Item 7 - PresentationRockenbaugh Elementary School
ZA19-0043
ZA19-0043
OWNER:Carroll ISD
APPLICANT:Hart Gaugler &Associates
REQUEST:Approval of a Site Plan to accommodate
construction of additional classroom space,
modify driveways,and add parking and covered
walkways.
LOCATION:301 Byron Nelson Parkway
Aerial View
Enlarged Aerial View
Current Approved Site Plan (ZA08-054)
The original Site Plan for
Rockenbaugh Elementary School
was approved by the City on
September 3, 1996. (ZA96-086)
A Revised Site Plan adding square
footage to the building was
approved on June 1, 1999. (ZA99-
043)
A Revised Site Plan adding a 400
square foot (20’ x 20’) Shade
Structure (standing seam metal
roof) was approved August 15,
2000. (ZA00-083)
A Revised Site Plan adding
approximately 2,532 square feet in
shade structures (cloth type roofing
material) was approved August 5,
2008. (ZA08-054)
Proposed Site Plan Details
Tree Preservation Plan
The current existing tree
canopy is approximately
22.25%. The applicant is
requesting to remove
approximately 31 trees or
10.25%. The resulting
tree preservation is
approximately 89.75%.
Proposed Elevations
Variance Requests
Building Articulation –variance to requirements in Zoning
Ordinance No.480,as amended,for horizontal and vertical
articulation,allowing building addition as shown on the proposed
elevations.The building elevations are in alignment with the
existing buildings on campus.The addition will match aesthetic
and detailing.
Landscaping –variance to Landscape Ordinance No.544-B,
Sections 3.3 and 3.4,requesting relief from additional interior
landscape requirements and additional landscape requirements
relating to the increase in parking.
Tree Preservation –variance to Tree Preservation Ordinance
No.585-E;requesting that any trees impacted by the building
addition or additional parking will not be mitigated.The resulting
preservation is approximately 89.75%.
Bufferyards –variance to Zoning Ordinance No. 480, as
amended, Section 42, to allow existing bufferyards to remain.
Where bufferyards are impacted by new site parking, requesting
that any trees removed not be mitigated.
Questions?