 ------100---100--
Veh in Median Storage, # - 0 - - 0 - - - 0 - - - 0 -
Grade, % - 0 - - 0 - - - 0 - - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 2 2222222222222
Mvmt Flow 1 02902232888111161001 11
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1495 1939 506 1439 1950 450 1012 1012 0 0 899 888 0 0
Stage 1 1041 1041 - 904 904 ---------
Stage 2 454 898 - 535 1046 ---------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 6.44 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 ---------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 ---------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.52 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 85 65 512 94 64 556 326 681 - - 385 758 - -
Stage 1 246 305 - 298 354 ---------
Stage 2 555 356 - 497 304 ---------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 79 63 512 91 62 556 411 411 - - 711 711 - -
Mov Cap-2 Maneuver 79 63 - 91 62 ---------
Stage 1 243 298 - 294 350 ---------
Stage 2 526 352 - 483 297 ---------
Approach EB WB NB SB
HCM Control Delay, s 25.1 24.1 0.1 0.2
HCM LOS D C
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)411 - - 79 512 220 711 - -
HCM Lane V/C Ratio 0.013 - - 0.013 0.004 0.144 0.024 - -
HCM Control Delay (s) 13.9 - - 51.2 12.1 24.1 10.2 - -
HCM Lane LOS B - - F B C B - -
HCM 95th %tile Q(veh) 0 - - 0 0 0.5 0.1 - -
Appendix - p. 33 of 52
Appendix - p. 33 of 52
HCM 6th TWSC 2021 Total AM Peak Hour - Add Turn Lane.syn
3: Carroll Ave & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour - Add Turn Lane.synSynchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.6
Movement EBL EBT EBR WBL WBT WBR NBU NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 1 029021328441011595110
Future Vol, veh/h 1 029021328441011595110
Conflicting Peds, #/hr 0 0000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free Free
RT Channelized - - None - - None - - - Yield - - - None
Storage Length 0 ----50-100---100--
Veh in Median Storage, # - 0 - - 0 - - - 0 - - - 0 -
Grade, % - 0 - - 0 - - - 0 - - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 2 2222222222222
Mvmt Flow 1 02902232888111161001 11
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1495 1939 506 1439 1950 450 1012 1012 0 0 899 888 0 0
Stage 1 1041 1041 - 904 904 ---------
Stage 2 454 898 - 535 1046 ---------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 6.44 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 ---------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 ---------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.52 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 85 65 512 94 64 556 326 681 - - 385 758 - -
Stage 1 246 305 - 298 354 ---------
Stage 2 555 356 - 497 304 ---------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 79 63 512 91 62 556 411 411 - - 711 711 - -
Mov Cap-2 Maneuver 79 63 - 91 62 ---------
Stage 1 243 298 - 294 350 ---------
Stage 2 526 352 - 483 297 ---------
Approach EB WB NB SB
HCM Control Delay, s 25.1 22.9 0.1 0.2
HCM LOS D C
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1WBLn2 SBL SBT SBR
Capacity (veh/h)411 - - 79 512 91 556 711 - -
HCM Lane V/C Ratio 0.013 - - 0.013 0.004 0.104 0.04 0.024 - -
HCM Control Delay (s) 13.9 - - 51.2 12.1 49.1 11.7 10.2 - -
HCM Lane LOS B - - F BEBB - -
HCM 95th %tile Q(veh) 0 - - 0 0 0.3 0.1 0.1 - -
Appendix - p. 34 of 52
