Item 4FCITY OF
5OUTHLAKE
MEMORANDUM
(December 5, 2017)
To: Shana Yelverton, City Manager
From: Rob Cohen, Director of Public Works
Item 4F
Subject: Approve Contract Amendment No. 7 with Nathan D. Maier
Consulting Engineers, Inc. in the amount of $31,830 for White
Chapel Boulevard from State Highway 114 to East Highland
Street
Action
Requested: Approve Contract Amendment No. 7 with Nathan D. Maier
Consulting Engineers, Inc. in the amount of $31,830 for White
Chapel Boulevard from State Highway 114 to East Highland Street.
Background
Information: In October 2008, Nathan D. Maier Consulting Engineers, Inc.
(NDM) was hired to design the North White Chapel Boulevard
Improvement project from the intersection at State Highway 114
down to, and including, the intersection of Highland Street. The
White Chapel Boulevard Improvement project design was for a
standard four lane divided roadway with a raised and landscaped
median.
The original professional services agreement (design contract) in
the amount of $264,859 included survey for the entire length of the
project, design of the roadway, a hydraulic report of Dove Creek to
properly size the proposed storm sewer box culverts near State
Highway 114, determination of right of way needs and
corresponding exhibits, geotechnical investigations to determine
pavement design, and design for relocating existing water and
sewer utilities within the corridor to accommodate the proposed
roadway. The original design contract signed in 2008 was for the
final design, bid documents and construction phase services of the
White Chapel Boulevard Improvement project.
NDM prepared and submitted conceptual design to the City for
review of a conventional four -lane divided roadway using the
existing centerline and taking right of way equally from both sides of
the proposed roadway. It was later determined that the straight
roadway alignment of White Chapel Boulevard should be shifted at
the intersection of Highland Street so that no additional right of way
Item 4F
will be required from the Southlake Church, due to the proximity of
the existing building to the right of way. Since the property at the
northwest corner of the intersection belongs to the City, there would
also be a cost savings in the right of way acquisition by shifting the
horizontal alignment of the roadway to the west.
Supplemental Agreement No. 1, in the amount of $12,285 was
approved by the City Manager in January, 2010 to revise the
horizontal alignment of White Chapel Boulevard at the intersection
of Highland Street to the west and add 2 feet of pavement on both
sides of the road for bike lanes. The design fee for the revision
also included revising the new typical sections of the roadway to
include the additional 2' on each side of the road to accommodate
bike traffic.
NDM coordinated with design engineers for the White Chapel
Countryside Office Park and made alignment recommendations for
the City's waterline construction project along Highland Street,
which is now complete. NDM had also revised the schematic
layout at the intersection and submitted it to staff for review.
Design had progressed to nearly 30% when the City suspended
work on the roadway design to allow consideration of alternative
traffic control methods at the Highland Street intersection.
Traffic circulation issues at Carroll High School caused the staff to
reconsider operation of the Highland Street intersection. Several
different types of intersection control methods were evaluated to
determine the most advantageous approach. A traffic engineering
consultant looked at the costs and level of service (LOS) for two
way stop control, four way stop control, traffic signal control, a
single lane roundabout, and a dual lane roundabout. Staff has
presented these options to members of the City Council and
Planning and Zoning Commissioners at two Southlake 2030 work
sessions. Summarizing those discussions, the two way and four
way stop control intersection and the single lane roundabout will not
efficiently handle the projected 2019 volume of traffic without
excessive delay. Signal control would be useful during the morning
and afternoon peak periods, but would not operate efficiently during
the remainder of the day and would impose continuing
maintenance and operation costs. The dual lane roundabout, does
improve capacity at the intersection and creates the least delay for
drivers of the options considered. Council and Planning and
Zoning members of the 2030 committee directed Staff to move
forward with the design of a dual lane roundabout at the
intersection of North White Chapel Boulevard and Highland Street.
