Loading...
Item 4C CITY OF SOUTHLAKE Item 4C MEMORANDUM (June 7, 2016) To: Shana Yelverton, City Manager From: Rob Cohen, P.E. Director of Public Works Subject: Sanitary Sewer System Improvements Action Requested: Reject the bid for the construction of Sanitary Sewer System Improvements. Background Information: In November 2014, with the approval of City Council, Baird, Hampton & Brown Inc. initiated the design of the sanitary sewer system improvement project. The project consisted of the construction of sanitary sewer at four different locations in the City - Summerplace Lane, Commerce Street and Market Loop, North Carroll Avenue and East Highland Street, North Carroll Avenue and Casey Court. The first two locations involved rehabilitation and reconstruction of the existing sanitary sewer while the next two involved new construction. The existing sanitary sewer required reconstruction to overcome several deficiencies such as size, shallow depth, sags and flat slopes resulting in very frequent maintenance by the City staff. Altogether, approximately 5,500 LF of 8-inch sanitary sewer pipe was proposed to be constructed with this project. In addition to the above listed work, a deteriorating and undersized corrugated metal storm sewer line at Summerplace Lane was proposed to be replaced with a new 36-inch reinforced concrete pipe (RCP). All the projects were lumped together into one contract with the expectation of economies of scale that would result in a better bid price and reduced overall project costs associated with engineering, administration and inspection. All projects were approved and $1,835,000 was dedicated for this initiative. The design and project specifications were completed in April 2016 and advertised to bid on May 1 , 2016 and May 8, 2016 in the local newspaper. The advertisement was also posted on the City website. The bidding was performed in compliance with the Texas government code (TGC) guidelines. One (1) bid was received on Item 4C May 17, 2016. The bid was reviewed by Baird, Hampton & Brown, Inc. and the City staff. The bid information is seen below: BIDDER BID AMOUNT OPCC Wilson Contractor Services $1 ,934,897 $1 ,381 ,000 The Opinion of Probable Construction Cost (OPCC) prepared by the consulting engineer was underestimated by approximately 40%. Contractors that pulled plans but failed to bid on the project were contacted. Reasons that bids were not provided for this project included contractor capacity was maximized, abundant work, methods of construction (direct bore versus open trench), project locations and scheduling. Portions of the work were required to be completed during the summer months while school was not in session. Following options can be considered by the City Council: a. Authorize additional funds to the project budget, in the amount of approximately $465,000, to cover engineering, material testing and construction contingencies and award the contract to Wilson Contractor Services b. Re-bid as is early next year and provide more