Item 6D,E,F
Carillon Corporate DistrictHotel Indigo
Items 6D-6F
1
Applicant: Jacobs Engineering, Inc.
Requests: 6D) Zoning Change and Development Plan for Carillon Corporate District to allow a Hotel Indigo.
6E) Site Plan for Hotel Indigo
6F) Preliminary
Plat for Hotel Indigo
Location: Southwest corner of Carillon Court and Riviera Lane
ZA16-029, ZA16-030, ZA16-031
Jacobs Engineering, Inc. is requesting approval of a Zoning Change and Development Plan for Carillon Corporate District to allow a Hotel Indigo. I will present 6D, 6E, and 6F together
2
The Future Land Use designation is Mixed Use.
3
The current zoning is ECZ Employment Center Zoning District.
4
6D Aerial View
Carillon Corporate District (ZA16-029)
An aerial view of the Carillon Corporate District is shown outlined in green.
5
6E Aerial View
Malai Kitchen
Site Plan Boundary (ZA16-030)
The Hotel Indigo lot included in the Site Plan is outlined in red.
6
6F Aerial View
Malai Kitchen
Preliminary Plat Boundary (ZA16-031)
The preliminary plat boundary is shown here in blue.
7
Item 6D - Existing Development Plan
The existing development plan shows two office building in blue 3 stories – approximately 160 K each), two retail buildings in pink (approx 13,000 sq ft each) and two parking garages
in the Corporate District. A right out only street connection is shown between the west office building and the plaza district. A hotel is shown in tan in the Plaza District.
8
Item 6D - Development Plan at 1st Reading
Hotel Indigo
Driveways to office property removed
After receiving input from Carillon residents, the right out driveway to SH 114 was added back to the plan and the driveway from Carillon Court to the office property was removed. A
driveway connection to the Plaza District to the west was also added on this plan.
9
Item 6D - Proposed Development Plan
This is the development plan under consideration this evening. The hotel has been flipped and the main entrance is towards Carillon Court or internal. Internal drive access from the
office district to Carillon Court have been removed. Right out drive just west of the hotel added. Childrens health building added to the master plan
10
Amend the permitted uses to allow a hotel as a permitted use in the Corporate District. The hotel height maximum is 90’. 100’ as indicated in the Plaza District restrictions. The hotel
architectural design is to generally conform to the Hotel-specific Plaza District requirements in the ECZ zoning.
Redefine the parking standards for the hotel use based on 1.2 spaces
per hotel room.
Amend the zoning to allow a loading zone at the front entrance.
Revise the Development Plan to incorporate a hotel use along S.H 114 and to replace the Plaza Street
‘C’ connection to S.H. 114 with a common access driveway.
Proposed amendments to the ‘ECZ Zoning District
* Changes to amendments since 1st reading on 8/2/2016
The proposed amendments to the ECZ zoning district are shown here with the changes to the amendments since 1st reading highlighted in red. The zoning is proposed to be amended to allow
a hotel in the Corporate District. The regulations for the hotel are proposed to be the same as the approved hotel in the Plaza District, with a maximum height of 90’., changed from
100’ per Council at 1st reading. Two other proposed changes are to redefine the parking standards for the hotel use based on 1.2 spaces per hotel room and to revise the Development Plan
to incorporate a hotel use along S.H 114 and to replace the Plaza Street ‘C’ connection to S.H. 114 with a common access driveway. The loading zone has been relocated, so the amendment
to allow a loading zone at the front entrance has been removed per Council’s direction at 1st reading.
11
Carillon ZoningCorporate District
The offices are intended to be 3 stories and about 160.K sq ft in size, 50 ‘ setback from SH 114 and 20’ from Kirkwood and internal ROW.
65’ height minimum with the provison
+ one 12 foor bonus floor
12
Item 6D - Corporate District Revisions
Here is a close up view of the Corporate District with the revisions.
13
6D. Circulation Plan
There is a Carillon circulation plan that identifies certain streets in the development and provides special streetscape designs
Street P – incorporates a 20 foot landscape buffer on
the office side of the street.
14
Corporate District Revisions
Plaza Street C connection replaced with common access driveway
The zoning is also being revised to replace the Plaza Street C connection with a common access driveway. As discussed before, the driveway will have a right out only connection to SH
114 and a connection to the Plaza District to the west.
15
Item 6D - Corporate District Revisions
Plaza Street C connection replaced with common access driveway
Plaza Street C was also revised on this page in the zoning booklet.
16
Item 6E - Proposed Hotel Indigo (ZA16-030)
The next few slides address the site plan exhibits – item 6E. The first floor will have the cut stone clad finish, Levels 2 through 4 will have the stucco finish and the 5th floor will
have the French mansard roofs. There are no vtac or ptac systems – roof top air conditioning equipment.
17
Item 6E - Elevations
Stone
Stucco
The north and south elevations of the hotel are shown here. The façade materials are stone and stucco.
18
Elevations
The east and west elevations of the hotel are shown here.