Item 4F
Supplemental Agreement No. 2, in the amount of $173,827 was for
the completion of design of White Chapel Boulevard along a
revised alignment to avoid taking right of way from Southlake
Church and included a dual lane roundabout at the intersection of
Highland Street.
The revised scope as outlined in Supplemental Agreement No. 2
included additional survey of up to 350' beyond the original limits of
Highland Street and up to 500' north of Highland Street along White
Chapel to accommodate the dual lane roundabout and the revised
alignment of the intersection. The agreement also included
landscaping and irrigation design of the proposed roundabout and
the center medians along White Chapel Boulevard. Subsurface
utility engineering work was to be performed in order to verify the
location of existing water and sanitary sewer lines and any other
private utilities within the corridor that will need to be relocated prior
to beginning construction. The utility design included the relocation
of existing sanitary sewer mains which will be in conflict with the
new pavement. The drainage design was updated to incorporate
the drainage from the new Countryside White Chapel Office Park
development that has been constructed since the original drainage
study was performed by NDM. Finally, the revised scope included
final engineering plans, traffic control and sequencing for
construction, contract documents, bidding of the construction
project and construction administration.
Supplemental Agreement No. 3, in the amount of $14,778 was for
re -alignment of White Chapel Boulevard to tie-in to the White
Chapel Boulevard Reconstruction project from Emerald Boulevard
to Highland Street. Changes also included lowering the elevations
of the roundabout subsequently resulting in the redesign of utilities
to lower them as well.
The revised scope for Supplemental Agreement No. 3 coordinated
the connection point between the two separately engineered White
Chapel widening projects. The White Chapel Boulevard
Reconstruction project from Emerald Boulevard to Highland Street
had a design that ended the pavement at a point 500 feet south of
Highland and transitioned into the existing pavement. The design
plans under this contract scope ended the pavement south of the
dual lane roundabout and had a design transition to existing
pavement at a point 500 feet south of Highland Street.
Supplemental Agreement No. 3 eliminated the transitions in each
set of plans and coordinated the matchline point. This caused for
some alignment changes through the transitions to marry the plans.
The roundabout was also lowered to eliminate a retaining wall at
the roundabout along the Southlake Church property.
Item 4F
The revised scope as outlined in Contract Amendment No. 4
included design for 1,250 linear feet of a new 8 inch sanitary sewer
gravity extension from approximately 400 feet south of Highland
Street north to an existing lift station located at Countryside Court.
The amendment also included coordination services for right of way
acquisition and additional right of way and easement document
preparation. Contract Amendment No. 4 was approved by City
Council on April 2, 2013 in the amount of $53,316.
Contract Amendment No. 5 in the amount of $12,709 was for the
design of a right -turn lane on southbound North White Chapel
Boulevard to westbound Countryside Court. The right -turn lane
was recommended with the development of the 3 -story medical
office building at this location known as Chapel Crossing. The
developer of Chapel Crossing escrowed $42,794 to reimburse the
City for the design of the right -turn lane ($12,709) and the probable
cost of the construction of the right -turn lane with the widening of
North White Chapel Boulevard ($30,085). This amendment was
approved by the City Manager in December 2014.
Contract Amendment No. 6 was also approved by the City Manager
in the amount of $16,000. This amendment was for right of way
staking for franchise utility relocation.
The revised scope as outlined in Contract Amendment No. 7
includes redesign of the traffic control plan after approval of the
temporary closures of West and East Highland Street to allow for
more efficient construction of the roundabout. This amendment
also modifies the bid phase and construction phase services of the
original contract.
A bid phase services task was included in the original 2008 scope
services but did not have a value associated with it. The value of
the bid phase services is $9,940 dollars. The original contract had
a construction phase services task in the amount of $12,470.
Supplemental Agreement No. 2 increased the construction phase
services by $2,640 for a total fee of $15,110. However, based on
the task descriptions for construction phase services in the original
scope, the construction phase services scope would have been
$54,700. Amendment No. 7 would revise the language and scope
of construction phase services to be on an as needed basis with a
not to exceed value of $20,000.