time for the contractors to compile bids. c. Re-bid as individual projects Based on the current market condition and feedback from the contractors and engineers, staff recommends Option B. Even with this option, staff requests additional funds to be added in the FY2017 budget in the amount of $465,000 for a total project cost not to exceed $2,300,000 to cover similar uncertainty. Financial Considerations: Funding for the 8-inch Sewer Line along North Carroll Avenue from Highland Street to Whispering Lane and 8-inch Sewer Line along Summerplace Lane from Highland Street to Dove Creek Trail was approved in the FY2014 Utility Fund budget. The funding for the 8- inch sewer Line along Market Loop and Bank Street lift station was approved in the FY2015 Utility Fund budget. Funding for Summerplace drainage improvements was approved in the FY2016 Storm Water Utility System Fund. Strategic Link: This project links to the City's strategy map relative to the focus area of Infrastructure by adhering to providing and maintaining high quality public assets. Item 4C Citizen Input/ Board Review: N/A Legal Review: No review required. Alternatives: The Council may reject all bids or authorize additional funds and award the contract to Wilson Contractor Services. Supporting Documents: Location Map Bid Tabulation Staff Recommendation: Reject the bid for the construction of Sanitary Sewer System Improvements. Staff Contact: Rob Cohen, P.E., Public Works Director Om Gharty-Chhetri, P.E., Civil Engineer W N Z_ zs �o 0,7o 'Nl 3H1A18 0 20 V z J � N Z D Z W g a = c� 3 a uj U '3AV 110aaVO 'N <v' �31N\V�'Id1�3dW� BHB No.2014.724.000 BHB Engineering Surveying 5/18/2016 4550 S.H.360,Suite 180 Grapevine,TX 76051 Tel(817)251-8550,Fax(817)251-8810 BID TABULATION Sanitary Sewer System Improvements at Summerplace Ln./N.Carroll Ave.&E.Highland St./ Market Loop&Commerce St./N.Carroll Ave.&Casey Ct. Storm Drain Improvements at Summerplace Ln. City of Southlake,Texas 5/18/2016 BHB Engineers Estimate Wilson Contractor Services,LLC Shaded Quantities&Totals=Correction to Submitted Bid Provided Bid Bond Yes Item no. Item Description Quantity Unit Unit Cost Amount Unit Cost Amount Sht 02:Summerplace Ln.Sanitary SewerImprovements(890 LF) 1 Implement and Maintain Erosion Control Measures 1 LS $ 1,500.00 $ 1,500.00 $ 2,925.00 $ 2,925.00 2 Implement and Maintain Traffic Control 1 LS $ 2,000.00 $ 2,000.00 $ 4,200.00 $ 4,200.00 3 Misc Utility Adjustments(Including Sprinklers) 1 LS $10,000.00 $ 10,000.00 $10,000.00 $ 10,000.00 4 Abandon 6"SS&Fill w/C.L.S.M. 870 LF $ 5.00 $ 4,350.00 $ 10.00 $ 8,700.00 Abandon SSMH:Remove Rim,Cover,&Top Cone Section.Fill w/C.L.S.M. 5 Provide Permanent Pavement Repair 1 EA $ 750.00 $ 750.00 $ 3,150.00 $ 3,150.00 6 Reconstruct Existing Sanitary Sewer Manhole Opening to 30" 1 EA $ 1,300.00 $ 1,300.00 $ 2,550.00 $ 2,550.00 7 Sawcut,Demolish,Remove,&Dispose Ex Cone Sidewalk Pvmt 13 LF $ 2.00 $ 26.00 $ 30.00 $ 390.00 8 ISawcut,Demolish,Remove,&Dispose Ex Cone Pvmt 175 LF $ 10.00 $ 1,750.00 $ 30.001$ 