Appendix - p. 34 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
4: NW Dwy & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 2.8
Movement EBT EBR WBL WBT NBL NBR
Lane Configurations
Traffic Vol, veh/h 21 4 4 22 9 10
Future Vol, veh/h 21 4 4 22 9 10
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 77 77 77 77 77 77
Heavy Vehicles, % 2 22222
Mvmt Flow 27 5 5 29 12 13
Major/Minor Major1 Major2 Minor1
Conflicting Flow All 0 0 32 0 69 30
Stage 1 - - - - 30 -
Stage 2 - - - - 39 -
Critical Hdwy - - 4.12 - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy - - 2.218 - 3.518 3.318
Pot Cap-1 Maneuver - - 1580 - 936 1044
Stage 1 - - - - 993 -
Stage 2 - - - - 983 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver - - 1580 - 933 1044
Mov Cap-2 Maneuver - - - - 933 -
Stage 1 - - - - 990 -
Stage 2 - - - - 983 -
Approach EB WB NB
HCM Control Delay, s 0 1.1 8.7
HCM LOS A
Minor Lane/Major Mvmt NBLn1 EBT EBR WBL WBT
Capacity (veh/h)988 - - 1580 -
HCM Lane V/C Ratio 0.025 - - 0.003 -
HCM Control Delay (s) 8.7 - - 7.3 0
HCM Lane LOS A - - A A
HCM 95th %tile Q(veh) 0.1 - - 0 -
Appendix - p. 35 of 52
Appendix - p. 35 of 52
HCM 6th AWSC 2021 Total AM Peak Hour.syn
5: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.8
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 28 9 16 7 16 12 2 47 1 1 93 9
Future Vol, veh/h 28 9 16 7 16 12 2 47 1 1 93 9
Peak Hour Factor 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77 0.77
Heavy Vehicles, %222222222222
Mvmt Flow 36 12 21 9 21 16 3 61 1 1 121 12
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 7.7 7.5 7.7 8
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %4% 53% 20% 1%
Vol Thru, %94% 17% 46% 90%
Vol Right, % 2% 30% 34% 9%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 50 53 35 103
LT Vol 2 28 7 1
Through Vol 47 9 16 93
RT Vol 1 16 12 9
Lane Flow Rate 65 69 45 134
Geometry Grp 1111
Degree of Util (X) 0.078 0.083 0.054 0.153
Departure Headway (Hd)4.333 4.349 4.285 4.131
Convergence, Y/N Yes Yes Yes Yes
Cap 832 828 840 855
Service Time 2.333 2.354 2.291 2.219
HCM Lane V/C Ratio 0.078 0.083 0.054 0.157
HCM Control Delay 7.7 7.7 7.5 8
HCM Lane LOS AAAA
HCM 95th-tile Q 0.3 0.3 0.2 0.5
Appendix - p. 36 of 52
Appendix - p. 36 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
6: State St & E Dwy
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.2
Movement EBL EBR NBL NBT SBT SBR
Lane Configurations
Traffic Vol, veh/h 4 0 0 47 115 2
Future Vol, veh/h 4 0 0 47 115 2
Conflicting Peds, #/hr 0 00000
Sign Control Stop Stop Free Free Free Free
RT Channelized - None - None - None
Storage Length 0 -----
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 81 81 81 81 81 81
Heavy Vehicles, % 2 22222
Mvmt Flow 5 0 0 58 142 2
Major/Minor Minor2 Major1 Major2
Conflicting Flow All 201 143 144 0 - 0
Stage 1 143 -----
Stage 2 58 -----
Critical Hdwy 6.42 6.22 4.12 - - -
Critical Hdwy Stg 1 5.42 -----
Critical Hdwy Stg 2 5.42 -----
Follow-up Hdwy 3.518 3.318 2.218 - - -
Pot Cap-1 Maneuver 788 905 1438 - - -
Stage 1 884 -----
Stage 2 965 -----
Platoon blocked, % - - -
Mov Cap-1 Maneuver 788 905 1438 - - -
Mov Cap-2 Maneuver 788 -----
Stage 1 884 -----
Stage 2 965 -----
Approach EB NB SB
HCM Control Delay, s 9.6 0 0
HCM LOS A
Minor Lane/Major Mvmt NBL NBTEBLn1 SBT SBR
Capacity (veh/h)1438 - 788 - -
HCM Lane V/C Ratio - - 0.006 - -
HCM Control Delay (s) 0 - 9.6 - -