Item 4F
Traffic Control Plan Redesign $17,000
Bid Phase Services $ 9,940
Construction Phase Services 4,890
Total Amendment No. 7 $31,830
The proposed amendment brings the total engineering design cost
for the White Chapel Boulevard from State Highway 114 to East
Highland Street Project to $579,604.
The project has been awarded to RKM Utility Services for
construction. The traffic control plan redesign will incorporate their
suggestions and schedule so that the road closures of East and
West Highland Street can take place during the summer of 2018.
Financial
Considerations: Funds for the engineering design of the White Chapel Boulevard
Improvement project are included in the previously approved
Capital Improvements Program project budget.
Strategic Link: The construction of the North White Chapel Boulevard
Improvements project links to the City's strategy map relative to the
focus areas of Mobility, Infrastructure and Quality Development.
The specific corporate objectives that are met by the construction of
this project include: C2 - Provide travel convenience within the City
and the region, and F2 - Invest to provide and maintain high quality
public assets. The critical business outcome is CBO2 - Enhance
mobility through aggressive traffic management initiatives and
capital project implementation.
Citizen Input/
Board Review: N/A
Legal Review: This is the standard construction services contract that has been
previously reviewed by the City Attorney.
Alternatives: The Council may approve the Amendment to the existing
Professional Services Agreement or deny it.
Supporting
Documents: Location Map
Nathan D. Maier Consulting Engineers, Inc. Contract
Item 4F
Amendment No. 7
Staff
Recommendation: Approve Contract Amendment No. 7 with Nathan D. Maier
Consulting Engineers, Inc. in the amount of $31,830 for White
Chapel Boulevard from State Highway 114 to East Highland Street.
Staff Contact: Rob Cohen, Public Works Director
Kyle D. Hogue, P.E., Deputy Director/City Engineer
Steven D. Anderson, P.E., CFM, Deputy City Engineer
E. Highland St
oA�
O
EXHIBIT SA -7
Supplemental Agreement No. 7
I Ell
WHITE CHAPEL BOULEVARD
111 MILVA
E. NORTHWEST PARKWAY (S.H. 114) TO E. HIGHLAND STREET
I XIA�
THE CITY OF SOUTHLAKE, TEXAS
This Supplemental Agreement No. 7 amends the original Scope of Services dated 10/14/08 to
include additional services to complete the construction plan set and bidding documents, as well as,
modifying the scope of services of Construction Administration from the original contract as
previously submitted to the City of Southlake by Nathan D. Maier Consulting Engineers, Inc.
(NDM).
The proposed changes altering the original scope include:
I. Construction Plan Set
NDM will finalize the plans for White Chapel Boulevard after approval of the temporary
closures of West and East Highland Street. Final plans will be prepared per the original
Scope of Services and previous Supplemental Agreements.
II. Bidding Documents
NDM will prepare bidding documents as outlined in the original Scope of Services. This
Supplemental Agreement is only to establish a fee for this scope as one was not established
in the original Agreement for Engineering Services.
III. Construction Administration
The original Scope of Services for Construction Administration shall be amended as such:
Section XVIII, Paragraph C — Construction Observation - NDM will perform site -visits as -
needed to determine the overall progress of construction and conformance with plans and
specifications and attend monthly progress meetings if needed. The scope does not include
the services of a full time project inspector. The scope does not include scheduled
observation for the duration of the project. Compensation for Construction Observation
will come from the not -to -exceed amount providing there are funds available.
Section XVIII, Paragraph E — NDM will review shop drawings as -needed and provide
written responses to requests for information or clarification to City or Contractor.
Compensation for shop drawing review and written responses will come from the not -to -
exceed amount providing there are funds available. Upon substantial completion of
construction, the Engineer will conduct a final project walkthrough with the Contractor and
City of Southlake and provide a punch list of outstanding issues.