5,250.00 9 Sawcut,Demolish,Remove,&Dispose Ex Cone Curb&Gutter 40 LF $ 5.00 $ 200.00 $ 20.00 $ 800.00 10 Conduct Pre Construction Television Inspection 870 LF $ 2.00 $ 1,740.00 $ 2.00 $ 1,740.00 11 8"PVC SDR-35 SS Pipe By Open Trench 755 LF $ 40.00 $ 30,200.00 $ 86.00 $ 64,930.00 12 8"PVC SDR-26 SS Pipe By Open Trench 85 LF $ 44.00 $ 3,740.00 $ 50.00 $ 4,250.00 13 Jack/Bore 8"Certa-Flo Greenline SDR 21 PVC SS Pipe or Approved Equal 50 LF $ 175.00 $ 8,750.00 $ 255.00 $ 12,750.00 14 16"Steel Casing Pipe with Spacers for 8"SS Carrier Pipe By Open Trench 10 LF $ 135.00 $ 1,350.00 $ 200.00 $ 2,000.00 15 4"SS Service Connection to Main 20 EA $ 400.00 $ 8,000.00 $ 400.00 $ 8,000.00 Jack/Bore 4"Certa-Flo Greenline SDR 21 PVC SS Service Pipe or Approved 16 lEqual(Long Services) 405 LF $ 125.001$ 50,625.00 $ 70.001$ 28,350.00 17 4"SDR 35 PVC SS Service Pipe By Open Trench(Short Services) 75 LF $ 25.00 $ 1,875.00 $ 30.00 $ 2,250.00 18 4"Private Plumbing Connection for Jacked/Bored Services 90 LF $ 20.00 $ 1,800.00 $ 35.00 $ 3,150.00 19 Trench Excavation Safety for Sewer Line Depth>5' 915 LF $ 2.00 $ 1,830.00 $ 10.00 $ 9,150.00 20 Install/Construct SSCO at R.O.W.Line 20 EA $ 200.00 $ 4,000.00 $ 230.00 $ 4,600.00 21 Install/Constmct4'Dia.SSMH(6'Deep) 5 EA $ 3,600.00 $ 18,000.00 $ 4,480.00 $ 22,400.00 22 Install/Construct Extra Depth for4'Dia.SSMH 8.4 VF $ 250.00 $ 2,100.00 $ 180.00 $ 1,512.00 23 Install/Construct Concrete Collar for SSMH 1 EA $ 250.00 $ 250.00 $ 1,000.00 $ 1,000.00 24 Conduct Post Construction Television Inspection 890 LF $ 2.00 $ 1,780.00 $ 2.00 $ 1,780.00 25 lConduct SSMH Vacuum or Ex'iiltration Test 5 EA $ 250.001$ 1,250.00 $ 300.001$ 1,500.00 26 Conduct SS Line Vacuum or Ex'iiltration Test 890 LF $ 1.00 $ 890.00 $ 2.00 $ 1,780.00 27 4"Cone Sidewalk Pavement Repair 10 LF $ 5.00 $ 50.00 $ 10.00 $ 100.00 28 Flagstone Sidewalk Repair 5 LF $ 15.00 $ 75.00 $ 100.00 $ 500.00 29 Permanent Asphalt Street Pavement Repair 65 LF $ 75.00 $ 4,875.00 $ 80.00 $ 5,200.00 30 Permanent Concrete Steet Pavement Repair(Residential) 10 LF $ 60.00 $ 600.00 $ 143.00 $ 1,430.00 31 Construct Concrete Street Pavement,High Early Strength(Residential) 20 CY $ 250.00 $ 5,000.00 $ 280.00 $ 5,600.00 32 Concrete Curb&Gutter Repair 40 LF $ 25.00 $ 1,000.00 $ 34.00 $ 1,360.00 33 Permanent Concrete D/W Pavement Repair(Residential) 165 LF $ 55.00 $ 9,075.00 $ 82.00 $ 13,530.00 34 4"Thick Top Soil in Disturbed Areas 84 CY $ 15.00 $ 1,260.00 $ 40.00 $ 3,360.00 35Solid Sod for Disturbed Areas 750 SY $ 5.00 $ 3,750.00 $ 6.00 $ 4,500.00 36 Remove,Salvage,Repair,Reinstall or Replace Post Mounted Mailbox 8 EA $ 500.00 $ 4,000.00 $ 50.00 $ 400.00 37 lRemove,Salvage,Repair,Reinstall or Replace Repair Brick Mailbox 3 EA $ 75.00 $ 225.00 $ 25.00 $ 75.00 38 lRemove,Salvage,Repair,Reinstall or Replace Existing Planter Bed Per Lot 3 1 EA $ 300.00 $ 900.00 $ 170.00 $ 510.00 Contingency 9.1% $ 19,134.00 Sanitary Sewer In proven ents Sub-Total $ 210,000.00 $ 245,672.00 Sht C3:N.Carroll Ave.,&E.Highland SL Sanitary