HCM Lane LOS A - A - -
HCM 95th %tile Q(veh) 0 - 0 - -
Appendix - p. 37 of 52
Appendix - p. 37 of 52
HCM 6th AWSC 2021 Total AM Peak Hour.syn
7: State St & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 7.6
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 16 18 38 1 14 8 9 22 4 9 81 24
Future Vol, veh/h 16 18 38 1 14 8 9 22 4 9 81 24
Peak Hour Factor 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
Heavy Vehicles, %222222222222
Mvmt Flow 19 21 44 1 16 9 10 26 5 10 94 28
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 7.5 7.3 7.5 7.8
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %26% 22% 4% 8%
Vol Thru, %63% 25% 61% 71%
Vol Right, % 11% 53% 35% 21%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 35 72 23 114
LT Vol 9 16 1 9
Through Vol 22 18 14 81
RT Vol 4 38 8 24
Lane Flow Rate 41 84 27 133
Geometry Grp 1111
Degree of Util (X) 0.048 0.093 0.031 0.149
Departure Headway (Hd)4.211 3.982 4.201 4.046
Convergence, Y/N Yes Yes Yes Yes
Cap 840 886 857 879
Service Time 2.29 2.071 2.201 2.107
HCM Lane V/C Ratio 0.049 0.095 0.032 0.151
HCM Control Delay 7.5 7.5 7.3 7.8
HCM Lane LOS AAAA
HCM 95th-tile Q 0.2 0.3 0.1 0.5
Appendix - p. 38 of 52
Appendix - p. 38 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
8: Federal Way & SW Dwy
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 1.1
Movement EBL EBT WBT WBR SBL SBR
Lane Configurations
Traffic Vol, veh/h 4 88 64 3 4 16
Future Vol, veh/h 4 88 64 3 4 16
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 86 86 86 86 86 86
Heavy Vehicles, % 2 22222
Mvmt Flow 5 102 74 3 5 19
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 77 0 - 0 188 76
Stage 1 - - - - 76 -
Stage 2 - - - - 112 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1522 - - - 801 985
Stage 1 - - - - 947 -
Stage 2 - - - - 913 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1522 - - - 799 985
Mov Cap-2 Maneuver - - - - 799 -
Stage 1 - - - - 944 -
Stage 2 - - - - 913 -
Approach EB WB SB
HCM Control Delay, s 0.3 0 8.9
HCM LOS A
Minor Lane/Major Mvmt EBL EBT WBT WBRSBLn1
Capacity (veh/h)1522 - - - 941
HCM Lane V/C Ratio 0.003 - - - 0.025
HCM Control Delay (s) 7.4 0 - - 8.9
HCM Lane LOS A A - - A
HCM 95th %tile Q(veh) 0 - - - 0.1
Appendix - p. 39 of 52
Appendix - p. 39 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
9: NE Dwy & Federal Way
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 2.9
Movement EBT EBR WBL WBT NBL NBR
Lane Configurations
Traffic Vol, veh/h 29 2 4 17 9 11
Future Vol, veh/h 29 2 4 17 9 11
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 77 77 77 77 77 77
Heavy Vehicles, % 2 22222
Mvmt Flow 38 3 5 22 12 14
Major/Minor Major1 Major2 Minor1
Conflicting Flow All 0 0 41 0 72 40
Stage 1 - - - - 40 -
Stage 2 - - - - 32 -
Critical Hdwy - - 4.12 - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy - - 2.218 - 3.518 3.318
Pot Cap-1 Maneuver - - 1568 - 932 1031
Stage 1 - - - - 982 -
Stage 2 - - - - 991 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver - - 1568 - 929 1031
Mov Cap-2 Maneuver - - - - 929 -
Stage 1 - - - - 979 -
Stage 2 - - - - 991 -
Approach EB WB NB
HCM Control Delay, s 0 1.4 8.8
HCM LOS A
Minor Lane/Major Mvmt NBLn1 EBT EBR WBL WBT
Capacity (veh/h)982 - - 1568 -
HCM Lane V/C Ratio 0.026 - - 0.003 -
HCM Control Delay (s) 8.8 - - 7.3 0
HCM Lane LOS A - - A A
HCM 95th %tile Q(veh) 0.1 - - 0 -