19
Hotel Indigo Details
Five (5) stories with 88,000 – 91,000 sq. ft. gross floor area
119 - 121 guestrooms - 300 sq. ft. minimum
Full service restaurant and bar - 2,200 sq. ft.
Ballroom and meeting rooms
- 3,000 – 4,000 sq. ft.
Fitness center - 750 sq. ft.
Full service kitchen, on-site laundry, office spaces and support services
Central A/C with screened roof mounted mechanical equipment
Here are some details of the proposed hotel.
20
Item 6E - Previous Hotel Indigo Site Plan (ZA16-030)
The proposed site plan for Hotel Indigo at 1st reading is shown here. The gross floor area is approximately 88,000 -91,000 square feet and the height is shown at 58’. The park areas
has been modified and trails and a gazebo are shown. A dog park that was presented in the open space lot at P&Z has been removed.
21
Item 6E - Revised Hotel Indigo Site Plan (ZA16-030)
Main entrance facing Carillion Ct.
Loading zone relocated
Dumpster enclosure relocated
The revisions to the site plan to address Council’s issues and concerns at 1st reading are shown here. The hotel has been flipped so that the main entrance faces Carillon Ct. The Corridor
Overlay District requires dumpster enclosures to be located to the side or rear of the principal building so the dumpster has been relocated to the south along the SH 114 frontage road.
The loading zone has been relocated from in front of the building to the eastern driveway. The future ROW indicated dedication for the offsite access easement is also labeled on the
Site Plan.
22
Item 6E - Primary Entry
We talked about defining the public realm. The zoning includes project entry plan for the development. Project entries help to define the community’s edge. There is also a major
intersection plan. The concept is intended to engage both the pedestrian and vehicle. Opportunities exist to incorporate public art, special paving, fountains.
23
Item 6E - Gazebo Examples
24
Variance Requested
A variance to Driveway Ordinance No. 634, as amended, Section 5.2(d), requiring a stacking depth of 75’ for both driveways on the proposed hotel site, is requested to allow approximately
20’ of stacking depth on the west driveway and approximately 25’ of stacking depth on the east driveway.
A variance to Driveway Ordinance No. 634, as amended, Section 5.2(d), requiring a stacking depth of 75’ for both driveways on the proposed hotel site, is requested to allow approximately
20’ of stacking depth on the west driveway and approximately 25’ of stacking depth on the east driveway.
25
Item 6E - Variance Exhibit
±20’
±25’
75’ Stacking Depth Required
Here is an exhibit showing the requested stacking depth variances.
26
Item 6E - Previous Landscape Plan
27
Item 6E - Revised Landscape Plan
28
Original Tree Preservation Analysis
Carillon Corporate District
Hotel Indigo Site
The Tree Preservation Analysis that was approved with the original Carillon zoning in 2008 showed all trees in the Corporate District to be subject to removal.
29
Item 6E - Previous Tree Preservation Plan
The Tree Preservation Plan for the hotel lot proposes 17% of the existing tree cover to be preserved.
30
Item 6E - Revised Tree Preservation Plan
The Tree Preservation Plan for the hotel lot proposes 17% of the existing tree cover to be preserved.
31
Item 6F - Preliminary Plat
32
ZA16-029
Planning and Zoning Commission:
May 19, 2016; A motion to the deny the item received a 2-2 vote.
City Council:
June 7, 2016; Tabled on consent (7-0) to the August 2, 2016 meeting.
August
2, 2016; Approved at 1st reading (7-0) subject to the staff report dated July 26, 2016 and Development Plan Review Summary No. 3, dated July 22, 2016, granting the variance to the Driveway
Ordinance No. 634, as amended, Section 5.2.d requiring a stacking depth of 75’ for both driveways on the proposed hotel site allowing approximately 20’ of stacking depth on the west
driveway and approximately 25’ of stacking depth on the east driveway noting the following:
that the applicant has indicated a willingness to work with staff on the right of way continuation
of Carillon Ct.;
also noting the applicant has agreed to offer alternative options at 2nd reading related to the commercial loading and unloading space and the potential to move that
out of the front of the building and the front entrance;
noting the applicant’s agreement that the maximum building height will be 90’;
and finally noting that Council with this approval
is directing staff to initiate a rezoning process in the Plaza District at Carillon specifically to the line item use of hotel as a permitted use and noting the applicant has consented
to this staff action.
August 16, 2016; Tabled on consent to the September 6, 2016 meeting.
A motion to deny the item received a 2-2 vote at the May 19, 2016 Planning and Zoning meeting.
33
ZA16-030
Planning and Zoning Commission:
May 19, 2016; A motion to the deny the item received a 2-2 vote.
A motion to deny the item received a 2-2 vote at the May 19, 2016 Planning and Zoning meeting.
34
ZA16-031
Planning and Zoning Commission:
May 19, 2016; A motion to the deny the item received a 2-2 vote.
A motion to deny the item received a 2-2 vote at the May 19, 2016 Planning and Zoning meeting.
35
Questions?
36