Sewerimprovements(2,070 LF) 39 Project Sign(To Be Moved To Multiple Locations) 2 1 EA $ 400.00 $ 800.00 $ 1,500.00 $ 3,000.00 40 Implement and Maintain Erosion Control Measures 1 LS $ 5,000.00 $ 5,000.00 $11,150.00 $ 11,150.00 41 Implement and Maintain Traffic Control 1 LS $ 7,500.00 $ 7,500.00 $ 4,200.00 $ 4,200.00 Portable Changeable Message Sign that is Trailer Mounted w/a Power Supply 42 (Ver-Mac PCMS-1210 or Approved Equivalent) 3 MO $ 400.00 $ 1,200.00 $ 1,800.00 $ 5,400.00 43 Misc Utility Adjustments(Including Sprinklers) 1 LS $ 5,000.00 $ 5,000.00 $10,000.00 $ 10,000.00 44 Demolish,Remove,&Dispose Existing SSMH 1 EA $ 500.00 $ 500.00 $ 2,000.00 $ 2,000.00 45 Abandon SS&Fill w/C.L.S.M. 190 LF $ 5.00 $ 950.00 $ 10.00 $ 1,900.00 Abandon SSMH:Remove Rim,Cover,&Top Cone Section.Fill w/C.L.S.M. 46 JProvide Permanent Pavement Repair 1 1 EA $ 750.001$ 750.00 $ 3,150.001$ 3,150.00 47 Sawcut,Demolish,Remove,&Dispose Ex Cone Sidewalk Pvmt 75 LF $ 2.00 $ 150.00 $ 30.00 $ 2,250.00 48 8"PVC SDR-35 SS Pipe By Open Trench 360 LF $ 40.00 $ 14,400.00 $ 60.00 $ 21,600.00 49 8"PVC SDR-26 SS Pipe By Open Trench 975 LF $ 44.00 $ 42,900.00 $ 100.00 $ 97,500.00 50 Jack/Bore 8"Certa-Flo Greenline SDR 21 PVC SS Pipe or Approved Equal 735 LF $ 175.00 $ 128,625.00 $ 255.00 $ 187,425.00 51 Construct Clay Dam 2 EA $ 300.00 $ 600.00 $ 1,700.00 $ 3,400.00 52 6"SS Service Connection to SSMH 1 EA $ 500.00 $ 500.00 $ 2,000.00 $ 2,000.00 53 4"SS Service Connection to Main 11 EA $ 400.00 $ 4,400.00 $ 400.00 $ 4,400.00 Jack/Bore 4"Certa-Flo Greenline SDR 21 PVC SS Service Pipe or Approved 54 JEqual(Long Services) 415 LF 1$ 125.00 $ 51,875.00 $ 75.001$ 31,125.00 55 4"SDR 35 PVC SS Service Pipe By Open Trench(Short Services) 100 LF $ 30.00 $ 3,000.00 $ 30.00 $ 3,000.00 56 6"SDR 35 PVC SS Service Pipe By Open Trench(Short Service) 30 LF $ 32.00 $ 960.00 $ 35.00 $ 1,050.00 57 Trench Excavation Safety for Sewer Line Depth>5' 1,465 LF $ 2.00 $ 2,930.00 $ 12.00 $ 17,580.00 58 Install/Construct SSCO at R.O.W.Line 12 EA $ 200.00 $ 2,400.00 $ 230.00 $ 2,760.00 59 4"SDR 35 PVC Private Plumbing 550 LF $ 20.00 $ 11,000.00 $ 25.00 $ 13,750.00 60 Install/Construct Private SSCO 6 EA $ 200.00 $ 1,200.00 $ 350.00 $ 2,100.00 61 Install/Construct Public 4'Dia.SSMH(8'Deep) 3 EA $ 4,000.00 $ 12,000.00 $ 4,840.00 $ 14,520.00 62 Install/Construct Extra Depth for4'Dia.SSMH 3.2 VF $ 250.001$ 800.00 $ 220.00 $ 704.00 63 Install/Cons tmct Public 5'Dia.SSMH(10'Deep) 2 EA $ 6,500.001$ 13,000.001$ 6,700.001$ 13,400.00 64 Install/Construct Public 5'Dia.Drop SSMH(10'Deep) 2 EA $ 7,500.00 $ 15,000.00 $ 6,200.00 $ 12,400.00 65 Install/Construct Extra Depth for 5'Dia.SSMH 16.1 VF $ 300.00 $ 4,830.00 $ 220.00 $ 3,542.00 66 Install/Construct Concrete Collar for SSMH 7 EA $ 250.00 1$ 1,750.001$ 1,000.00 1$ 7,000.00 67 Conduct Post Construction Television Inspection 2070 LF $ 2.00 1$ 4,140.001$ 2.00 1$ 4,140.00 BID TAB_Southlake SS Improvemen[s_5-17-16.,Ia Page 1 of 3 BHB No.2014.724.000 BHB Engineering Surveying 5/18/2016 4550 S.H.360,Suite 180 Grapevine,TX 76051 Tel(817)251-8550,Fax(817)251-8810 BID TABULATION Sanitary Sewer System Improvements at Summerplace Ln./N.Carroll Ave.