Appendix - p. 40 of 52
Appendix - p. 40 of 52
HCM 6th TWSC 2021 Total AM Peak Hour.syn
10: Federal Way & SE Dwy
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total AM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 1.1
Movement EBL EBT WBT WBR SBL SBR
Lane Configurations
Traffic Vol, veh/h 3 89 52 3 4 15
Future Vol, veh/h 3 89 52 3 4 15
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 86 86 86 86 86 86
Heavy Vehicles, % 2 22222
Mvmt Flow 3 103 60 3 5 17
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 63 0 - 0 171 62
Stage 1 - - - - 62 -
Stage 2 - - - - 109 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1540 - - - 819 1003
Stage 1 - - - - 961 -
Stage 2 - - - - 916 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1540 - - - 817 1003
Mov Cap-2 Maneuver - - - - 817 -
Stage 1 - - - - 959 -
Stage 2 - - - - 916 -
Approach EB WB SB
HCM Control Delay, s 0.2 0 8.9
HCM LOS A
Minor Lane/Major Mvmt EBL EBT WBT WBRSBLn1
Capacity (veh/h)1540 - - - 957
HCM Lane V/C Ratio 0.002 - - - 0.023
HCM Control Delay (s) 7.3 0 - - 8.9
HCM Lane LOS A A - - A
HCM 95th %tile Q(veh) 0 - - - 0.1
Appendix - p. 41 of 52
Appendix - p. 41 of 52
Timings 2021 Total PM Peak Hour.syn
1: Carroll Ave & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Lane Group EBL EBT WBL WBT WBR NBU NBL NBT SBU SBL SBT
Lane Configurations
Traffic Volume (vph)21 1 182 1 103 22 13 944 10 90 1042
Future Volume (vph)21 1 182 1 103 22 13 944 10 90 1042
Turn Type Perm NA Perm NA Perm custom pm+pt NA custom pm+pt NA
Protected Phases 4 8 5 2 1 6
Permitted Phases 4 8 8 5 2 1 6
Detector Phase 44888552116
Switch Phase
Minimum Initial (s) 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0 5.0
Minimum Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 20.0 14.0 14.0 20.0
Total Split (s)20.0 20.0 20.0 20.0 20.0 14.0 14.0 21.0 14.0 14.0 21.0
Total Split (%)36.4% 36.4% 36.4% 36.4% 36.4% 25.5% 25.5% 38.2% 25.5% 25.5% 38.2%
Yellow Time (s)3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
All-Red Time (s)1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Lost Time Adjust (s)0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s)4.5 4.5 4.5 4.5 4.5 4.5 4.5
Lead/Lag Lead Lead Lag Lead Lead Lag
Lead-Lag Optimize?Yes Yes Yes Yes Yes Yes
Recall Mode None None None None None None None Max None None Max
Act Effct Green (s)11.6 12.0 12.0 25.5 22.1 28.9 27.1
Actuated g/C Ratio 0.24 0.25 0.25 0.53 0.46 0.60 0.56
v/c Ratio 0.14 0.64 0.24 0.10 0.71 0.28 0.58
Control Delay 10.1 26.5 5.0 6.6 21.9 7.8 15.6
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 10.1 26.5 5.0 6.6 21.9 7.8 15.6
LOS B C A A C A B
Approach Delay 10.1 18.8 21.4 14.9
Approach LOS B B C B
Intersection Summary
Cycle Length: 55
Actuated Cycle Length: 48
Natural Cycle: 60
Control Type: Actuated-Uncoordinated
Maximum v/c Ratio: 0.71
Intersection Signal Delay: 18.0 Intersection LOS: B
Intersection Capacity Utilization 62.5%ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Carroll Ave & Federal Way
Appendix - p. 42 of 52
Appendix - p. 42 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
2: Carroll Ave & W Dwy 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0
Movement WBL WBR NBT NBR SBL SBT
Lane Configurations
Traffic Vol, veh/h 0 3 1075 5 0 1144
Future Vol, veh/h 0 3 1075 5 0 1144
Conflicting Peds, #/hr 0 00000
Sign Control Stop Stop Free Free Free Free
