Loading...
Sept - FM 1938 Southlake Photo by Liam Frederick Fort Worth District FM 1938 Construction Update Brian R. Barth, P.E. District Engineer Tuesday, September 20, 2016 1 3 FM 1938 (Davis Extension) Phase I—from SH 114 to Randol Mill Ave / Completed Fall 2012 / Cost ~ $15 million Phase II—from Randol Mill Ave to FM 1709 (Southlake Blvd) Began Spring 2015 Partnership Project with Cities of Southlake, Keller, Westlake and Trophy Club and FHWA, Tarrant County, NCTCOG and TxDOT    3 4 FM 1938 Phase II Quick Facts Length: 1.6 miles Est. Cost: $20.6 M Description Four-lane roadway with curbed medians and left turn bays Widen FM 1938 / FM 1709 intersection to provide dual-left turn bays on each approach Landscaping, illumination and sidewalks Progress: 60% of total project complete On schedule despite early utility delays Est. Completion: 2017 Discuss bullet points Project began in Spring (March) 2015 with first earth work beginning in June 2015 due to extreme rain events Project team always looking at ways of expediting completion time FYI……At this time, total project time takes 617 working days due to change orders related to numerous utility conflicts 4 5 FM 1938 Progress Before Construction Underground Drainage Installation New Roadway Construction Pavement Placement Earth Work Example of construction process north of the intersection Involves significant amount of underground storm drainage to be installed (approximately 70% placed to date). Slow progress early in process with wet weather and discovery of numerous unknown utilities. Followed by earth work and subgrade stabilization, again difficult to perform in wet weather conditions Southbound pavement placed Traffic switched to new southbound pavement section in order to begin work on northbound pavement section 5 6 FM 1938 Progress The majority of the northbound lanes have been completed. Work will begin later this month on the new southbound lanes between Fawkes Lane and Florence Road. Significant amount of new roadway concrete pavement placed north of FM 1709 Traffic currently switched to new southbound pavement from Florence Rd to FM 1709 Upcoming planned traffic switch will move traffic to new northbound lanes from Palomar Trail to near Fawkes 6 7 FM 1938 Progress Original Roadway (Hillside Court) New Roadway Completed Side Streets Johnson Road Lovegrass Lane Top Rail Lane Hillside Court Palomar Trail Florence Road Current Activity Camden Circle Kingswood Drive Beam Drive Remaining Activity Wildwood Way Brookforest Drive Fawkes Lane Example of construction process for side street 12 total side streets that need to be reconstructed in order to tie in to FM 1938 Each of these locations involve placement of underground storm drainage along with new concrete pavement. At some locations access has to be maintain all the time due to no other access, which makes for construction challenges. 7 8 FM 1938 Progress Residential Driveways 18 Completed 3 Under Construction 26 Future Stage Nearly half of residential driveways complete or under construction 47 total residential driveways north of FM 1709 intersection to be reconstructed This effort being coordinated with each property owner to maintain access or limit amount of impact through use of high early strength concrete in some instances 8 9 FM 1938 / FM 1709 Intersection Progress Completed Activity All Driveways Storm Drainage Most Curb/Gutter Most Sidewalks This slide shows the construction activity at the intersection 13 total business access driveways reconstructed / open at intersection Maintaining access to businesses throughout construction on each quadrant of intersection Have removed the low profile concrete barrier located on the outside lanes and replaced with barrels in anticipation for beginning to perform pavement work Discuss completed activity 9 Remaining Activity North of FM 1709 10 North End of Project Sept. 24-25 traffic switch from Fawkes to Florence (Local Access Maintained) Construct southbound pavement Re-construct side streets Fawkes Ln Beam Dr Brookforest Wildwood Way Re-construct remaining residential driveways South End of Project Construct screen walls Construct curbed medians Discuss bullets North End Project Southbound pavement from Fawkes Ln to Palomar Trail - pavement sections include underground storm drainage, retaining walls and sidewalk installation South End Project screen walls located outside of Myers Meadow subdivision (east side, Lovegrass Ln to Hillside Ct) Entire Project Limits also includes: Irrigation and landscaping (grass, shrubs and trees (350)) 10 11 FM 1938 Intersection Work Expedited Originally scheduled completion: Spring 2017 After further design review and city approved night/weekend work Expedite substantial completion: End of 2016 End of Year: Pavement improvements complete Dual left turn lanes open 2017 Occasional left turn closures needed to complete medians/misc. work Discuss bullet points Work at Intersection of FM 1938 at FM 1709 began in August 2015 Project team continually looking at ways of expediting intersection completion time 11 Public Information 12 Traffic Impacts and Updates E-alerts One-on-One Meetings Websites and Social Media: City of Southlake and City of Keller Newsletters/Newspaper Tarrant County Commissioner Fickes’ Northeast Newsletter Community Impact Newsletter Fort Worth Star Telegram Public Outreach Mobility Coordinator: Stephen E. Ranft fm1938mobility@gmail.com (817) 462-0520 Send out email-alerts to announce lane closures, road closures and traffic switches Project information disseminated to public through One-on-One Meetings, Cities of Southlake and Keller websites, local newsletters and Star Telegram Utilizing mobility coordinator to reach out to residents and businesses to coordinate project activity/information 12 Work Zone Driving Safety Minute 13 Slow down Always follow work zone speed limits Pay attention Be Patient Plan ahead Stay Alert: Don’t talk or text while driving Check highway conditions at DriveTexas.org. Speed one of major causes of work zone crashes Traffic fines double in work zones Workers and heavy equipment may only be a few feet from passing vehicles Delays can be frustrating but it only takes a few extra minutes to slow down for a work zone Leave a few minutes early when traveling through a work zone to reach your destination on time. Distraction is the second major causes of crashes in work zones 13 Questions ? 14 THANK YOU Fort Worth District 15