&E.Highland St./ Market Loop&Commerce St./N.Carroll Ave.&Casey Ct. Storm Drain Improvements at Summerplace Ln. City of Southlake,Texas 5/18/2016 BHB Engineers Estimate Wilson Contractor Services,LLC Shaded Quantities&Totals=Correction to Submitted Bid Provided Bid Bond Yes Item no. Item Description Quantity Unit Unit Cost Amount Unit Cost Amount 68 Conduct SSMH Vacuum or Exfiltration Test 7 EA $ 250.00 $ 1,750.00 $ 300.00 $ 2,100.00 69 Conduct SS Line Vacuum or Exfiltration Test 2070 LF $ 1.00 $ 2,070.00 $ 2.00 $ 4,140.00 70 4"Cone Sidewalk Pavement Repair 75 LF $ 5.00 $ 375.00 $ 10.00 $ 750.00 71 Permanent Asphalt Street Pavement Repair 995 LF $ 75.00 $ 74,625.00 $ 80.00 $ 79,600.00 72 4"Thick Top Soil in Disturbed Areas 130 CY $ 15.00 $ 1,950.00 $ 40.00 $ 5,200.00 73 Solid Sod for Disturbed Areas 1170 SY $ 4.00 $ 4,680.00 $ 6.00 $ 7,020.00 74 lRemove,Salvage,Repair,Reinstall or Replace Existing School Zone Sign1 EA $ 4,000.00 $ 4,000.00 $ 1,000.00 $ 1,000.00 Contingency 9.02% $ 42,390 Sanitary Sewer Improvements Sub-Total $ 470,0001 $ 586,256.00 Sht C4:Market Loop&Commerce St Sanitary Sewerimprovements-(2,280 LF) 75 Implement and Maintain Erosion Control Measures 1 LS $ 3,000.00 $ 3,000.00 $ 5,400.00 $ 5,400.00 76 Implement and Maintain Traffic Control 1 LS $ 2,000.00 $ 2,000.00 $ 4,200.00 $ 4,200.00 77 Misc Utility Adjustments(Including Sprinklers) 1 LS $20,000.00 $ 20,000.00 $ 500.00 $ 500.00 78 Abandon 6"SS&Fill w/C.L.S.M. 1,280 LF $ 5.00 $ 6,400.00 $ 10.00 $ 12,800.00 79 Conduct Pre Construction Television Inspection 2,190 LF $ 2.00 $ 4,380.00 $ 2.00 $ 4,380.00 80 Demolish,Remove,&Dispose Existing SSMH 5 EA $ 500.00 $ 2,500.00 $ 2,000.00 $ 10,000.00 81 Sawcut,Demolish,Remove,&Dispose Ex Cone Pvmt(Including Integral Curb) 550 LF 1$ 12.00 $ 6,600.00 $ 30.00 $ 16,500.00 82 8"PVC SDR-35 SS Pipe By Open Trench 210 LF $ 40.00 $ 8,400.00 $ 70.001$ 14,700.00 83 8"PVC SDR-26 SS Pipe By Open Trench 820 LF $ 44.00 $ 36,080.00 $ 330.00 $ 270,600.00 84 Jack/Bore 8"Certa-Flo Greenline SDR 21 PVC SS Pipe or Approved Equal 1,247 LF $ 175.00 $ 218,225.00 $ 255.00 $ 317,985.00 85 4"SS Service Connection to Main 15 EA $ 400.00 $ 6,000.00 $ 400.00 $ 6,000.00 Jack/Bore 4"Certa-Flo Greenline SDR 21 PVC SS Service Pipe or Approved 86 Equal(Long Services) 367 LF $ 125.00 $ 45,875.00 $ 70.00 $ 25,690.00 87 4"SDR 35 PVC SS Service Pipe By Open Trench(Short Services) 39 LF $ 25.00 $ 975.00 $ 30.00 $ 1,170.00 88 4"Private Plumbing Connection for Jacked/Bored Services 70 LF $ 20.00 $ 1,400.00 $ 30.00 $ 2,100.00 89 Trench Excavation Safety for Sewer Line Depth>5' 1,069 LF 1$ 2.00 $ 2,138.00 $ 7.00 $ 7,483.00 90 1 Install/Construct SSCO at R.O.W.Line 15 EA $ 200.00 $ 3,000.00 $ 230.001$ 3,450.00 91 Install/Constmct4'Dia.SSMH(4'Deep) 3 EA $ 3,000.00 $ 9,000.00 $ 3,675.00 $ 11,025.00 92 Install/Construct Extra Depth for4'Dia.SSMH 7.1 VF $ 250.00 $ 1,775.00 $ 220.00 $ 1,562.00 