RT Channelized - None - None - None
Storage Length - 0 ----
Veh in Median Storage, # 0 - 0 - - 0
Grade, % 0 - 0 - - 0
Peak Hour Factor 91 91 91 91 91 91
Heavy Vehicles, % 2 22222
Mvmt Flow 0 3 1181 5 0 1257
Major/Minor Minor1 Major1 Major2
Conflicting Flow All - 593 0 0 - -
Stage 1 ------
Stage 2 ------
Critical Hdwy - 6.94 ----
Critical Hdwy Stg 1 ------
Critical Hdwy Stg 2 ------
Follow-up Hdwy - 3.32 ----
Pot Cap-1 Maneuver 0 449 - - 0 -
Stage 1 0 - - - 0 -
Stage 2 0 - - - 0 -
Platoon blocked, %- --
Mov Cap-1 Maneuver - 449 ----
Mov Cap-2 Maneuver ------
Stage 1 ------
Stage 2 ------
Approach WB NB SB
HCM Control Delay, s 13.1 0 0
HCM LOS B
Minor Lane/Major Mvmt NBT NBRWBLn1 SBT
Capacity (veh/h)- - 449 -
HCM Lane V/C Ratio - - 0.007 -
HCM Control Delay (s) - - 13.1 -
HCM Lane LOS - - B -
HCM 95th %tile Q(veh) - - 0 -
Appendix - p. 43 of 52
Appendix - p. 43 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
3: Carroll Ave & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 1.2
Movement EBL EBT EBR WBL WBT WBR NBU NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 9 0 12 4 1 22 2 4 1116 11 3 13 1157 4
Future Vol, veh/h 9 0 12 4 1 22 2 4 1116 11 3 13 1157 4
Conflicting Peds, #/hr 0 0000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free Free
RT Channelized - - None - - None - - - Yield - - - None
Storage Length 0 ------100---100--
Veh in Median Storage, # - 0 - - 0 - - - 0 - - - 0 -
Grade, % - 0 - - 0 - - - 0 - - - 0 -
Peak Hour Factor 92 92 92 92 92 92 92 92 92 92 92 92 92 92
Heavy Vehicles, % 2 2222222222222
Mvmt Flow 10 0 13 4 1 24 2 4 1213 12 3 14 1258 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1913 2519 631 1894 2527 613 1262 1262 0 0 1225 1213 0 0
Stage 1 1294 1294 - 1231 1231 ---------
Stage 2 619 1225 - 663 1296 ---------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 6.44 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 ---------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 ---------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.52 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 41 28 424 43 27 435 225 547 - - 238 571 - -
Stage 1 172 231 - 188 248 ---------
Stage 2 443 249 - 417 231 ---------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 36 26 424 40 25 435 365 365 - - 444 444 - -
Mov Cap-2 Maneuver 36 26 - 40 25 ---------
Stage 1 169 222 - 184 243 ---------
Stage 2 409 244 - 389 222 ---------
Approach EB WB NB SB
HCM Control Delay, s 67.4 36.8 0.1 0.2
HCM LOS F E
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1 SBL SBT SBR
Capacity (veh/h)365 - - 36 424 142 444 - -
HCM Lane V/C Ratio 0.018 - - 0.272 0.031 0.207 0.039 - -
HCM Control Delay (s) 15 - - 138.8 13.8 36.8 13.4 - -
HCM Lane LOS C - - F B E B - -
HCM 95th %tile Q(veh) 0.1 - - 0.9 0.1 0.7 0.1 - -
Appendix - p. 44 of 52
Appendix - p. 44 of 52
HCM 6th TWSC 2021 Total PM Peak Hour - Add Turn Lane.syn
3: Carroll Ave & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour - Add Turn Lane.synSynchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 1.1
Movement EBL EBT EBR WBL WBT WBR NBU NBL NBT NBR SBU SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 9 0 12 4 1 22 2 4 1116 11 3 13 1157 4
Future Vol, veh/h 9 0 12 4 1 22 2 4 1116 11 3 13 1157 4
Conflicting Peds, #/hr 0 0000000000000
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free Free Free