For Construction Administration services provided pursuant to this Supplemental
Agreement, the City of Southlake shall pay NDM an amount not to exceed $20,000.00
($12,470 from the original Agreement for Engineering Services, $2,640 from Supplemental
Agreement No. 2, and $4,890 from Supplemental Agreement No. 7). These services shall
be invoiced on an hourly, not -to -exceed basis. The maximum overall fee established herein
shall not be exceeded without written authorization from the City of Southlake, based on
increased scope of services.
Supplemental Agreement No. 7
For
White Chapel Boulevard
E. Northwest Parkway (S.H. 114) to Highland Street
Engineering Fees
DESCRIPTION ENGINEERING FEE
BASIC SERVICES
Roadway Design $129,639
TOTAL BASIC SERVICES $129,639
SPECIAL SERVICES
Survey Services
$35,170
Hydraulic / Hydrology Study and Analysis
$25,485
Waterline Replacement
$19,455
Permitting
$11,160
Construction Administration
$12,470
Geotechnical Investigation
$8,000
Reimbursable Expenses
$2,900
Unit Costs ($1,715 per unit) $20,580
Right-of-way dedication exhibits
Easement dedication
TOTAL SPECIAL SERVICES $135,220
TOTAL ENGINEERING $264,859
SUPPLEMENTAL AGREEMENT NO. 1
TOTAL FOR SUPPLEMENTAL NO. 1
$12,285
TOTAL ENGINEERING $277,144
SUPPLEMENTAL AGREEMENT NO. 2
BASIC SERVICES
Roadway Design $79,735
SPECIAL SERVICES
Survey Services
$22,164
Drainage Design
$7,254
Utility Design
$4,654
Subsurface Utility Engineering
$39,450
Landscape and Irrigation Design
$12,500
Construction Administration
$2,640
Reimbursable Expenses
$2,000
Unit Costs ($1,715 per unit) $3,430
Additional ROW Dedication Exhibits
Additional Easement Dedication Exhibits
TOTAL FOR SUPPLEMENTAL NO. 2 $173,827
TOTAL ENGINEERING $450,971
SUPPLEMENTAL AGREEMENT NO.3
BASIC SERVICES
Roadway Design $7,415
SPECIAL SERVICES
Drainage Design $530
Utility Design (Water Line Replacement) $6,608
Reimbursable Expenses $225
TOTAL FOR SUPPLEMENTAL NO. 3 $14,778
TOTAL ENGINEERING $465,749
SUPPLEMENTAL AGREEMENT NO.4
SPECIAL SERVICES
ROW / Easement Acquisition Coordination $5,115
Utility Design (8" Wastewater Gravity) $12,086
Reimbursable Expenses $100
Unit Costs ($1,715 per unit) $36,015
Additional ROW Dedication Exhibits
Additional Easement Dedication Exhibits
TOTAL FOR SUPPLEMENTAL NO. 4 $53,316
TOTAL ENGINEERING $519,065
SUPPLEMENTAL AGREEMENT NO. 5
BASIC SERVICES
Roadway Design $7,221
SPECIAL SERVICES
Drainage Design $5,388
Reimbursable Expenses $100
TOTAL FOR SUPPLEMENTAL NO. 5 $12,709
TOTAL ENGINEERING $531,774
SUPPLEMENTAL AGREEMENT NO. 6
SPECIAL SERVICES
ROW staking and grade calculations $16,000
TOTAL FOR SUPPLEMENTAL NO. 6 $16,000
TOTAL ENGINEERING $547,774
SUPPLEMENTAL AGREEMENT NO. 7
BASIC SERVICES
Roadway Design $17,000
SPECIAL SERVICES
Construction Bidding $9,940
Construction Administration $4,890
TOTAL FOR SUPPLEMENTAL NO. 7 $31,830
TOTAL ENGINEERING $579,604