93 Install/Construct 5'Dia.SSMH(10'Deep) 6 EA $ 6,500.00 $ 39,000.00 $ 6,200.00 $ 37,200.00 94 Install/Construct Public 5'Dia.Drop SSMH(10'Deep) 2 EA $ 7,500.00 $ 15,000.00 $ 6,700.00 $ 13,400.00 95 Install/Construct Extra Depth for 5'Dia.SSMH 21.1 VF $ 300.00 $ 6,330.00 $ 220.00 $ 4,642.00 96 Install/Construct Concrete Collar for SSMH 9 EA $ 250.00 $ 2,250.00 $ 1,000.00 $ 9,000.00 97 Conduct Post Construction Television Inspection 2,277 LF $ 2.00 $ 4,554.00 $ 2.00 $ 4,554.00 98 Conduct SSMH Vacuum or Exfiltration Test 11 EA 1$ 250.00 $ 2,750.00 $ 300.00 $ 3,300.00 99 lConduct SS Line Vacuum or Exfiltration Test 2,277 LF $ 1.00 $ 2,277.00 $ 2.00 1$ 4,554.00 100 Permanent Cone DNV Pavement Repair(Industrial) 71 LF $ 65.00 $ 4,615.00 $ 82.001$ 5,822.00 101 Permanent Cone Street Pavement Repair(Industrial) 480 LF $ 70.00 $ 33,600.00 $ 143.00 $ 68,640.00 102 Construct Concrete Street Pavement,High Early Strength(Industrial) 20 CY $ 250.00 $ 5,000.00 $ 280.00 $ 5,600.00 103 4"Thick Top Soil in Disturbed Areas 73 CY $ 15.00 $ 1,095.00 $ 40.00 $ 2,920.00 104 Solid Sod for Disturbed Areas 431 SY $ 5.00 $ 2,155.00 $ 6.00 $ 2,586.00 105 Hydromulch Seeding 222 SY $ 2.00 $ 444.00 $ 2.00 $ 444.00 106 Remove,Salvage,Repair,Reinstall or Replace Chain Link Fence 15 LF $ 20.00 $ 300.00 $ 30.00 $ 450.00 107 Remove,Salvage,Repair,Reinstall or Replace Post Mounted Sign 1 1 EA 1$ 250.001$ 250.00 $ 50.00 $ 50.00 Contingency 9.1% $ 49,632.00 Sanitary Sewer Improvements Sub-Total $ 547,000.00 $ 878,707.00 Sht C5:N.Carroll Ave.&Casey Ct Sanitary SewerImprovements-(180 LF) 108 Implement and Maintain Erosion Control Measures 1 1 LS $ 1,500.00 $ 1,500.00 $ 500.00 $ 500.00 109 Implement and Maintain Traffic Control 1 LS $ 2,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00 110 Misc Utility Adjustments(Including Sprinklers) 1 LS $ 1,000.00 $ 1,000.00 $10,000.00 $ 10,000.00 111 Demolish,Remove,&Dispose Existing SSMH 1 EA $ 500.00 $ 500.00 $ 2,000.00 $ 2,000.00 112 8"PVC SDR-26 SS Pipe By Open Trench 28 LF $ 44.00 $ 1,232.00 $ 160.00 $ 4,480.00 Dry Auger Bore 16"Steel Casing Pipe&Install 8"Certa-Flo Greenline SDR 26 113 PVC SS Pipe or Approved Equal 149 LF $ 275.00 $ 40,975.00 $ 495.00 $ 73,755.00 114 Trench Excavation Safety for Sewer Line Depth>5' 28 LF $ 2.00 $ 56.00 $ 50.00 $ 1,400.00 115 Install/Construct Public 5'Dia.SSMH(10'Deep) 1 EA $ 6,500.001$ 6,500.00 $ 6,200.001$ 6,200.00 116 Install/Construct Public 5'Dia.Drop SSMH(10'Deep) 1 EA $ 7,500.00 $ 7,500.00 $ 6,200.00 $ 6,200.00 117 Install/Construct Extra Depth for 5'Dia.SSMH 4.5 VF $ 300.00 $ 1,350.00 $ 220.00 $ 990.00 118 Install/Construct Concrete Collar for SSMH 2 EA $ 250.00 $ 500.00 $ 1,000.00 $ 2,000.00 119 Conduct Post Construction Television Inspection 177 LF $ 2.00 $ 354.00 $ 2.00 $ 354.00 120 Conduct SSMH Vacuum or Exfiltration Test 2 EA $ 250.00 $ 500.00 $ 300.00 $ 600.00 121 Conduct SS Line Vacuum or Exfiltration Test 177 LF $ 1.00 $ 177.00 $ 2.00 $ 354.00 122 Permanent Asphalt Street Pavement Repair 20 LF $ 75.00 $ 1,500.00 $ 