RT Channelized - - None - - None - - - Yield - - - None
Storage Length 0 ----50-100---100--
Veh in Median Storage, # - 0 - - 0 - - - 0 - - - 0 -
Grade, % - 0 - - 0 - - - 0 - - - 0 -
Peak Hour Factor 92 92 92 92 92 92 92 92 92 92 92 92 92 92
Heavy Vehicles, % 2 2222222222222
Mvmt Flow 10 0 13 4 1 24 2 4 1213 12 3 14 1258 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 1913 2519 631 1894 2527 613 1262 1262 0 0 1225 1213 0 0
Stage 1 1294 1294 - 1231 1231 ---------
Stage 2 619 1225 - 663 1296 ---------
Critical Hdwy 7.54 6.54 6.94 7.54 6.54 6.94 6.44 4.14 - - 6.44 4.14 - -
Critical Hdwy Stg 1 6.54 5.54 - 6.54 5.54 ---------
Critical Hdwy Stg 2 6.54 5.54 - 6.54 5.54 ---------
Follow-up Hdwy 3.52 4.02 3.32 3.52 4.02 3.32 2.52 2.22 - - 2.52 2.22 - -
Pot Cap-1 Maneuver 41 28 424 43 27 435 225 547 - - 238 571 - -
Stage 1 172 231 - 188 248 ---------
Stage 2 443 249 - 417 231 ---------
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 36 26 424 40 25 435 365 365 - - 444 444 - -
Mov Cap-2 Maneuver 36 26 - 40 25 ---------
Stage 1 169 222 - 184 243 ---------
Stage 2 409 244 - 389 222 ---------
Approach EB WB NB SB
HCM Control Delay, s 67.4 33.8 0.1 0.2
HCM LOS F D
Minor Lane/Major Mvmt NBL NBT NBREBLn1EBLn2WBLn1WBLn2 SBL SBT SBR
Capacity (veh/h)365 - - 36 424 36 435 444 - -
HCM Lane V/C Ratio 0.018 - - 0.272 0.031 0.151 0.055 0.039 - -
HCM Control Delay (s) 15 - - 138.8 13.8 122 13.8 13.4 - -
HCM Lane LOS C - - F B F B B - -
HCM 95th %tile Q(veh) 0.1 - - 0.9 0.1 0.5 0.2 0.1 - -
Appendix - p. 45 of 52
Appendix - p. 45 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
4: NW Dwy & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 2.7
Movement EBT EBR WBL WBT NBL NBR
Lane Configurations
Traffic Vol, veh/h 15 10 11 22 6 7
Future Vol, veh/h 15 10 11 22 6 7
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 81 81 81 81 81 81
Heavy Vehicles, % 2 22222
Mvmt Flow 19 12 14 27 7 9
Major/Minor Major1 Major2 Minor1
Conflicting Flow All 0 0 31 0 80 25
Stage 1 - - - - 25 -
Stage 2 - - - - 55 -
Critical Hdwy - - 4.12 - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy - - 2.218 - 3.518 3.318
Pot Cap-1 Maneuver - - 1582 - 922 1051
Stage 1 - - - - 998 -
Stage 2 - - - - 968 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver - - 1582 - 914 1051
Mov Cap-2 Maneuver - - - - 914 -
Stage 1 - - - - 989 -
Stage 2 - - - - 968 -
Approach EB WB NB
HCM Control Delay, s 0 2.4 8.7
HCM LOS A
Minor Lane/Major Mvmt NBLn1 EBT EBR WBL WBT
Capacity (veh/h)983 - - 1582 -
HCM Lane V/C Ratio 0.016 - - 0.009 -
HCM Control Delay (s) 8.7 - - 7.3 0
HCM Lane LOS A - - A A
HCM 95th %tile Q(veh) 0.1 - - 0 -
Appendix - p. 46 of 52
Appendix - p. 46 of 52
HCM 6th AWSC 2021 Total PM Peak Hour.syn
5: State St & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 9
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 30 10 14 21 47 27 8 142 2 8 123 41
Future Vol, veh/h 30 10 14 21 47 27 8 142 2 8 123 41
Peak Hour Factor 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81
Heavy Vehicles, %222222222222
Mvmt Flow 37 12 17 26 58 33 10 175 2 10 152 51
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 8.5 8.8 9.1 9.1
HCM LOS AAAA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %5% 56% 22% 5%
Vol Thru, %93% 19% 49% 72%
Vol Right, % 1% 26% 28% 24%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 152 54 95 172
LT Vol 8 30 21 8
Through Vol 142 10 47 123
RT Vol 2 14 27 41
Lane Flow Rate 188 67 117 212
Geometry Grp 1111
Degree of Util (X) 0.241 0.092 0.157 0.264
Departure Headway (Hd)4.627 4.959 4.809 4.47
Convergence, Y/N Yes Yes Yes Yes
Cap 775 719 744 803
Service Time 2.667 3.01 2.855 2.508
HCM Lane V/C Ratio 0.243 0.093 0.157 0.264
HCM Control Delay 9.1 8.5 8.8 9.1
HCM Lane LOS AAAA
HCM 95th-tile Q 0.9 0.3 0.6 1.1
Appendix - p. 47 of 52
Appendix - p. 47 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
6: State St & E Dwy 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.1
Movement EBL EBR NBL NBT SBT SBR
Lane Configurations
Traffic Vol, veh/h 3 0 0 147 155 4
Future Vol, veh/h 3 0 0 147 155 4
Conflicting Peds, #/hr 0 00000
Sign Control Stop Stop Free Free Free Free
RT Channelized - None - None - None
Storage Length 0 -----
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 85 85 85 85 85 85
Heavy Vehicles, % 2 22222
Mvmt Flow 4 0 0 173 182 5
Major/Minor Minor2 Major1 Major2
Conflicting Flow All 358 185 187 0 - 0
Stage 1 185 -----
Stage 2 173 -----
Critical Hdwy 6.42 6.22 4.12 - - -
Critical Hdwy Stg 1 5.42 -----
Critical Hdwy Stg 2 5.42 -----
Follow-up Hdwy 3.518 3.318 2.218 - - -
Pot Cap-1 Maneuver 640 857 1387 - - -
Stage 1 847 -----
Stage 2 857 -----
Platoon blocked, % - - -
Mov Cap-1 Maneuver 640 857 1387 - - -
Mov Cap-2 Maneuver 640 -----
Stage 1 847 -----
Stage 2 857 -----
Approach EB NB SB
HCM Control Delay, s 10.7 0 0
HCM LOS B
Minor Lane/Major Mvmt NBL NBTEBLn1 SBT SBR
Capacity (veh/h)1387 - 640 - -
HCM Lane V/C Ratio - - 0.006 - -
HCM Control Delay (s) 0 - 10.7 - -
HCM Lane LOS A - B - -
HCM 95th %tile Q(veh) 0 - 0 - -
Appendix - p. 48 of 52
Appendix - p. 48 of 52
HCM 6th AWSC 2021 Total PM Peak Hour.syn
7: State St & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Intersection Delay, s/veh 9.6
Intersection LOS A
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 31 64 45 8 67 22 111 93 14 10 49 95
Future Vol, veh/h 31 64 45 8 67 22 111 93 14 10 49 95
Peak Hour Factor 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88
Heavy Vehicles, %222222222222
Mvmt Flow 35 73 51 9 76 25 126 106 16 11 56 108
Number of Lanes 010010010010
Approach EB WB NB SB
Opposing Approach WB EB SB NB
Opposing Lanes 1111
Conflicting Approach Left SB NB EB WB
Conflicting Lanes Left 1111
Conflicting Approach Right NB SB WB EB
Conflicting Lanes Right 1111
HCM Control Delay 9.4 9 10.4 8.9
HCM LOS AABA
Lane NBLn1 EBLn1 WBLn1 SBLn1
Vol Left, %51% 22% 8% 6%
Vol Thru, %43% 46% 69% 32%
Vol Right, % 6% 32% 23% 62%
Sign Control Stop Stop Stop Stop
Traffic Vol by Lane 218 140 97 154
LT Vol 111 31 8 10
Through Vol 93 64 67 49
RT Vol 14 45 22 95
Lane Flow Rate 248 159 110 175
Geometry Grp 1111
Degree of Util (X) 0.335 0.218 0.154 0.221
Departure Headway (Hd)4.865 4.925 5.022 4.553
Convergence, Y/N Yes Yes Yes Yes
Cap 733 722 708 781
Service Time 2.931 2.999 3.102 2.624
HCM Lane V/C Ratio 0.338 0.22 0.155 0.224
HCM Control Delay 10.4 9.4 9 8.9
HCM Lane LOS BAAA
HCM 95th-tile Q 1.5 0.8 0.5 0.8
Appendix - p. 49 of 52
Appendix - p. 49 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
8: Federal Way & SW Dwy 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.5
Movement EBL EBT WBT WBR SBL SBR
Lane Configurations
Traffic Vol, veh/h 12 167 277 9 3 10
Future Vol, veh/h 12 167 277 9 3 10
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 88 88 88 88 88 88