80.00 $ 1,600.00 123 4"Thick Top Soil in Disturbed Areas 1 CY $ 15.00 $ 15.00 $ 40.00 $ 40.00 124 Solid Sod for Disturbed Areas 9 SY $ 5.00 $ 45.00 $ 6.00 $ 54.00 Contingency 8.7% $ 6,296.00 Sanitary Sewer Improvements Sub-Total $ 72,000.001 $ 112,527.00 Summerplace Ln.Storm Drain Improvements(225 LF) 125 Implement and Maintain Erosion Control Measures 1 LS $ 1,500.00 $ 1,500.00 $ 3,000.00 $ 3,000.00 126 Implement and Maintain Traffic Control 1 LS $ 2,000.00 $ 2,000.00 $ 4,200.00 4 $ ,200.00 127 Sawcut,Demolish,Remove,&Dispose Ex Cone Curb&Gutter 40 LF $ 5.00 $ 200.00 $ 20.00 $ 800.00 128 Misc Utility Adjustments(Including Sprinklers) 1 LS $ 2,000.00 1$ 2,000.00 $10,000.00 1$ 10,000.00 129 Demolish,Remove,&Dispose Existing Grate Inlets 2 EA $ 500.00 $ 1,000.00 $ 1,000.001$ 2,000.00 BID TAB_Southlake SS lmprovements_5-17-16.,Ia Page 2 m 3 BHB No.2014.724.000 BHB Engineering Surveying 5/18/2016 4550 S.H.360,Suite 180 Grapevine,TX 76051 Tel(817)251-8550,Fax(817)251-8810 BID TABULATION Sanitary Sewer System Improvements at Summerplace Ln./N.Carroll Ave.&E.Highland St./ Market Loop&Commerce St./N.Carroll Ave.&Casey Ct. Storm Drain Improvements at Summerplace Ln. City of Southlake,Texas 5/18/2016 BHB Engineers Estimate Wilson Contractor Services,LLC Shaded Quantities&Totals=Correction to Submitted Bid Provided Bid Bond Yes Item no. Item Description Quantity Unit Unit Cost Amount Unit Cost Amount 130 Demolish,Remove,&Dispose Concrete Flume 275 SF $ 2.00 $ 550.00 $ 10.00 $ 2,750.00 131 Demolish,Remove,&Dispose Existing 30"SD 225 LF $ 20.00 $ 4,500.00 $ 15.00 $ 3,375.00 132 Lower6"DIP Water Line Below Storm Drain 30 LF $ 150.00 $ 4,500.00 $ 160.00 $ 4,800.00 133 Install 36-inch Reinf.Cone.Pipe(Class III) 180 LF $ 120.00 $ 21,600.00 $ 140.00 $ 25,200.00 134 Install 30-inch Reinf.Cone.Pipe(Class IV) 43 LF $ 110.00 $ 4,730.00 $ 100.00 $ 4,300.00 135 Construct 30-inch SD Cone.Collar 1 EA $ 300.00 $ 300.00 $ 1,000.00 $ 1,000.00 136 lConstruct 10'Curb Inlets 2 1 EA $ 2,750.001$ 5,500.00 $ 2,240.001$ 4,480.00 137 Construct Concrete Sloped Headwall(3:1)for36"RCP 1 EA $ 3,000.00 $ 3,000.00 $ 3,900.00 $ 3,900.00 138 Construct 12"Thick Gabion Mattress w/Perimeter Concrete Footing 54 SY $ 140.00 $ 7,560.00 $ 480.00 $ 25,920.00 139 Erosion Control Blanket(Cudex I CL Single Net or Approved Equal) 130 SY $ 10.00 $ 1,300.00 $ 7.00 $ 910.00 140 Concrete Curb&Gutter Repair 40 LF $ 25.00 $ 1,000.00 $ 15.00 $ 600.00 141 Permanent Asphalt Street Pavement Repair 60 LF $ 50.00 $ 3,000.00 $ 80.00 $ 4,800.00 142 Proposed Grading Per Sheet C2.4 1 LS $ 7,500.00 $ 7,500.00 $ 5,000.00 $ 5,000.00 143 4"Thick Top Soil in Disturbed Areas 50 CY $ 15.00 $ 750.00 $ 40.00 $ 2,000.00 144 Solid Sod for Disturbed Areas 450 SY $ 5.00 $ 2,250.00 $ 6.00 $ 2,700.00 Contingencyl 8.85°h $ 7,260.00 Storm Drain Improvements Sub-Total $ 82,000.00 $ 111,735.00 Sanitary Sewer System Improvements Total $ 1,299,000.00 $ 1,823,162.00 CONSTRUCTION TOTAL $ 1,381,000.00 $ 1,934,897.00 BID TAB_Southlake SS lmprovements_5-17-16.,Ia Page 3 of 3