Heavy Vehicles, % 2 22222
Mvmt Flow 14 190 315 10 3 11
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 325 0 - 0 538 320
Stage 1 - - - - 320 -
Stage 2 - - - - 218 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1235 - - - 504 721
Stage 1 - - - - 736 -
Stage 2 - - - - 818 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1235 - - - 497 721
Mov Cap-2 Maneuver - - - - 497 -
Stage 1 - - - - 726 -
Stage 2 - - - - 818 -
Approach EB WB SB
HCM Control Delay, s 0.5 0 10.6
HCM LOS B
Minor Lane/Major Mvmt EBL EBT WBT WBRSBLn1
Capacity (veh/h)1235 - - - 653
HCM Lane V/C Ratio 0.011 - - - 0.023
HCM Control Delay (s) 7.9 0 - - 10.6
HCM Lane LOS A A - - B
HCM 95th %tile Q(veh) 0 - - - 0.1
Appendix - p. 50 of 52
Appendix - p. 50 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
9: NE Dwy & Federal Way 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 2.8
Movement EBT EBR WBL WBT NBL NBR
Lane Configurations
Traffic Vol, veh/h 14 8 12 27 6 8
Future Vol, veh/h 14 8 12 27 6 8
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # 0 - - 0 0 -
Grade, % 0 - - 0 0 -
Peak Hour Factor 81 81 81 81 81 81
Heavy Vehicles, % 2 22222
Mvmt Flow 17 10 15 33 7 10
Major/Minor Major1 Major2 Minor1
Conflicting Flow All 0 0 27 0 85 22
Stage 1 - - - - 22 -
Stage 2 - - - - 63 -
Critical Hdwy - - 4.12 - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy - - 2.218 - 3.518 3.318
Pot Cap-1 Maneuver - - 1587 - 916 1055
Stage 1 - - - - 1001 -
Stage 2 - - - - 960 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver - - 1587 - 907 1055
Mov Cap-2 Maneuver - - - - 907 -
Stage 1 - - - - 991 -
Stage 2 - - - - 960 -
Approach EB WB NB
HCM Control Delay, s 0 2.2 8.7
HCM LOS A
Minor Lane/Major Mvmt NBLn1 EBT EBR WBL WBT
Capacity (veh/h)986 - - 1587 -
HCM Lane V/C Ratio 0.018 - - 0.009 -
HCM Control Delay (s) 8.7 - - 7.3 0
HCM Lane LOS A - - A A
HCM 95th %tile Q(veh) 0.1 - - 0 -
Appendix - p. 51 of 52
Appendix - p. 51 of 52
HCM 6th TWSC 2021 Total PM Peak Hour.syn
10: Federal Way & SE Dwy 11/22/2019
H:\T1115.11 - TIA for Proposed Development Block 11\Synchro-Updated\2021 Total PM Peak Hour.syn Synchro 10 Report
T1115.11
Intersection
Int Delay, s/veh 0.5
Movement EBL EBT WBT WBR SBL SBR
Lane Configurations
Traffic Vol, veh/h 11 159 276 9 3 10
Future Vol, veh/h 11 159 276 9 3 10
Conflicting Peds, #/hr 0 00000
Sign Control Free Free Free Free Stop Stop
RT Channelized - None - None - None
Storage Length - - - - 0 -
Veh in Median Storage, # - 0 0 - 0 -
Grade, % - 0 0 - 0 -
Peak Hour Factor 88 88 88 88 88 88
Heavy Vehicles, % 2 22222
Mvmt Flow 13 181 314 10 3 11
Major/Minor Major1 Major2 Minor2
Conflicting Flow All 324 0 - 0 526 319
Stage 1 - - - - 319 -
Stage 2 - - - - 207 -
Critical Hdwy 4.12 - - - 6.42 6.22
Critical Hdwy Stg 1 - - - - 5.42 -
Critical Hdwy Stg 2 - - - - 5.42 -
Follow-up Hdwy 2.218 - - - 3.518 3.318
Pot Cap-1 Maneuver 1236 - - - 512 722
Stage 1 - - - - 737 -
Stage 2 - - - - 828 -
Platoon blocked, % - - -
Mov Cap-1 Maneuver 1236 - - - 506 722
Mov Cap-2 Maneuver - - - - 506 -
Stage 1 - - - - 728 -
Stage 2 - - - - 828 -
Approach EB WB SB
HCM Control Delay, s 0.5 0 10.6
HCM LOS B
Minor Lane/Major Mvmt EBL EBT WBT WBRSBLn1
Capacity (veh/h)1236 - - - 657
HCM Lane V/C Ratio 0.01 - - - 0.022
HCM Control Delay (s) 7.9 0 - - 10.6
HCM Lane LOS A A - - B
HCM 95th %tile Q(veh) 0 - - - 0.1
Appendix - p. 52 of 52